Beruflich Dokumente
Kultur Dokumente
Suralaya PP in Indonesia
1,600MW/hr
Unit 1~4
1 Power Capacity
4Unit-@400MW/hr
Since 1983,1984,1989
Main Equipment
1 Boiler Bobcock & Wilcox
2
2 Turbine Mitsubishi
3 Generator Melco
Sub-Bituminous Coal
3 Coal Property AVR. 4,800 kcal/kg
(4,200~5,000)kcal/kg
Coal Total Moisture Over 40%
1 Inherent Moisture Over 25%
2 Surface Moisture Over 15%
4
6EA-@500 ton
6EA-@58 ton/hr
6EA-@43 ton/hr
Doosan
Doosan
Doosan
Bituminous Coal
AVR. 5,800 kcal/kg
5,600~6,000)kcal/kg
Less than 13%
Less than 10%
Less than 3%
AVR. 60~75%
Dry Season
50~70%
6EA-@500 ton
6EA-@58 ton/hr
6EA-@43 ton/hr
CV-08A/B
1200 ton/hr
1200 mm
200 m/sec
256m
300KW
6600V
Double Vibrating
1200 ton/hr
100*100 mm
40*40 mm
2750*7200 mm
850 CPM
8mm
20 degree
Motor-V Belt
25KW * 6P
460V* 60Hz