GRAIN DISCHARGER
MODEL - BE-100, BE-125, BE-150,
BE-200, BE-250, BE-300, BE-350, BE-375
INDEX
A ERECTION & COMMISSIONING
B.1 Construction 12
B.8 Annexure 19
1
Grain Discharger
INTRODUCTION
Grain Discharger
In the present era of globalization, Eminence strives to come up with
new, ultramodern machinery to suit grain handling needs of its clients
achieving the world class standards.
To handle a variety of free flowing material like rice and wheat Eminence
has developed a special Grain Discharger. It handle the grains very
gentle having negligible fall back and negligible broken percentage.
This technical manual aims to provide all the details necessary for its
operation and maintenance.
2
Grain Discharger
A. ERECTION AND COMMISSIONING
Refer to the list of “Packing Details” for Grain Discharger, given in the manual . These parts
are independently despatchable and at times erectable items. These are dispatched in one or
more lots. Verify the goods received at site and Packing List received with the consignment for
the Grain Dischargers. Acknowledge the receipt of materials to Eminence Equipments Pvt.
Ltd. within 3 days from the date of receipt of material at site. Any loss, damage or mismatch
(Quality , Packing List quantity and actual received quantity) should be informed to Eminence
and / or to the Insurance company to make the necessary claims, as the case may be. The
G.A. drawing and layout drawing of Grain Discharger is also attached for reference in the
manual.
Use proper lifting tools / tackles and devices for unloading of material from truck. In case of
manual unloading, proper care should be taken to avoid any possibility of damage to any of
the packing or sub assembly. Please do not throw the Box on Ground from Truck.
For longer storage, prior to erection, keep all material in covered area while the bases of these
units raised by 100mm from the floor. Ensure that all units rest on their bases and not on any
sides, during or after the unloading.
Before erection of equipments, sub-assemblies etc., verify overall foundation provided for the
equipment with the help of drawing.
In case of any variations, get the same corrected before starting the erection of the
equipment.
3
Grain Discharger
4.0 ASSEMBLY AND ERECTION OF GRAIN DISCHARGER
4.1 Assembly Of Bottom Casing
4.1.1 After rectification & ensuring correct foundations
for discharger, bottom casing of Grain Discharger
is kept on foundations, leveled and grouted. Refer
procedure for leveling and grouting, given in
Annexure
4.1.2 After 72 hrs of curing once again check the level of
top flange of bottom casing. Correct the same by
adding shims below the equipment base if
necessary.
4.1.3 Check level of Tail-shaft in this position by water
level and correct the same if required, using Take
up screw assembly.
4.1.4 Keep the Tail-shaft in its upper most position
again using the take-up screw.
Top casing consists of head pulley, shaft, bearings, casings, mechanical type hold-back etc.
And is relatively heavy and bulky. Since it is to be assembled on the top of the middle casings
assembled so far, proper lifting arrangement should be made before starting erection and
assembly of top casing. Please note following points before starting the erection and
assembly of top casing.
4.3.1 Bottom flange of the Top-casing is punched for assembly with Top Intermediate casing
and should be perfectly horizontal. (Check it by water level).
4.3.2 Sliding arrangement should not damage the Top casing while lifting.
4.3.3 The orientation of outlet from Top casing and shaft extensions are as per drawing.
Head Shaft has extention at both the ends & we can change the Drive motor position &
Hold back position on both sides.
4.3.5 Level of the top flange of Bottom casing using water level, correct the same if
necessary. Use suitable packing for this purpose.
Inspection and Bottom casings are to be assembled respectively at the start. Standard
Middle casing are to be assembled in between. Following precautions should be
taken while assembling the Middle Casings.
l) Bolts used for fixing “Distance pieces” are to be tightened only after checking &
assuring of respective casing by plumb in all planes thoroughly.
ll) While placing trunks of middle casing over the another, inner surfaces of both the
trunks should flush correctly with that of the other. Refer sketch in the annexure for
details. Any damage to horizontal edges of inner surface of trunking would result in
obstruction to the belt movement during operation. This must be rectified immediately
if found.
5
Grain Discharger
lll) Middle casing of Grain Discharger must be laterally
supported at every 4 meters. Support brackets or members
must only be bolted to Grain Discharger casing. Welding is
not to be adopted on any of the Grain Discharger parts.
Lateral supports may be obtained from any adjoining
structure. Ensure that verticality / plumbline of Grain
Discharger casing is not disturbed because of these lateral
supports. Refer sketch in annexure for details.
The most Important factor which directly affects the performance of the
Grain Discharger is plumb (Alignment of Grain Discharger)
To check the plumb level, remove the plate as shown in photo of top
casing. Insert the plumb from inside the Intermediate casing.
Remove the side plate at bottom casing & check for the plumb level
Three points on both sides as shown in the photo.
6
Grain Discharger
4.5 ASSEMBLY FOR GRAIN DISCHARGER BELT
Assembly of Grain Discharger belt is an important as well as critical process. As such it is very
important to adhere the procedure given here under for the assembly.
4.5.1 Ensure that length of the Grain Discharger belt received at site is not less than that
given in the packing list of the Grain Discharger. Inform Eminence otherwise,
4.5.2 For Paddy Grain Discharger normally black belt is provided. For rice / wheat food
grade white belts are provided & for discharges after Polisher Oil Resistant Belts are
provided. Choose the belts accordingly referring the Bill of material & drawing.
4.5.3 Place the belt on ground & insert the bucket bolts from
Higher rubber thickness side ( 3mm) Bolt head should
be at higher thickness side & bucket should be fixed
from lower rubber thickness side as shown in photo.
4.5.4 Do not fix all the buckets on the belt. Leave at least 2
meters from rubber both ends of belt without
buckets.
4.5.5 Check that all the buckets are properly tightened. Cup
washer, washer, square nut & nylock nut are tightened.
Fix the belt joining plate at one end of the belt.
4.5.7 Take out both ends of belt from Inspection casing. Remove the Rope.
Fix belt joining plate on other side of the belt with the provision to tight
the belt with TURN BUCKLE
7
Grain Discharger
4.5.8 The turn buckle should be fully open. Tight the belt with the help;
of TURN BUCKLE. After tightening the belt should freely
rotate in the casings.
4.5.9 Cut the extra length of belt with the help of Hake
Saw.
8
Grain Discharger
4.6 Drive Motor Installation,
Before Installation of Drive motor check the free movement of belt with hand.
4.6.1 Check for Oil in the geared motor before the electrical connection.
Check the no load current of motor on ground floor before installation of motor. No.
load currents should be 60% to 70% of rated current of motor. Rated current 60% to
70% (No load current)
9
Grain Discharger
4.6.4 After correct alignment tight the bolts place the chain.
Lock the chain with lock, apply some grease on chain.
Tight the grub screw on Motor shaft & pulley shaft .
Place the aluminium cover.
5.1 Before making electrical connections, ensure that there is no obstruction for the
movement of Belt - Disengage Preferably the electrical connection to the motor should
be the hold baek paul done with armored cable. Provide the relay of appropriate
rating & set the Tripping current as per following table.
Amp. 1.07 1.55 1.85 2.82 3.7 5.4 8.9 11.8 15.7
Check the direction of motor running. Run the motor in corrected direction.
10
Grain Discharger
6.0 NO LOAD TRIALS
6.1 Run the Grain Discharger continuously for 8 hours and then observe for belt details,
any abnormal noise, bucket touching, nuts / bolts getting loose etc. and take
corrective action.
6.2 Check current of the monitor when the elevator is in operation which should not be
more than 60% of the full load rated current of the drive motor.
7.1 Ensure that the equipments incoming & outgoing in the line to the Grain Discharger
are in operation and interlocks are functioning.
7.2 Start the Grain Discharger and start feeding the material to the inlet hopper of the
Grain Discharger.
7.3 Gradually increase the feeding till one achieves the capacity of the system.
7.4 Observe the vibrations, shifting of belt etc. If so observed, put off the system and
analyse the problem and take corrective actions.
7.5 Check the current of motor at full load capacity, It should be less than the mentioned
rated full load current.
11
Grain Discharger
B. OPERATION AND MAINTENANCE
B.1 CONSTRUCTION
a. Bottom Assembly.
b. Top Assembly.
c. Intermediate Casings.
Intermediate Casings are fabricated with mild steel and fixed on each other with the help of
joining clamps and distance pieces. First casing immediately above bottom assembly is
provided with inspection door. This can be used for joining the belt, observing the material in
bucket, to check whether the belt is running at centre etc.
12
Grain Discharger
B.2 OPERATING INSTRUCTIONS
Grain Discharger is running equipment which does not need regular supervision. For safe,
trouble free and efficient operation it is necessary to follow the instructions given below,
B.2.1 Do not operate Grain Discharger unless all equipments incoming & outgoing from the
Bucket Elevator are in operation.
B.2.2 Do not run the Grain Discharger when the belt is loose.
B.2.3 Do not run the Grain Discharger when the buckets are loose.
B.2.4 Do not put hands inside the trunking when the Grain Discharger is in operation
B.2.5 Control the feed to the rated capacity of the Grain Discharger.
B.2.7 Ensure that all connecting parts and chutes are firmly connected to the Grain
Discharger and no abnormal noise is heard during the operation.
B.2.8 After periodic electrical maintenance, before restarting the Grain Discharger, check
and ensure for the correct direction of rotation and hold back assembly in it's locking
position.
B.2.10 Do not run the Grain Discharger if it's safeties are not functioning
13
Grain Discharger
B.3. PERIODIC MAINTENANCE
Above schedule is given on the basis of 8 hours operation of the equipments. In any other
case, change the frequency of maintenance suitably.
14
Grain Discharger
TROUBLE SHOOTING
2. Abnormal Noise 1. Hissing Noise (Loose Belt) Adjust the Take-up screw such
that the belt remains at centre.
15
Grain Discharger
PACKING DETAILS
7. Motor Mounting Bracket / Drive base Frame Crate (with Top casing)
16
Grain Discharger
LOAD TRIAL FORMAT
SR. BE Height No Load Full Load Capacity
Model HP Remark
NO. NO. Meters Current Current TPH / Hr
17
Grain Discharger
A. PRE-TRIAL CHECKS
B POST-TRIAL CHECKS
18
Grain Discharger
PULLEY
PULLEY
GRAIN DISCHARGER
19
Grain Discharger
20
(BUTT JOINT)
Bucket Bolt
Grain Discharger
EMINENCE
EMINENCE EQUIPMENTS PVT . LTD.
Gat No. 343, Plot No. 27 to 32, Near Hindustan Petroleum, Village-Mahalunge, Tal. Khed, Dist. PUNE - 410 501
Phone : 020 - 3230 6023 / 3230 6025 / 3230 5689 Fax : 020 - 2711 9410 • E-mail : eminence@eth.net