Madya Pahadi LokMarga Project

Predecessor
Start Date End Date Task Name Duration (days) Activities Activities
08-Jul-18 14-Jul-18 Preliminary data collection 7 A -
Start making appointment process with NPC & Madhya
10-Jul-18 13-Jul-18 Pahadi Lokmarg office 4 B -
14-Jul-18 14-Jul-18 Visit Nepal Planning Commission 1 C A,B
15-Jul-18 15-Jul-18 Visit Construction Office 1 D C
Conversation with Project Manager about project fund, %of
16-Jul-18 18-Jul-18 project completion and CPM application 3 E D
Discussion(personal meetings or emails) with team leader
19-Jul-18 24-Jul-18 on daily operation and challenges 6 F D
Gap analysis during formulation of project and real
25-Jul-18 28-Jul-18 implementation 4 G E
29-Jul-18 31-Jul-18 First draft of the report 3 H F,G
01-Aug-18 1-Aug-18 Review of report with the instructor and corrections 1 I H
02-Aug-18 5-Aug-18 Show the second draft to the project manager for validation 4 J I
06-Aug-18 6-Aug-18 Final corrections and print the report 1 K J
Network Analysis

Determination of the Critical activity


Duration Slack Critical
Activities (days) EST EFT LST LFT time activity
A 7 0 7 0 7 0 Yes
B 4 0 4 3 7 3 No
C 1 7 8 7 8 0 Yes
D 1 8 9 8 9 0 Yes
E 3 9 12 9 12 0 Yes
F 6 9 15 10 16 1 No
G 4 12 16 12 16 0 Yes
H 3 16 19 16 19 0 Yes
I 1 19 20 19 20 0 Yes
J 4 20 24 20 24 0 Yes
K 1 24 25 24 25 0 Yes

Critical path Time (days)


A-C-D-E-G-H-I-J-K 25