Rate Analysis of Water Tank 10000 ltrs capacity

Date: 2073/02/12
S.N. Particulars Unit Qty Rate Amount (Rs) Remarks
A STRUCTURAL WORK
1 Earthwork in excavation cf 949.40 13.00 12,342.21
2 Earthwork in filling Cf 339.61 11.00 3,735.75
3 Brick soling Sf 123.68 99.00 12,244.28
4 100 micron DPM Sf 123.68 8.00 989.44
5 M10 (PCC) Cf 30.92 247.00 7,637.21
6 M20 (RCC) Cf 209.79 381.00 79,928.75
7 Normal Formwork (12 mm Ply) Sf 502.28 75.00 37,670.71
8 Reinforcement Work Kg 546.65 125 68,331.20

B FINISHING WORK
1 Plaster work Sf 180.00 34.00 6,120.00
2 Punning work Sf 180.00 22.00 3,960.00
3 IPS work Sf 80.00 72.00 5,760.00
4 Water Proofing work Sf 242.28 54.00 13,082.91
Total 251,802.45