Doc. No. : 001/LOC-FI/TG/2011 Rev. 0


DATE 15-April-2011 Page 1/3
PREP'D NS
Jln. Raya Bekasi Timur KM. 17 Klender
Jakarta Timur, 13930 CHK'D HRD
Telp. 021-46835541 Fax. 021-46835542 APP'D YS
DESIGN MANUAL
FAN FIN COOLER FOR GAS TURBINE COOLING SYSTEM
MUARA TAWAR PROJECT

1. Purpose
This specification concerns the Lube Oil cooling by water circulation.
The purpose of the system is the cooling of the following elements :
 Generator bearings lubricating oil,

2. Description
2.1 Constitution
Lube Oil are cooled in paralel.
The off-base cooling system is mainly composed of :
 Fin fan cooler modules
 An atmospheric expansion tank
 All interconnecting piping, instrumentation and valves

2.2 Fin fan coolers modules


a). Mechanical equipment
Modules are installed in parallel and made of :
 fans (blades in aluminium)
 plenum and framework (mild steel)
 supporting frame
 air and water compact heat exchanger
Cooling fluid Water
3
Additive 35 l/m (Nalco 2000)
Total cooling water flow rate 154 m3/h
Total heat to be dissipated 297.22 kW

Heat exchanger outlet temperature 46 C


̊ for a max ambient air temperature of 37˘̊ C
Heat Transfer Coefficient 4.16 W/m².K
Reserve or fouling factor %
Type of draft Induced
Tubes material Copper, 12mmOD x 0.35mmThickness

REV DATE PAGE DESCRIPTION PREP’D CHK’D APP’D


0 13-April-2011 Issued for Bid Proposal NS HRD YS
Page 2 of 3

Fins type Plate


Fins material Aluminium Epoxy, 0.25mmThickness
Fin pitch 4 mm
Collectors material Copper
Bundles protection Epoxy-Coating
Acoustic pressure Maxi 82 dB(A) at 1 m

b). Electrical equipment


Fans are direct driven by electrical motors. In each module, fan motors divided into two
groups :
Block Module 1
Permanent 011 88FC1
012 88FC2
013 88FC3
Controll 2 FAN FC1-3

Motors Characteristic Value Unit


Power 15 KW
Number of motor 2 pcs
Voltage 400 VAC
Frequency 50 Hz
Speed 1000 Rpm
Anti-condensation heaters 1A-1B-1C TR Cn (n is the index of the 230 VAV
corresponding motor)
Fan Blade Characteristic, divided by 6 group ( 1 goup as stanby
unit)
Fan blade material Alumunium
Fan blade diameter 1240 Mm
Wind Flow per Impeller 2 x 30 m3/s
Total Wind Flow per Turbine 60 m3/s
Number of fan blade, 1(one group) as standby unit 2 Pcs

c). Instrumentation
 Temperature indicator 1A-1B-1C measures the water temp. at fin fan coolers inlet.
 Temperature indicator 1A-1B-1C measures the water temp. at fin fan coolers outlet.
 Pressure indicator 1A-1B-1C measures the water pressure at fin fan coolers inlet.
 Pressure indicator 1A-1B-1C measures the water pressure at fin fan coolers outlet.
 Resistance thermal detector 1A-1B- measures the fin fan coolers water outlet
temperature (type : PT100 – 3 wires).

REV DATE PAGE DESCRIPTION PREP’D CHK’D APP’D


0 13-April-2011 Issued for Bid Proposal NS HRD YS
Page 3 of 3

An alarm “High cooling water temperature” is displayed if fin fan coolers outlet water
temperature higher than 45 ̊ C.
An alarm “Cooling water temperature sensor is trouble” is displaied if water
temperature is below 20 C
̊ or above 80 C
̊ .
 Each module can be isolated with butterfly valves at the inlet 1A-1B-1C and at the outlet

2.3 Expansion Tank (Make Up Water Tank)


a). Mechanical equipment
The expansion tank is installed on the GT air inlet filter structure.
Expansion tank volume is designed to permit the coolant dilatation due to temperature
variation and ensures a minimal pressure in the circuit.
o Capacity : 0.9 m3
o Material : Mild steel

b). Instrumentation
 Level indicator 1A-1B-1C indicates the water level in the expansion tank
 The low level switch 1A-1B-1C send an alarm “ expansion tank low water level” on
The GT control panel if the level is under the low level.
Setting point : 200 mm under the centre line of the expansion tank.
3. Fluid
Water Quality and control : according to Gas Turbine Manufacturer specification
Additive : Nalco 2000 as anti-corrosion product for the first filling and the make-up.
Supplier : NALCO COMPANY, Indonesia

4. Reference documents
Performance Data Basis Data for Water Base Generator Cooler Design

REV DATE PAGE DESCRIPTION PREP’D CHK’D APP’D


0 13-April-2011 Issued for Bid Proposal NS HRD YS