Beruflich Dokumente
Kultur Dokumente
SAFETY NOTE:
1. Ensure the safety shoes, glasses, gloves and ear plugs. For electrical tests, shoes used should not
have any metal protection layer.
2. Ensure that any personal protective equipments were worn correctly and same is in good condition.
3. Ensure the tools and its settings are inspected and ensure the upgradation date.
4. Any equipment not meeting its manufacturers set criteria must not be used and is to be reported to the
maintenance department immediately.
5. Extension cords should have earthing and the running cable should be free of damages to avoid
electrical accidents.
6. Ensure Air supply pipes are appropriately lifted off the floor where possible to eliminate the possibility of
damages and accidents.
7. Ensure floor area is clear and clean during and after work process.
9. Hang DANGER labels over the chains on all four sides of dedicated testing area.
10. Ensure the time to time calibration of all the instruments and its maintenance to avoid
failure/accidents.
11. If any equipment, practice or environment is considered to be unsafe, see your Supervisor
without delay.
ENVIRONMENTAL NOTE
1. Environmental aspects are controlled by storing and using materials as per the relevant guidelines and
using engineering controls and/or personal protection equipment where appropriate.
2. Fluid leaks or spills must be cleaned up immediately the accident or incident occurs. Care must be
taken to ensure all items used in containing or cleaning of accident or incident are disposed of in the
correct manner, as stated in the relevant guidelines.
Items Observation
1.0 General
1.1 Check phase-phase and phase-earth clearances.
1.2 Check for damage.
1.3 Check all connections as per GA & SLD and check for for tightness.
1.4 Insulation Resistance on busbars (>100M) with 5000V/2500V Megger *
1.5 Micro-Ohmmeter test of all connections (if required to check the interconnections)
1.6 Power frequency HV test (10kV AC phase-earth) **
(* IR should be done before & After HV test)
(** HV should be done at 70% of 10kV, if already 100% voltage is applied during routine
test)
3.0 Cubicle
3.1 Capacitor bank name plate is fitted.
3.2 Clean equipment, wiping insulating parts clean with non-fraying cloth, remove any
grease or adhesive dirt.
3.3 Check for appropriate joining of modules.
3.4 Check doors and panels to ensure straight, square and function.
3.5 Paint finish no chips or scratches. (Touch-up paint supplied).
3.6 Correct and level positioning of cubicle(s). Anchor bolts fitted.
3.7 Check for name plate details & rating & Type.
PPHV – CAPACIOTRS 1
5.4 Check for name plate details & rating & Type.
4.2 Remove reactor packing timbers (if fitted for transportation).
12.0 Earthing
12.1 Earth cable fitted.
12.2 Continuity of earth conductor.
12.3 Check the Earth resistance
12.4 Check for equipment earthing (only capacitor as reactors are with resin cast insulator)
PPHV – CAPACIOTRS 2
13.0 Surge arrestors (if fitted)
13.1 Check mounting of SA. Check for damage.
13.2 Check for earth connections & tightness.
13.3 Surge Counter connection (if any)
13.4 Check for name plate details & rating & Type.
13.0 Protections
13.1 Check for Over current protection settings (Irss =110Amps)
13.2 Check for Earth fault settings.
13.3 Check for time settings.
13.4 Check for Over voltage settings (110%)
13.5 Check for Under voltage settings (90%).
14.0 Measurements
14.1 Check for AC Aux. voltage
14.2 Check for DC Aux. voltage.
14.3 Check for Ammeter & voltmeter & Mvar meter connections.
1) Check and confirm earth switches are in OFF positions (if any).
2) Close main ( bus ) isolator (if Any).
3) In control panel of circuit breaker, local/ remote switch should be in remote
position.
4) Ensure that closing spring of circuit breaker is in charged condition.
5) Check in control relay panel three phase bus supply voltage availability & under
voltage relay is reset or not.
6) Check that the master trip relay in control and Relay panel is in reset position.
7) Check for pre close trip circuit healthiness in both the Trip circuit supervision Relay
for RED LED glowing, which indicates healthiness of trip circuits.
8) Check whether there is sufficient load on the bus & make sure that the indication of
“BREAKER READY FOR CLOSING”.
9) After satisfying above conditions Close the circuit breaker.
10) After closing the breaker check for POST CLOSE Trip circuit supervision (if provided).
If the RED LED is not glowing TRIP the Circuit breaker Manually.
NOTE- NEVER CLOSE CIRCUIT BREAKER FROM CIRCUIT BREAKER PANEL (i.e. FROM
LOCAL), EXCEPT FOR MAINTENANCE JOB.
PPHV – CAPACIOTRS 3
SAFETY:
FOR UNITS DESIGNED TO IS 13925 - ISOLATE & EARTH SUPPLY. WAIT TEN
MINUTES. APPLY HAND EARTHS TO ALL CAPACITOR TERMINALS.
HV capacitors
These instructions apply to type CHD capacitors, supplied as standard with your APFC
System. The capacitors are impregnated with FARADOL 810.
Safety Regulations
When working with capacitor banks the following safety instructions in particular must be
observed.
Do not touch a capacitor bank until it has been completely discharged, short-circuited
and grounded. Also short-circuit the capacitor units individually. If there is an internal
fault, such as a damaged discharge resistor, there may still be a voltage even though
the capacitor bank has been discharged.
The capacitors have internal discharge resistors which, depending on the standard
used reduces the voltage of the unit as defined in the following table:
Avoid skin contact with the impregnation fluid in the event of leakage, and avoid
breathing in fumes or gases from the impregnation fluid. In the event of skin contact,
wash with soap and water. If fluid gets in your eyes, rinse with lukewarm water.
Installation – Mechanical
PPHV – CAPACIOTRS 4
Table 3 Structural Connections
Installation - Electrical
Field Power Wiring
When selecting the appropriate cable size due consideration should be given to possible
future extension of the equipment. Cables and isolating switchgear should be rated at 1.5
times the nominal capacitor current of the total capacitor bank and should always be
coordinated with the current rating of the systems protection level. Furthermore, there are
important installation requirements specified in local supply authority rules. In determining
the appropriate size of installation cabling the following are some of the parameters that
should be considered:
maximum output power of the PFC unit;
current carrying capacity of the system busbars;
fault rating of the system;
physical location of the installation relative to main switchboard.
Ensure correct phasing of cables from the main switchboard to the incoming connections
of the PFC System.
PPHV – CAPACIOTRS 5
STANDING (in General) INSTRUCTIONS
1) Whenever the breaker trips due to any fault the concerned relay will drop its flag
and simultaneous alarm and annunciator indication will come. The personnel in
charge of the installation shall silence the alarm and record all the control panel
indications as well as the time of tripping and corresponding load conditions.
Further action may be taken in consultation with a competent authority.
2) In the case of tripping due to unbalance relay the bank should be recharged only
after rectifying the cause of unbalance. If a capacitor unit has failed it is replaced
with another one of equal value. In no case the bank is to be operated
unbalanced. Any re arrangement of capacitor units to obtain new value of
capacitance involves extensive redesign calculations in ABB office not covered by
this contract.
4) If the earth fault / over current relay has operated look for possible short circuits or
grounding or check whether LA has operated. The bank may be charged after
rectifying the fault and meggering.
5) If an automatic power factor control relay is provided it should be put into service
only when sufficient load is there. Otherwise this will cause unnecessary hunting
of the bank, which will reduce the life of the breaker.
6) If DC failure occurs the personnel in charge of the system should manually trip the
breaker immediately as all the protection will be out of service.
7) If the re-close blocking timer is not working, the bank should not be put in auto
mode. Operating staff should consciously ensure that every re-closing should be
done after 5 minutes of discharge time only.
11) A separate fence may protect the entire capacitor bank installation and no
unauthorised persons must be allowed to touch the installations.
PPHV – CAPACIOTRS 6
12) Unlike some other equipment the capacitor retains its charge for definite time.
Therefore, before handling the units the entire bank is to be isolated by first
tripping the breaker and then by opening the isolator. Wait for 5 minutes before
touching a capacitor unit, always discharge, short and then ground it.
13) During servicing and maintenance of any equipment the nature and design of the
system is to be preserved. Any modification whatsoever must be done only in
consultation with a competent authority.
14) In case of any difficulty in operation or maintenance kindly contact the supplier for
assistance.
15) Competent authority may make changes in the operating instructions based on
their special studies without violating principles of safe operations within rated
capacities.
16) Users of the capacitor banks expecting power relief in tariff should bear in mind
that most of the tri-vectors increment the MVAh even when capacitive MVArh are
being drawn just as in case of inductive MVAr drawal. Capacitive MVArh may not
nullify the previous inductively incremented MVAh. This means operating
capacitor banks during net leading power factor conditions shall also attract poor
power factor penalty not withstanding the fact that the power factor shall be
leading during this period. This is because the power factor calculations are made
by utilities based on integrated monthly figures of MWh / MVAh. This aspect calls
upon judicious advice to be evolved by the competent authority of the consumer
after closely studying their own load profile, being made available to the operating
staff as regards switching off and on the banks. This is necessary to make best
commercial use of the banks.
PPHV – CAPACIOTRS 7
PPHV – Capacitors
ABB
INSTRUCTION MANUAL
FOR
INSTALLATION, OPERATION AND
MAINTENANCE
OF
H.V. SHUNT & SERIES CAPACITORS
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 1/41
1HYC416004_A
ABB
Table of contents
1) Introduction
2) Safety regulation
a. Explosion
b. Leakage
c. Safety equipment
3) Handling
a. Documents
b. Transport / unloading
i) Lifting device
ii) Unpacking
iii) Storage
4) Installation
a. Documents
b. Tightening torque
c. Support insulators
d. Module
e. Connection insulators and busbars
f. Capacitor unit
g. Connection cables
h. Connection of capacitor bank
i. Capacitor bank
5) Commissioning
i) Visual inspection
ii) Capacitance measurement
i) Voltage measurement
ii) Current measurement
iii) Unbalance current
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 2/41
1HYC416004_A
ABB
c. Checking operation data
i) Voltage
ii) Capacitor current
iii) Ambient temperature
iv) Unbalance voltage
v) Unbalance current
d. Special precaution
e. Maintenance
i) During operation
ii) Capacitance measurement
iii) Clearing
iv) Cracks
v) Leakage
vi) Painting damages
vii) Replacement of faulty capacitor units
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 3/41
1HYC416004_A
ABB
1. INTRODUCTION
This instruction is a guide for persons working with capacitors but does not
replace official regulations or any insurance company requirements relating to
the installation and operation of capacitors.
The capacitor banks are built up of single phase or 3 phase capacitor units to
form a composite capacitor bank of required rating and is supplied along with
the accessories like banking materials, structures, interconnection materials,
etc.. The capacitors of ABB are made of 100% polypropylene film impregnated
with non-PCB, non-toxic dielectric (FARADOL) and are provided with internal or
external fuses or are Fuseless and discharge resistors.
In case of internal fuse capacitor unit, if a particular element has failed the
respective fuse will blow and disconnect the element. However, this will not
affect the operation of the capacitor unit but will result in a slight reduction in the
capacitance value. In Case of Externally Fused Bank or Fuseless Bank, there
will be a slight change in the Capacitance value upon element failure.
2. SAFETY REGULATIONS
When working with capacitor banks, the following safety regulations must be
observed.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 4/41
1HYC416004_A
ABB
Do not touch a capacitor bank until it has been completely discharged,
short circuited and grounded. Short circuit the capacitor units individually.
In some special cases, primarily for test lab applications, the capacitor units do
not have discharge resistors. In these cases, special care must be taken. The
discharge circuit must include suitable resistance and the discharge tool must
have extra insulation to withstand full voltage.
a. Explosion
In extreme cases, a capacitor unit can fail with case rupture as a result. In
such cases, there can also be risk for oil leakage and perhaps even fi re.
b. Leakage
Upon capacitor unit leakage, avoid skin contact with the impregnation fluid.
In the event of skin contact, wash with soap and water. If fluid is splashed
into the eyes, rinse with lukewarm water and seek medical care. For
detailed information about the impregnation fluid, see the material safety
data sheet for the Faradol 810. For measures to be taken in the event of
leakage, see Section 5 (e) (v).
c. Safety equipment
3. HANDLING
a. Documents
· This manual
· Packing lists
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 5/41
1HYC416004_A
ABB
b. Transport/Unloading
i) Lifting devices
The nuts on the bushing studs shall be tightened with a torque of 20-
25 Nm approximately.
All transports to and from the substation must be conducted with the
material properly enclosed in its packaging.
Take care not to damage the paint of the units during installation.
Protect the sides of the units from scratches when they are pushed
into the rack. Touch up any paint damage that may occur.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 6/41
1HYC416004_A
ABB
ii) Unpacking
iii) Storage
4. INSTALLATION
a. Documents
b. Tightening torque
Nuts on the bushings with clamps for copper cables are torqued to 15–
20 Nm.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 7/41
1HYC416004_A
ABB
Other, galvanized, nuts/bolts (without lubricant):
c. Support Insulators
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 8/41
1HYC416004_A
ABB
The next step is to place the module at
its correct position according to the
assembly drawing. It is important to
place the rack on the insulators with
care since they can otherwise be
damaged. If there is more than one
rack per phase or if the three phases
are placed above one another, the first
rack must be tightened before
continuing with the next phase or rack.
If the insulators are heavy, they should
be lifted with a lifting device and
secured with bolts. If the insulators are
light, it can be easier to lift the module
and bolt the insulators in place from
beneath before the entire module with
the insulators is lifted into place.
d. Module
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 9/41
1HYC416004_A
ABB
When lifting the modules, use the lifting slings (see picture above) or lift
it in the rack.
If paint damage occurs during assembly then see section-VI (e) (vi)
Bushing on capacitor units may not be subjected to external pressure or
impact. Capacitors should not be lifted by bushings
e. Capacitor Unit
For tightening the nuts of the capacitor unit terminal, first fix both the parts of
terminal connector on the bushing stud, pass the interconnection wire through
the groove provided, place the plain washer, spring washer and then put a nut
on the top as shown in page no --.Then tighten the nut carefully without
exerting excessive force with the help of a Spanner.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 10/41
1HYC416004_A
ABB
f. Connection cables
Rack shorting
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 11/41
1HYC416004_A
ABB
The recommendation is that the switching equipment has an interlocking
system to prevent reconnection of the capacitor bank before it’s
discharged to less than 10% residual voltage.
i) Capacitor Bank
The capacitor banks either come as separate capacitor units, racks and
connecting parts or as complete modules and the units mounted in
racks. With a view of voltage distribution and balance, the units in a
capacitor bank must be installed in a given order.
The tolerance group of each unit is marked on the unit rating plate on
the right hand side. In case the unit has to be replaced, please ensure
that the new unit being replaced has the same tolerance or a tolerance
group near to the unit being replaced. This is to ensure a proper
balanced bank. For filter banks used for installation like HVDC, the new
unit being replaced should have a tolerance not more than one step
away from the unit being replaced.
5. COMMISSIONING
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 12/41
1HYC416004_A
ABB
a. Inspection prior to energization
i) Visual inspection
Check that modules are fitted at the correct positions according to the
assembly drawing.
Check that all internal connections are properly made, follow the current
path from the incoming terminal through the complete capacitor bank.
Check all air clearances within the capacitor bank. The following table
gives some minimum air clearance distances as per IEC 60071-2, 1996.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 13/41
1HYC416004_A
ABB
ii) Capacitance measurement
All capacitor units delivered from the factory has passed routine testing
as per applicable standard. Due to this, it’s not necessary to measure the
capacitance of all units in the capacitor bank prior to energization.
However, we still recommend to perform a capacitance measurement to
be performed on all units in the bank, because it gives the benefit of
having a reference value of the capacitance from a measurement with
own measuring equipment for future maintenance, and also the benefit
of maintenance staff having a chance to get familiar with the equipment.
For the capacitance measurement we recommend to use an ABB
Portable Capacitance meter CB2000 which allows to perform the
measurement without removing the interconnections between the
capacitor units.
Tightening torque
Check all tightening torques for the nut on the top of the bushing, as well
as all other electrical connections. The correct torques can be found in
Section 4 (b).
i) Voltage measurements
The purpose with the current measurement is to confirm that the current
do not exceed the design values for the equipment.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 14/41
1HYC416004_A
ABB
iii) Unbalance current
i) Voltage
Voltage before and after switching on the capacitor bank. The capacitor
must not be subjected to a continuous voltage exceeding 110% of the
nominal voltage for a period exceeding 12 hours in a period of 24 hours.
v) Unbalance Current
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 15/41
1HYC416004_A
ABB
d. Special Precautions
The voltage and current margins stated above are intended to allow
operation during temporary peaks. These margins should not be used
under normal service conditions.
Voltages and currents should, therefore be measured under all the load
situations that occur, in order to ensure that the capacitor bank is not
overloaded.
e. MAINTENANCE
In order to assure long life time and trouble free operation, periodical
inspection of the capacitors banks are suggested as listed below:
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 16/41
1HYC416004_A
ABB
i) During operation
For the capacitor banks with units having internal fuses, the unbalance
current value of upto 50% of the tripping value of the protection system
is acceptable. Failure of single element does not affect the service ability
of the capacitor bank or significantly reduce its service life.
If the unbalance current value exceeds 50% of the tripping value, the
capacitance of all the units in the bank shall be checked and those
whose values deviate by more than 10% from the original value must be
replaced.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 17/41
1HYC416004_A
ABB
iii) Cleaning
iv) Cracks
v) Leakage
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 18/41
1HYC416004_A
ABB
vii) Replacement of faulty capacitor unit
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 19/41
1HYC416004_A
ABB
g. Corrective Action After Relay Operation
i) Unbalanced protection
If the control and relay panel is supplied by ABB, refer the recommended
Relay Settings given in the Operation and Instruction manual. If the
control and relay panel is not in the scope of ABB, then the settings of
the relays shall be provided in such a way that:
Overloads specified in IEC 60871-1 are taken care of. The following
major relays are generally required for capacitor protection :
· overcurrent and earth fault
· under voltage
· over voltage
· unbalance relay
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 20/41
1HYC416004_A
ABB
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 21/41
1HYC416004_A
ABB
ANNEXURE – 1
Do’s and Don’ts for capacitor bank guide for commissioning engineer.
Introduction
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 22/41
1HYC416004_A
ABB
Following should be carefully taken care
Connections
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 23/41
1HYC416004_A
ABB
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 24/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no.
5 Reduction in clearance.
This can result bushing to
bushing flashover causing
severe damage to unit
and bank.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 25/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no.
Loose connection Hot
spot
8 No loose connection no
hot spot
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 26/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no.
9 Lack of rack shorting will
result floating potential
at rack and cause
abnormally high
overvoltage beyond the
design limit on capacitor
bushing and inter rack
insulator. This can result
failure of inter rack
insulator bushings and
severe damage to total
capacitor bank.
Do not Forget Rack shorting
Wrong
10 Rack shorting will
uniformly distribute the
voltage on inter rack
insulator and capacitor
bushing since rack has
fixed potential. This will
not allow the overvoltage
on unit and insulator
beyond the designed
limit
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 27/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no.
11 It can generate hotspot
due improper connection
between copper
conductor and terminal
connector
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 28/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no
.
13
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 29/41
1HYC416004_A
ABB
Kindly ensure tightness with skilled manpower under supervision of experienced
knowledgeable engineer
Clearances
Capacitor bank is made up of various component such as capacitor unit, busbar
support insulator, capacitor racks, inter rack insulators, bank support insulators,
aluminum flats, flexible conductor and GI support angles for supporting insulators.
Hence it is important to refer GA drawing and Schematic drawing bank detailed drawing
such as flat drawing angle drawing before assembling the capacitor bank. The erection
commissioning engineer should be trained to understand capacitor bank and
clearances. He should take advice of capacitor technical department while erection
and commissioning. Any mistake in assembly or connection can result violent failure of
capacitor unit and bank. The capacitor bank should be charged after technical
clearance of PPHV Capacitor technical department. Following clearances should be
checked
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 30/41
1HYC416004_A
ABB
Sr Dos Remark and
no. description
1 Capacitor unit
DO – Measure clearance between Current container is at different
carrying Aluminium flat and capacitor potential i.e. rack
Container. potential while
Aluminium flat is at
different potential.
Hence it is necessary
to check clearance
between Aluminium flat
busbar and container.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 31/41
1HYC416004_A
ABB
Sr Dos Remark and description
no.
3 DO – Measure clearance between Phase to phase clearance
phase to phase. especially capacitor bank when
RYB phases are vertically
installed are very important.
Phase to phase clearance
should be measured as follows.
Between R phase- Y phase
Between Y phase – B phase
ABB
Sr Dos Remark and description
no.
5 Unit bushing are connected to
DO – Measure clearance between incomer phase conductor by
flexible conductor for connection to flexible copper conductor. It is
unit to incomer phase and container necessary to check the
which is at rack potential clearance between the flexible e
copper conductor to container
which is at rack potential
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 33/41
1HYC416004_A
ABB
Sr Dos Remark and description
no.
7 In case of C filter where
DO – Measure clearance between Resister resistor is mounted on
and capacitor incomer and Unit to resister top of capacitor. Resister
interconnection and rack body capacitor incomer
and rack are at different
potential. Flexible
interconnection between
resister and capacitor
should have sufficient
clearances.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 34/41
1HYC416004_A
ABB
Sr Don’t or Dos Impact
no.
9 This can cause
flashover between two
bushing which may
lead to unit as well as
bank failure
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 35/41
1HYC416004_A
ABB
Protection
Overcurrent protection 1.2* bank current (calculated based on Installed bank voltage
and installed MVAR) K=0.1 IDMT
Earth fault – based on system and Current transformer rating.
Overvoltage- alarm-1.1* Rated system voltage at bus time – IDMT k=0.2
Trip 1.15 Rated system voltage at bus time- definite time =1 sec
Under voltage – Trip -0.8* Rated system voltage at bus. Time- 2 sec
Unbalance current- As per unbalance calculation sheet given by designer. Time
setting for trip is 100mS
During commissioning, unbalance current setting should be kept more sensitive
based on actual unbalance current. It is advisable to keep unbalance current to
1.5 to 2 times actual unbalance current for initial stabilisation period. This will help
to trip the capacitor bank very fast and avoid cascading effect.
It is advisable to keep some commissioning spares to avoid delay in
commissioning if one or two units failed during test charging.
Unbalance current – as per unbalance current calculation time IDTMT K=0.1
On time delay- capacitor breaker should be switched on only after discharge of
capacitor bank. This time delay is normally 600 sec or 300 sec depending on discharge
time specified for capacitor bank.
For SVC, HVDC projects, protection setting will be given separately by System
Engineer.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 36/41
1HYC416004_A
ABB
Pre commissioning checks
For big bank like SVC filter bank where no of units are more. The low voltage
measurement is advisable at site to check natural unbalance current.
This measurement is done at 400V (phase to phase voltage). This is possible at site
since 3 phase 400V is available at site.
Procedure- connect the 3 cables R/Y/B to incomer of bank. This measurement can be
done with reactor or without reactor.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 37/41
1HYC416004_A
ABB
Check this unbalance current is at least 50% less than trip current of unbalance
calculation of capacitor bank
If this unbalance current is more than 50% of trip current then kindly balance the bank
by swapping units based on individual unit capacitance phase capacitance group
capacitance. When unbalance current is less than 50% of trip current and all
clearances are ok and all units capacitance values are ok and insulation resistance of
all insulators are ok then bank can be charged and monitor the actual unbalance
current.
Monitor unbalance current for 12 hours (hourly unbalance current should be recorded)
If there is no abnormality the bank can be continue in service
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 38/41
1HYC416004_A
ABB
Low voltage measurement at site
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 39/41
1HYC416004_A
ABB
General information about insulation level and clearances
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 40/41
1HYC416004_A
ABB
This document must not be copied without our written permission, and the contents thereof must not be imparted to a third party nor be
used for any unauthorized purpose. ABB India Limited, Peenya, Bangalore – 560058, Karnataka, INDIA
Page : 41/41
*************************************
INSTALLATION OPERATION AND
MAINTENANCE INSTRUCTIONS
FOR DRY TYPE TRANSFORMERS
AND REACTORS.
***************************************
INSTALLATION,OPERATION AND MAINTENANCE INSTRUCTIONS
FOR DRY TYPE TRANSFORMERS/REACTORS.
6. CABLING: Cable trenches inside sub-station and switch station shall be filled with
stand,pebbles or completely covered with non-inflammable slabs.
7. DRYING TRANSFORMERS/REACTORS: If as a result of tests carried out
presence of moisture is indicated or the insulation resistance readings are not
satisfactory it is necessary to dry the transformer/reactor.
The transformers/reactors should never be left unattended during the drying periods.
It should be carefully watched through the drying process and all observations shall be
recorded. If the drying is improperly performed, great damage, may result to the
transformer/reactor insulation through overheating.
The handhole covers should be removed or raised slightly to allow moisture to escape.
All openings should be protected from weather. Drying should be continuous without
a break maintaining the temperature of the transformer at a specific value of say 80C
and a log sheet of the record should be maintained.
HALF YEARLY b) Bushing & arcing i) Clean off all dust,paint and other
(Before and after the horns. deposits.
rainy season) ii) Examine & replace the cracked
broken or chipped bushings.
iii) Examine & replace the damaged
gaskets.
iv) Adjust the arcing horns for
alignments and proper gaps
between rods.
YEARLY c) Barbed wires Recondition or replace barbed wire as
danger plate etc. necessary,paint & reprint the danger
plate,if defaced.
d) General condition. Clean off all dirt etc from the body of
the transformer/reactor & tighten all
bolts nuts etc.