From: Jonathan Anyon (AT)

Sent: Thursday, 14 December 2017 11:42 a.m.


To: Marilyn Nicholls (AT) <Marilyn.Nicholls@at.govt.nz>
Subject: FW: Onewa Rd T3 lane words

Please see below.

From: Wally Thomas (AT)


Sent: Thursday, 14 December 2017 11:41 a.m.
To: Jonathan Anyon (AT) <Jonathan.Anyon@at.govt.nz>
Cc: Marilyn Nicholls (AT) <Marilyn.Nicholls@at.govt.nz>; Randhir Karma (AT)
<Randhir.Karma@at.govt.nz>
Subject: RE: Onewa Rd T3 lane words

yes

Wally Thomas | Chief Stakeholder Relationships Officer


Communications and Corporate Relations
20 Viaduct Harbour, Auckland 1010
P 09 355 3553 | DDI 09 477 4006| M 021 593 412
www.at.govt.nz

From: Jonathan Anyon (AT)


Sent: Thursday, 14 December 2017 11:36 a.m.
To: Wally Thomas (AT) <Wally.Thomas@at.govt.nz>
Cc: Marilyn Nicholls (AT) <Marilyn.Nicholls@at.govt.nz>; Randhir Karma (AT)
<Randhir.Karma@at.govt.nz>
Subject: RE: Onewa Rd T3 lane words

Wally

I agree we’re not looking at alternatives but I don’t think we can say that given their resolutions.
We’ll ensure Crs Darby and Hills are part of ongoing contact. Are you comfortable with idea of
brief pause (Till Feb) then proceeding as planned?
Regards

Jonathan

From: Wally Thomas (AT)


Sent: Thursday, 14 December 2017 11:32 a.m.
To: Jonathan Anyon (AT) <Jonathan.Anyon@at.govt.nz>
Cc: Marilyn Nicholls (AT) <Marilyn.Nicholls@at.govt.nz>; Randhir Karma (AT)
<Randhir.Karma@at.govt.nz>
Subject: RE: Onewa Rd T3 lane words

Thanks- I’ll pick up and get responses out. Just to be clear, we are not looking at alternatives. We
are simply taking the opportunity to better explain the rationale and benefits to the LB.
Please ensure Crs Darby and Hills are involved in discussions/briefings going forward.

Wally Thomas | Chief Stakeholder Relationships Officer


Communications and Corporate Relations
20 Viaduct Harbour, Auckland 1010
P 09 355 3553 | DDI 09 477 4006| M 021 593 412
www.at.govt.nz

From: Jonathan Anyon (AT)


Sent: Thursday, 14 December 2017 10:36 a.m.
To: Wally Thomas (AT) <Wally.Thomas@at.govt.nz>
Subject: Onewa Rd T3 lane words

Wally

I think short, sweet will work best, given the resolutions the LB actually made. However, if we go
with the wording below, we would need to alert Lester and Mark G to what we’re doing, as
obviously we have an AT Board reso mandating the increased hours and we would need to
reassure them that we’re not considering any alternatives to those agreed times.

Therefore I suggest the following wording:


‘In response to strong advocacy from the Kaipatiki Local Board, Auckland Transport has agreed to
delay the implementation of the extended hours of the Onewa Road T3 lane, while it considers
whether there are any viable alternatives.’

And then in terms of a way forward, meet with Danielle and John Gillon in early February and
explain that we have considered things and there are no viable alternatives and therefore no
reason for further delay. Then implement new T3 times 14 days later.

Regards

Jonathan