PROJECT TITLE
RELOCATION OF EXISTING SEWERAGE SERVICES FOR CADANGAN PINDAAN KEPADA PELAN PERINTAH
PEMBANGUNAN YANG TELAH DILULUSKAN KEPADA CADANGAN PEMBANGUNAN PANGSAPURI SERVIS
YANG MENGANDUNGI: FASA 1 A) 1 BLOK PANGSAPURI SERVIS (30 TINGKAT) BLOK A 414 UNIT DENGAN
RUANG MEKANIKAL DI ARAS BUMBUNG B) 1 PODIUM (8 TINGKAT) DENGAN RUANG LEGAR, RUANG LETAK
KERETA DAN 1 TINGKAT KEMUDAHAN PENDUDUK, DAN C) 1 TINGKAT RUANG LETAK KERETA DAN
MEKANIKAL SUB-BESMEN FASA 2 A) 1 BLOK PANGSAPURI SERVIS (31 TINGKAT) BLOK B 366 UNIT DENGAN
RUANG MEKANIKAL DI ARAS BUMBUNG DI ATAS LOT 17911, MUKIM SETAPAK, KUALA LUMPUR UNTUK
TETUAN SKYMERIDIEN DEVELOPMENT SDN BHD
SUBJECT
PRESENT
AGENDA
Action By /
Item
Date
1.0 Introduction
2.1.3 The commencement date of relocation sewerage works shall remain unchanged
to 5th March 2018. Consent between EW and SMD that no performance bond Info
will apply to this contract.
2.1.4 EW was again asked to forward the Contractor’s All Risks and Workmen’s
Compensation Insurance policies as stated in LOA to SMD and cc copy to OSE, EW
GRA and VTA.
4.1.1 EW to check the sewerage pipe and manhole level done by previous contractor.
EW yet to carry out the checking on the existing manhole invert level. OSE
EW
highlighted to EW shall bear for all the necessary consequences which might
arise on site.
4.1.2 RE advised that EW to ensure the diversion UPVC pipes are in proper order and
EW
the sump was covered in proper manner with some barriers for safety issue.
4.1.4 OSE advised EW to carry out an underground utilities survey. OSE again
reminded the existing utilities plan is only for reference. EW will need to bear
EW
the risk of discrepancy between the current underground utilities location and
the provided utilities plan if no additional survey carry out by EW.
EW
4.1.5 SMD and OSE has reminded EW to follow up closely with TNB to obtain the
permit from TNB as soon as possible.
4.2.1 OS again requested EW to add in the work done progress summary in the
progress report. EW is required to specify the work progress status throughout EW
the contract period.
4.2.2 EW submitted revised method statement to OSE on 25th April 2018. However,
some items commented before still yet to be clarified. OSE had commented on
EW
the revised method statement and reverted to EW on the same day. EW has to
revise and submit to OSE latest by this week.
4.2.3 CE method statement had submitted by EW together with the progress report
Info
during the meeting.
4.2.5 OSE again requested EW to update work progress daily to all parties in prompt
EW
action.
4.3.1 DBKL
Open excavation permit is obtained on 02 April 2018 valid until 04 May EW
2018. SMD advised EW to renew the permit by this week.
4.3.2 TNB
EW reported CE absented for last week meeting (19th April 2018).
EW
EW will attend a meeting on 26th April 2018 (Thursday), CE will attend
with EW for the method statement presentation in the meeting.
5.1 Claims
5.1.1 EW to submit progress claim 3 days before site evaluation to VTA and cc copy
EW
to OSE.
- -
The statements made in these meeting are the Writer’s understanding of the various discussion held and conclusions reached.
Other participants are requested to review the statements herein and advise the Writer of any errors or omissions within 3 calendar
days from the date of the meeting.
Prepared by:
ONE SMART ENGINEERING SDN. BHD.
…………………………………………………
TANG MUN YAN
Engineer