PROJECT : 4-STOREY APARTMENT W/ ROOF DECK

LOCATION : Cristobal St. Brgy. Kaunlaran, Cubao, Quezon City


OWNER : Mr. Manuel Rodil 321 Holdings Incorporated
SUBJECT : FORM OF BILL OF QUANTITIES

Activity Name

Structural Works
Excavation To Foundation
Gravel Bedding to Foundation
Formworks to Foundation
Installation of Rebars to Foundation
Concreting of Foundation
Stripping of Formworks to Foundation
Installation of Rebars pedestal
Installation of Formworks of Pedestal
Installation of formworks of Tie Beam
Installation of Rebars of Tie Beam
Stripping of Formworks to pedestal & Tie Beam
Instalaltion of Anchor Bolt
Concreting of Tie Beam & Pedestal
Backfilling and compaction
Erection of steel column (elev.6.0m)
Installation of steel beam of Second Floor
Instalaltion of Rebars of slab
Concreting of slab (Ground)
Installation of steel deck (2nd Floor)
Installation of Steel Shear Studs (2nd floor)
Installation of Rebars of slab (2nd Floor)
Installataion of Steel Column (elev. 6.0m to 12.0m)
Formworks of RC Wall (Elev. 3.325m)
Installation of rebar of RC Wall (Elev. 3.325m)
Conreting of RC wall (Elev. 3.325m)
Concreting of slab (2nd Floor)
CHB Laying (elev. 3.325m)
Installation of rebars of stair
Installation of formworks of stair
Concreting of stair (Ground - Second)
Installation of steel deck (3rd Floor)
Installation of Steel Shear Studs (3rd floor)
Installation of Rebars of slab (3rd Floor)
Formworks of RC Wall (Elev. 3.325m - 6.650m)
Installation of rebars of RC Wall (Elev. 3.325m - 6.650m)
Conreting of RC wall (Elev. 3.325m- 6.650)
Concreting of Slab (3rd Floor)
CHB Laying (elev. 3.325m - 6.650m)
Installation of rebars of stair
Installation of formworks of stair
Concreting of stair ( 2nd - 3rd floor)
Installation of steel deck (4th Floor)
Installation of Steel Shear Studs (4th floor)
Installation of Rebars of slab (4th Floor)
Installation of steel Columns (elev. 12.00m - 13.30m)
Formworks of RC Wall (Elev. 6.650 - 9.975m)
Installation of rebar of RC Wall (Elev. 6.650-9.975m)
Conreting of RC wall (Elev.6.650-9.975)
Concreting of Slab (4th Floor)
CHB Laying (elev. 6.650-9.975m)
Installation of formworks of stair (3rd - 4th)
Instalaltion of rebars of stair (3rd - 4th)
Concreting of stair (3rd - 4th)
Installation of steel deck (Roof Deck)
Installation of Steel Shear Studs (Roof Deck)
Installation of Rebars of slab (Roof Deck)
Formworks of RC Wall (Elev. 9.975m - 13.30m)
Installation of rebar of RC Wall (Elev. 9.975m - 13.30m)
Conreting of RC wall (Elev. 9.975m - 13.30m)
Concreting of Slab (Roof Deck)
CHB Laying (Elev. 9.975m - 13.30m)
Installation of formworks of stair (4th - roof)
Installation of rebars of stair (4th - roof)
Concreting of stair (4th - roof)
Installation of CHB (Roof)
Formworks of RC Wall (Elev. 13.30m - 16.10m)
Installation of rebar of RC Wall (Elev. 13.30m - 16.10m)
Concreting of RC wall (Elev. 13.30m - 16.10m)
Quezon City

Duration Date Start Date Finish

10 14-May-18 24-May-18
1 25-May-18 26-May-18
2 26-May-18 28-May-18
2 28-May-18 30-May-18
1 30-May-18 31-May-18
1 31-May-18 1-Jun-18
2 1-Jun-18 3-Jun-18
1 3-Jun-18 4-Jun-18
3 4-Jun-18 7-Jun-18
2 7-Jun-18 9-Jun-18
3 9-Jun-18 12-Jun-18
1 12-Jun-18 13-Jun-18
1 13-Jun-18 14-Jun-18
7 14-Jun-18 21-Jun-18
1 21-Jun-18 22-Jun-18
1 22-Jun-18 23-Jun-18
1 23-Jun-18 24-Jun-18
1 24-Jun-18 25-Jun-18
3 25-Jun-18 28-Jun-18
1 28-Jun-18 29-Jun-18
1 29-Jun-18 30-Jun-18
1 30-Jun-18 1-Jul-18
1 1-Jul-18 2-Jul-18
6 2-Jul-18 8-Jul-18
6 8-Jul-18 14-Jul-18
2 14-Jul-18 16-Jul-18
3 16-Jul-18 19-Jul-18
1 19-Jul-18 20-Jul-18
2 20-Jul-18 22-Jul-18
1 22-Jul-18 23-Jul-18
6 23-Jul-18 29-Jul-18
1 29-Jul-18 30-Jul-18
1 30-Jul-18 31-Jul-18
1 31-Jul-18 1-Aug-18
6 1-Aug-18 7-Aug-18
6 7-Aug-18 13-Aug-18
2 13-Aug-18 15-Aug-18
3 15-Aug-18 18-Aug-18
1 18-Aug-18 19-Aug-18
2 19-Aug-18 21-Aug-18
1 21-Aug-18 22-Aug-18
6 22-Aug-18 28-Aug-18
1 28-Aug-18 29-Aug-18
1 29-Aug-18 30-Aug-18
1 30-Aug-18 31-Aug-18
1 31-Aug-18 1-Sep-18
6 1-Sep-18 7-Sep-18
6 7-Sep-18 13-Sep-18
2 13-Sep-18 15-Sep-18
3 15-Sep-18 18-Sep-18
1 18-Sep-18 19-Sep-18
2 19-Sep-18 21-Sep-18
1 21-Sep-18 22-Sep-18
6 22-Sep-18 28-Sep-18
1 28-Sep-18 29-Sep-18
1 29-Sep-18 30-Sep-18
1 30-Sep-18 1-Oct-18
6 1-Oct-18 7-Oct-18
6 7-Oct-18 13-Oct-18
2 13-Oct-18 15-Oct-18
3 15-Oct-18 18-Oct-18
1 18-Oct-18 19-Oct-18
2 19-Oct-18 21-Oct-18
1 21-Oct-18 22-Oct-18
1 22-Oct-18 23-Oct-18
1 23-Oct-18 24-Oct-18
6 24-Oct-18 30-Oct-18
6 30-Oct-18 5-Nov-18
Summary of Punchlist

DESCRIPTION Date Start Date Finish


Comfort Room (Male)
flood testing certificate
door closer to be rectify
low flush in urinal
clogged slope sink
missing screw of floor drain
cleaning of all floor drain
weak pressure of fauset
rectification of uneven ceiling
buffing of counter top
proper cleaning
weak pressure of fauset

Comfort Room (Female)


clogged slope sink
missing screw of floor drain
weak pressure of fauset
cleaning of all floor drain
permanent stain at lavatory; for replacement
rectification of sealant in lavaratory
flood testing certificate
proper cleaning

Comfort Room (PWD)


lavaratory for clean
emergency lights not functioning
replacemet of mirror
installation of tile
cleaning of all floor drain
Remarks

Hspow and Arknet


Hspow
American standard
Greenmaster
Greenmaster
Greenmaster
Greenmaster
Hspow
Hspow
Hspow
Hspow

Greenmaster
Greenmaster
Greenmaster
Greenmaster
Hspow
Hspow
Hspow and Arknet
Hspow

hspow
supplier
hspow
hspow
Greenmaster
Summary of Punchlist

DESCRIPTION Date Start


Materials
Lifting Chain for grease tank
Gate Valve for element
replacement of water meter @ Cluster 3
replacement of toilet mirror
threshold/stair nosing of all comport room
not yet open of all floor cleanout
1 remaining glass canopy of cluster 1
Sealant of all canopies
punchlish of Tiles

Manhole cover of elements


Date Finish Remarks

Procurement
Procurement
Greenmaster
Procurement
Procurement
Greenmaster
Procurement
Supplier/Procurement
NIRO

Hspow
Summary of Punchlist

DESCRIPTION Date Start Date Finish


CLUSTER 1
Painting of Canopy
Rectification of Tiling Works
Broom Finish to be Rectified
Removal of Unwanted Objects at Canopies
Manhole not Yet open
Exposed wire to be properly align
Rectify of Grout
completed plumbing works
Rectification of exposed wires/conceal exposed wires
Rectification of rusted stainless steel
Rectification of uneven wall finish
All clean-out to be open by Green master
Remarks

GreenMaster