Commissioning Check List E

Restricted
ANSI 40
CL-E129 Underexcitation
Protection
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Plant Code

System: Protection/ Synchronization and Metering (Generator)

Component: CHA10-U08-F01 – generator protection

Page: 1 of 1 Appendices:

No. Activity (Items not applicable to be marked N/A) Remarks Confirmed

1.
Technical data: See device coversheet

Secondary injection checklist CL-E229 available 

2. Primary tests

This test will be carried out, when possible, at capacitive load at the
underexcitation limit. Characteristic curves will be tested in two points each by
reducing the settings (1/xd) temporarily.

Curve 1 Curve 2 Curve 3


 1 = 84°  2 = 91°  3 = 90°

1/xd = 0,48 1/xd = 0,45 1/xd = 0.92


Test Point 1 2 1 2 1 2
U [kV]
I [kA]
P [MW] 50% 75%
Q [MVAr]
Excit Voltage n.a n.a n.a n.a n.a n.a
1/xd (pickup) n.a. n.a. n.a. n.a. n.a. n.a.

3. Evaluation

- Mark test points in generator load diagram attached 


- Distance between underexcitation limit and pickup value acceptable 
- Reset operational settings 

4. Remarks:
.......................................................................................................................................................................................... 1

Department: ........................................................ Name: .......................................................................

Date:. ...................................................................... Signature: .............................................................

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.

Das könnte Ihnen auch gefallen