1 GENERAL:
1.1 DO#38: ‘Communication Strategy’
- Semasa Pembinaan ALL -Date proposed on 4/10/2014.
-In progress.
-Selepas Pembinaan ALL -Date to be decided.
1.2 Prima Setapak 2 (PS2) complaints. ALL a)- Meeting with DBKL, PR2 and MHP
- Was held on 6/10/15. Main complaints with updates
were:
1. Mosquito problems.
Fogging certificate.- Pending submission by WW by today.
2. Site safety.
WW has been reminded to continuously improve. – on
going checking.
4. Road cleanliness.
Progressive cleaning.
b)- School.
2 ARCHITECTURE:
2.1 Matters discussed: TA/JPB a) Client accepted the frosted white glass door for duplex
units. AI to be issued.
4 M&E:
4.1 NSC nominated are:
Electrical - EITA Power System S/B JPKT a) Transformer delivery by 8/2/2016. TNB kick-off meeting
Hydraulics - Perniagaan Kim Chong S/B at 2.30 pm at site office.
Fire protection - Tenaga Ideal (M) S/B
Lift - Kone Elevator (M) S/B b) Open cut excavation, Ir Lee of KOSMOS to advise Mr.
Swimming Pool - Teamspec S/B Gan upon TNB application to DBKL.
c) Will discuss in detail during coordination meeting on
INFO handling over testing and also G-Form requirement.
5 LANDSCAPE:
5.1 Softscape and Playground under NSC. HD a) Client was briefed on the playground tender and
decided to call for tender interview on 19/2/2016 at 2.30
pm at MH HQ. HD to issue notification to all.
6 QUANTITY SURVEYOR:
6.1 Provisional Sum VTA/TA a) VTA to seek WW’s Quotation for letter box which is the
last item in the provisional sum.
7 Strata Title INFO a) Strata Surveyor should finish by CNY and submission by
29/2/2016.
8 OTHER MATTERS:
9 MEETING:
9.1 Next CCM meeting will be held on 15/2/2016 INFO
(Monday) at 9.00am at MHP310 site, Jalan
Gombak.