Beruflich Dokumente
Kultur Dokumente
1/JULY 2017
TO
IRC:6-2017 “Standard Specifications and Code of Practice for Road Bridges,
Section-II Loads and Load Combinations”
(Seventh Revision)
S. No. Clause No. For Read
Page No.
1 ANNEX-B, New Clause 9. Combination for Design of Bearings
Add new a) The design of the various bearings shall be based on serviceability or ultimate limit
Clause 9 state depending upon the safety classification of the limit state under consideration.
after clause 8
(Page 90) b) For structures with elastic behaviour, all forces and movements should be based on
characteristic values of action. The method of calculation for actions, rotations and
4 Table B.3 Thermal effects include restraint associated Thermal effects include restraint associated with expansion/contraction due to type
Foot Note No. 2 with expansion / contraction due to type of construction (Portal Frame, arch and elastomeric bearings), frictional restraint
(Page 95) of construction (Portal Frame, arch and in metallic bearings and thermal gradients.
elastomeric bearings), frictional restraint in
metallic bearings and thermal gradients. This
combination however is not valid for the
design of bearing and expansion joint.
5 219.5 Note:- For structural components like short Note:- For short rigid structural components like short piers and rigid abutments, the
Computation and rigid abutments, the value of Sa/g shall be value of Sa/g shall be taken as 1. The component is considered as rigid in case the
of Seismic taken as 1. Also , the response reduction factor time period is less than 0.03 sec. Also , the response reduction factor R shall be taken
Response R shall be taken as 1.0 for seismic design of as 1.0 for seismic design of such structural component.
AMENDMENTS
permanent combination
Moderate 0.3 0.2
load (mm)
combination Severe 0.3 0.2
(mm) Very Severe 0.3 0.2 and decompression
Moderate 0.3 0.2 Extreme 0.2 0.2 and decompression
Severe 0.3 0.2
Very Severe 0.2 0.2 and
and Extreme decompression
4. Table 14.1, New Addition Add following note below table.
Page 141
Note: Relative Humidity is as defined in note no. (3) below Table 6.9.
14 Section 1 New
Contents, A-5 Test on Mild Steel and Corrugated HDPE sheeting ducts.
Normative -
Annexures
A-5.
Page(vi)
15 Section 1 - NEW
Contents, A-6Design considerations for Construction stages
Normative
Annexures
A-6.
Page(vi)
16 18.9 - NEW
Page 229 18.9 Design considerations for construction stages
Refer to Annexure A-6
AMENDMENTS
_______________
ANNEXURE A-5
(Refer Clause 13.4.2 and Clause 13.4.3)
TESTS ON MILD STEEL AND CORRUGATED HDPE SHEATHING
DUCTS
Thereafter, the sealing joints will be visually inspected to verify that no failure or opening has taken place.
The sample is placed on a horizontal support 500 mm long so that the sample is supported at all points of
outward corrugations.
A load as specified in Table-A5-1 below is applied gradually at the centre of the supported portion
through a circular contract surface of 12 mm dia. Couplers shall be placed so that the load is applied
approximately at the centre of two corrugations, Fig. A5-2. The load as specified below is applied in
increments.
Between more than more than more than more than more than more than
Dia: 25 mm 35 mm 45 mm 55 mm 65 mm 75mm 85 mm
to Up to Up to Up to Up to Up to Up to
35 mm 45 mm 55 mm 65 mm 75 mm 85 mm 90 mm
The sample is acceptable if the water loss does not exceed 1.5 per cent of the volume . The volume is
worked out as follows:
Another sample 500 mm long is sealed at one end and the volume of hallow space arrived at by pouring
water from a measuring cylinder.
The hear-shrink coupler Fig.A5-6 is supplied in the form of bandage rolls which can be used for all
diameters of sheathing ducts. The bandage is coated on the underside with a heat sensitive adhesive so
that after heating the bandage material shrinks in to the sheathing and ensures formation of a leak proof
joint, without the need for extra taping or support in the form of corrugated sleeve couplers. The heating
is effected by means of a soft gas flame.
Relevant
Clause
No. of
Sr. No. Requirement Method of verification Acceptance criteria Frequency of Test
Bulletin
No. 75,
fib
Material
1 Material 5.2 Table Material certificates based on Material to comply with certificates, specified As specified in footnote of Table 5.2 of
requirements 5.2 testing properties, and declared properties fib75
Test reports Specified
properties Declared material
ANNEXURE A-6
DESIGN CONSIDERATIONS FOR CONSTRUCTION STAGES
A6-1 General
(i) For bridges built in stages, the design and detailing shall take into account of the construction
procedure, sequence etc., as appropriate.Some situations are illustrated in the following.:
a) Where forces, other than those produced on the completed structure, occur in any structural
section during the phases of construction (e.g. deck erection by incremental launching, bridges
built by balanced cantilever, change in sections during construction, change of support conditions
during construction etc.).
b) Where redistribution of forces due to Creep, shrinkage and steel relaxation is originated by
changes to the structural arrangement during the construction process (e.g. continuous bridges
built span by span on false work or by cantilever).
c) Where distribution of stresses due to Creep, shrinkage and steel relaxationis originated by changes
to structural sections during the construction process (e.g. decks consisting of precast beams and
an insitu slab).
d) Where the erection or construction sequence may have an influence on: the stability of the
structure / capacity of section during construction, the forces in the completed structure, or the
geometry of the completed structure.
(ii) For structures in which any of the circumstances described in paragraphs (i) a) to d) apply, the
serviceability limit states and ultimate limit states should be verified during various construction
stages.
(iii) For structures in which the circumstances described in paragraphs (i) b) or c) apply, long term values
of forces or stresses should be determined from an analysis of redistribution effects. Step by step or
approximate methods may be used in these calculations.
(iv) For structures in which the circumstances described in paragraph (i) d) apply erection and casting
sequences/procedures should be indicated on drawings or detailed in a construction procedure
document along with assumed construction and equipment loads / configurations etc.
A6-2.1 General
(a) Distributed construction live load taken as 50 kg/m2 of deck area for cantilever construction,
sequential/span by span construction etc.
(b) Specialized construction equipment load from launching gantry, from traveler, beam and winch,
movement of precast segments over constructed portion etc.
(c) Dynamic load of equipment may be taken as 10% of the lifting load.
(d) Longitudinal forces arising from construction equipment loads according to the type of the
machinery.
(f) Horizontal wind load on structure shall be taken in accordance with the provisions of IRC:6 for
construction stages.
(g) Effects arising from imposed deformations shallbe taken into account. These effects can be of
permanent nature, depending upon the situation. In such situations the strains and stresses shall
be algebraically superimposed as per applicable section at various construction stages.
(h) The support restraints during all construction stages shall be ensured tor stability against sliding
and overturning. The situation may arise when restraint, particularly in longitudinal direction,
may be absent during construction stage. Need of temporary restraint for this situation shall
be either accounted for in suggested sequence & detailing or constructor shall be instructed to
provide appropriate restraint.
(b) For verification of equilibrium under the accidental combination, dynamic response due to
accidental release of precast segment taken as equivalent to additional static load as 100% of the
weight of the precast segment.
(b) The idea of frequent combination does not exist during construction and also limit states
related to durability are not pertinent for short term-phases as such limiting stresses in concrete
to 0.48 fck(t) and steel to 0.8fyk under rare combination during constructionis adequate.
(c) For bridges or element of bridges in which limit state of decompression is checked on the
completed structure, tensile stresses less than fctm(t) under the quasi permanent combination
during construction is permitted.
(d) Prestressing effects may be taken as rsup= rinf= 1.0 during the construction
3. 10.3.4, Indented: a surface with indentations complying with Indented: a surface with indentations complying with
Page 96 Fig. 10.8 Fig. 10.8:μ = 0.9
ERRATA
4. 6.4.1 (c), Page 36 High performance concrete is similar to standard High performance concrete is similar to standard
concrete but contains additional one or more mineral concrete but contains additional one or more mineral
admixtures providing….. admixtures and super plasticizers providing….
B
A s2 (1- C2/ CU2) h
or
Strain distribution for (1- C3/ CU3) h
section with neutral
d axis within section
h C Strain distribution for section
with zero strain at the least
AP compressed face
p p(0)
Ap
AR
A s1 Strain distribution for section Fig. 8.1
in axial compression
Tension Compression
s, p c
ud y c2 cu2
=0.9 uk
0 ( c3) ( cu3)