Fixing Gabion – Labour & Material Cost


-
17 pieces ( 1m x 3m: Gabion ) x RM 180/pcs = RM 3,060
-
6m x 9m Hard core: RM x 77mt = RM 2,772
-
Hiring Labour – Fixing Gabion: RM100/pcs x 17 pcs = RM 1,700
-
Hiring Backhoe: RM 50/pcs x 17pcs = RM 850
RM 8,382

2. Foundation (1 Layer Hard core 6” x 9”) – 12” Thickness


-
50m (Length) x 2.4m (Width) x 0.3m (Thickness) = 36m3
-
36m3 / 8m3 (Trip) = ± 5 trips
-
5 trips x ± 18mt/trip = 90 mt
-
90 mt x RM 36/mt = RM 3,240

3. Laterite (1 Layer Laterite on top of Hard Core)


-
6” Thickness of laterite
-
50m (length) x 2.4m (width) x 0.183m (thickness: 6”) =± 22m3
-
22m3/3m3 per trip ( 6 tonne lorry) = ± 7 trips
-
± 7 trips x RM 40/trip = RM 280

4. Drain
-
Drain length = 170 ft @
-
V Shape Drain = 2 ft (length) x 1 ft (width)
-
170 ft/ 2 ft/mt = 85 units V shape drain

V Shape Drain Cost & Labour


-
V Shape Drain : RM 25/unit x 85 units = RM 2,125
-
Labour : RM 20/unit x 85 units = RM 1,750
-
Cost of Cement & Bricks : RM 10/unit x 85 units = RM 850
RM 4,725

5. Loading Soil – Transport & Hiring Machine


(Top up soil to original level – Land Slide Area)
-
RM 21/trip x 200 trip = RM 4,200

Total Cost :-
1. Gabion = RM 8,382
2. Foundation = RM 3,240
3. Laterite = RM 280
4. Drain = RM 4,725
5. Loading Soil = RM 4,200
RM 20,827 @ RM 21,000