Beruflich Dokumente
Kultur Dokumente
This is graded homework. Include a problem statement with each problem. Put your name,
course number, and page number at the top of each page.
You have taken over as project manager for a light duty warehouse. A draft CPM schedule is
attached. All of the problems below refer to the draft CPM. Your company policy is to work a
normal 5 day, 40 hour per week schedule.
2. (9 points) The project will start on February 24th, 2010. Prepare a Project Date – Calendar
Date conversion chart for the entire project. A template is included on page 3 of this assignment.
The template file is also in <CON 4000 HW 05 Project – Calendar date correlation.xls> . For
parts b. and c. sketch a bar chart style schedule for the task on your Project – Calendar date
template. The “Mobilize” task is shown on the template as an example.
a. What is the calendar completion date of the project?
b. What is the earliest date that you can schedule a pressure test of the building fire
hydrants with the fire department?
c. What is the earliest date that you can schedule a test of the building fire sprinkler
system with the fire department?
3. (9 points) It is now Friday afternoon on March 19th. The owner just gave you a change order
to use a different style of windows and doors for the front entrance. Your window supplier
informed you that if you order today, the windows will arrive on the job March 31st by regular
freight.
a. What tasks does this change affect in your schedule?
b. The windows can be shipped by air freight and arrive March 26th. This will cost an
additional $900.00. Should you choose the air freight? Explain your answer.
c. Who should pay for the additional expense? Explain your answer.
CON 4000 HW 5 Warehouse
3 3
Irrigation Land
system scaping 3
Install
7 heaters
Water 3
lines Rough
Rough
3
plumbing 5
Fire
Fire
hydrants
sprinklers
2
Clear &
Clear & 3
Grub Rough 3
electrical Insulate
ext walls
2
2 3 8 5 4 Finish
Excavate
Excavate Form &
Form & Frame
Frame Frame
Frame
Mobilize 3 plumbing
ftg & slab pour slab ext walls roof
Roofing 6 3 1
Install Paint
3 Close out
drywall interior
Temp
Road 2
2 2
Temp
Frame Finish
power 4
interior electrical
Windows
& doors
4 3
Install Paint
siding exterior
ES D EF
3
Activity Pave
Pave
Road
LS F LF
SF FF IF
CON 4000 HW 05 Warehouse
Febrary March
Project Day 1 2
Calendar Day 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Mobilize
March April
Project Day 1
Calendar Day 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
April
Project Day
Calendar Day 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30