Sequence of Activities

Below are the major activities and internal activities that need to be completed to move onto next major
activity

1. Procurement Phase – Milestone – Major Activity


Internal sequence of activities
1.1. Finalize Infrastructure Project Design
1.2. Hire 3 infrastructure contractors and request vendor Beta subject matter expert assistance.
1.3. Download and stage Infrastructure pre-requisites binaries
1.4. Procure Physical Solaris machines from Unix Team for each environment phase
1.5. Verify all OS level pre-requisites for each environment phase

2. POC Phase - Milestone – Major Activity


Internal sequence of activities
2.1. Database configuration – DB team for POC
2.2. Install and configure JDK required versions
2.3. Installation of Vendor Beta infrastructure software and Database configurations
2.4. Provide access privileges per environment specifics
2.5. Code migration to environment
2.6. Sanity check and thorough testing phase.

3. Development Phase – Milestone – Major activity


Internal sequence of activities
3.1. Procurement Phase
3.2. POC-Phase
3.3. Database configuration for Development – DB team
3.4. Network security Configuration – Network Team
3.5. Install and configure JDK required versions
3.6. Installation of Vendor Beta infrastructure software and Database configurations
3.7. Provide access privileges per environment specifics
3.8. Code migration to environment
3.9. Backups and SAN storage steps
3.10. Hand over to Development teams with full admin access

4. Stage Phase - Milestone – Major activity


Internal sequence of activities
4.1. Procurement-Phase Milestone
4.2. Development-Phase Milestone
4.3. Database configuration for Stage– DB team
4.4. Network Configuration
4.5. Install and configure JDK required versions
4.6. Installation of Vendor Beta infrastructure software and Database configurations - cluster design
4.7. Provide access privileges per environment specifics

1
4.8. Code migration to environment

5. Production Phase – Milestone – Major activity


Internal sequence of activities
5.1. Procurement-Phase-Milestone
5.2. POC-Phase-Milestone
5.3. Development-Phase-Milestone
5.4. Stage-Phase-Milestone
5.5. Database builds for production
5.6. Network Configuration
5.7. Infrastructure builds
5.8. Code Migration
5.9. Verification and mock-go-live drills
5.10. Go-live and monitoring
5.11. Hand over to operations team
5.12. Document historical information and Close out Project

2
Project Sequence Activities

Project-
Kick-Off
Procuremen
t-Phase

POC-
Phase-
Milestone

Development-
Phase-Milestone

Stage-Phase-
Milestone

Production-Phase-
Milestone

Project-Closeout and success Party

3
Procurement-Phase – Milestone

Project- Finalize Infrastructure


Kick-Off Design

Hire Contractors
Procure Solaris Physical Request Vendor
machines per environment Beta SME

Download and Stage


Infrastructure s/w

4
POC- Phase Mile Stone [sequence of activities]

Project- Procurement-Phase-
- POC Database configuration
Kick-Off Milestone
- POC Network COnfiguration

POC environment setup

- Install JDK requisite


- Install Vendor Beta s/w
- Install 3rd party s/w

Code Migration and update


any changes

Sanity checks and Testing


phase

5
Development-Phase Milestone

Project- Procurement-Phase-
Kick-Off Milestone

POC-Phase-Milestone

Development Database and


Update any design changes Network configuration
and configuration
requirements

Development Env setup

Access-privileges to
application teams

Handover to Application
Teams

6
Stage Environment – Phase - Milestone
Procurement-Phase-Milestone

POC-Phase - Milestone

Development Phase -
Milestone

Stage Environment Installs

Includes DB and network


configuration

Access-privileges and
CodeMigration

Stage Cluster testing

Backups and SAN storage

7
Production Environment – Phase – Milestone

Project- Procurement-
Kick-Off Phase - Milestone
POC-Phase - Milestone

Development Phase -
Milestone

Stage-Phase-Milestone

Production Builds includes DB Production Infrastructure


and network configuration Mock drill

Start-start

Code Migration

Go-Live and Monitor Phase

Hand-over to operations Team

Project Closeout