DEVELOPMENT OF PAF BASE BHOLARI Kashif Aslam & Associates

PAKISTAN (Pvt) Limited.

BHOLARI FLOOD PROTECTION SYSTEM - 2 BILL NO. 1.02 Bridge Structure FD-2 at Service Road

Bridge Structure FD-2 at Service Road Bridge (as per rates by Qavi Engineers) Qavi - Culvert

Unit Rate Unit Rate


Sch. Item Item No. Item Description Unit Qty Amount (RS) Qty Amount (RS)
(RS) (RS)

DIVISION 02 - SITE WORK

Bridge Structure FD-2 at Service Road


Excavation over areas upto 1.5m depth in foundation / to
obtain earth for filling under floors / areas etc., or for shafts,
wells exc. 30 sqm each, through earth clear of edges of
1 excavation within 10 m

a) Ordinary Soil
01-6 Cum 1,667 235.00 391,839 2,261 235.00 531,335

b) hard
01-7 Cum 596 235.00 139,943 808 235.00 189,763

c) Rock not requiring blasting.


01-8 Cum 119 2,355.00 280,481 162 2,355.00 380,333

2 Load Excavated Spoil as in Soil/Rock on Truck/Trolley or


1-17 any other Means carry upto 100m ,unload and stack or Cum 2,382 24.00 57,168 3,230 24.00 77,520
spread
3 Providing and laying of CC Type 'C' using crushed or
broken stone as in walls, partitions, slabs, sills, copings,
channels, steps, string courses, corbels, pier caps, hinge
3-8 stones, mantel pieces, louvers, chimney tops etc, but except Cum 35 8,920.00 309,078 61 8,920.00 544,120
jointing and pointing

4 Providing and laying reinforced cement concrete Type B


using crushed or broken stone in Foundation,independent
Column Footings,Solid Floor,etc incl from work as specified.
3-18 Reinforcement measured and paid separately Cum 320 10,320.00 3,302,400 585 10,320.00 6,037,200

5 Providing and laying reinforced cement concrete Type B


using crushed or broken stone in columns, beams, stairs,
posts, struts, piers, lintols, and the like requiring shuttering,
3-24 as specified. Reinforcement measured and paid separately Cum 98.00 12,200.00 1,195,600 0.00 12,200.00 0

6 Providing and laying reinforced cement concrete Type B


using crushed or broken stone in roof slabs, landings, walls,
plinth beams and bands etc as specified. Reinforcement
3-22 measured and paid separately Cum 95.00 13,660.00 1,297,700 136.00 13,660.00 1,857,760

7 Supply and fix bars round, using deformed bars grade - 60


including cutting, bending, binding and placing
9-56 reinforcement in position. Kg 76,950 136.00 10,465,200 108,150 136.00 14,708,400

8 Providing and Laying expansion joint of neoprene strip


N.S-TS-7 4"x1/4" and plastic bitumen m 56 2,000.00 112,000 0 2,000.00 0

9 Providing and placing Poly sulphide joint sealent. I" wide, 2"
N.S-TS-7 deep. Rm 56 1,100.00 61,600 0 1,100.00 0

10 Elastomeric Bearing Pads (According to Size and


N.S-TS-6 Thickness) - 14" x 9" x 3/4" No. 32 5,000.00 160,000 5,000.00 0

11 Bitumen coating to plastered or cement concrete surface :-


N.S-TS-4 6.35 kg per Sq.m Sqm 258 200.00 51,600 258 200.00 51,600

N.S 12 Providing and fixing rain water outlet of A.C. pipe:- 3" dia. No 48 1,970.00 94,560 48 1,970.00 94,560
PAKISTAN AIR FORCE

DEVELOPMENT OF PAF BASE BHOLARI Kashif Aslam & Associates

PAKISTAN (Pvt) Limited.

BHOLARI FLOOD PROTECTION SYSTEM - 2 BILL NO. 1.02 Bridge Structure FD-2 at Service Road

Bridge Structure FD-2 at Service Road Bridge (as per rates by Qavi Engineers) Qavi - Culvert

Unit Rate Unit Rate


Sch. Item Item No. Item Description Unit Qty Amount (RS) Qty Amount (RS)
(RS) (RS)

Providing and laying premix carpet 75mm thick, compacted


using cold emulsion and broken /crushed stone as specified
2-78 13 incl Tack coat. sqm 258 1,500.00 387,000 258 1,500.00 387,000

DISMANTLING
Dismantling of 1 Pipe Culvert with 3 pipes 0.91 m dia and
roadway dimension of 10m, cement concrete reinforced,
separating reinforcement from concrete, cleaning and
straightening and removal all kind of dismantling material
N.S-TS-5 14 from the site like concrete and excavation, complete in all P/C 1.00 25,000.00 25,000 1.00 25,000.00 25,000
respects and satisfaction of the site incharge.

Total Amount C/O to Summary 18,331,168 24,884,590