LAUNCING GIRDER

Launching Bridge

Girder

L = 12,00 m L = 12,00 m L = 12,00 m


N = 18 N = 18 N = 18
LAUNCING GIRDER

Launching Bridge

L = 12,00 m L = 12,00 m
L = 12,00 m
N = 18 N = 18
N = 18
LAUNCING GIRDER

3
Launching Bridge

Girder
ASPHALT PAVEMENT

1. Spraying of Prime Coat by Asphalt Sparyer


2. Delivery and Dumping of Bituminous Base Course by Dump Truck to Asphalt Finisher
3. Spreading by Asphalt Finisher
4. First Compacting by Tandem Roller
5. Second Compacting by Pneumatic Tire Roller
6. Final rolling by Tandem Roller

Asphalt Finisher
Spraying of Prime Coat

Tandem Roller
Asphalt Finisher Tire Roller Tandem Roller

Bituminous Base Course


ASPHALT PAVEMENT

1. Spraying of Tack Coat by Asphalt Sparyer


2. Delivery and Dumping of Asphalt Concrete by Dump Truck to Asphalt Finisher
3. Spreading by Asphalt Finisher
4. First Compacting by Tandem Roller
5. Second Compacting by Pneumatic Tire Roller
6. Final rolling by Tandem Roller

Asphalt Finisher
Spraying of Tack Coat

Bituminous Base Course

Tandem Roller
Asphalt Finisher Tire Roller Tandem Roller

Asphalt Concrete
Bituminous Base Course
CAST IN PLACE CONC. PILE ø 800 mm

Reif. Bar

Dia. 800 mm

Reif. Bar

Reif. Bar

Dia. 800 mm
STRUCTURE WORK

Cast in place of Foundation of Abutment

Reinf. Bar

Dia. 800 mm

Dia. 800 mm
EARTH WORK
COMMON EXCAVATION / STRUCTURE EXCAVATION

Excavation

Excavator

Excavator

2 Soil Excavation
REINF. CONCRETE PIER
EARTH WORK
COMMON EMBANKMENT

1. Hauling of Common Embankment material to site by Dump Truck


2. Dumping of Common Embankment material
3. Spreading of Common Embankment material by Motor Grader
4. Compacting layer per layer by Vibro Roller, 15 cm thick per each layer

1 2

3 4