Sie sind auf Seite 1von 1

13

MARCH 2004 AL INDUSTRY FOCUS


Promotion

Dewatering system eradicates


drift conveyor spillage
ontinual downtime and production

C
“Dewatering systems made by Brain
losses at a longwall mine have been Industries in Sydney have become known as
dramatically reduced by installing a new proven performers within our industry,”
“run of mine” product dewatering system that Hartley said, “ So I contacted their principal,
removes excess water from the coal on its Keith Hobbs.”
conveyor belts. Hobbs visited the mine with his design The assembled Newstan dewatering
Water being delivered into the mine’s personnel to assess the availability of suitable system before delivery.
underground bin would subsequently cause existing conveyor transfer stations where a
wet coal to spill from the main drift conveyor. dewatering system could be installed. The tripper and loading station was
These major drift belt spillages are now a “Unfortunately none of the existing designed specifically so that it could be placed
thing of the past. In turn, potential for transfers proved to be suitable,” Hobbs said, into position below the existing roof mounted
secondary damage to the drift belt has been “but we informed Trevor Hartley that a tripper belt whilst still in operation. The head pulley
reduced. could be introduced into a conveyor to was then pulled up into position and the belt
Supplying 3.5Mtpa to domestic and export accommodate our system.” cut and re-routed through the tripper.The final
markets, Newstan Colliery near Toronto in NSW This had immediate appeal and the 3.5 underground installation was completed in
is one of several underground longwall mines kilometre long South West trunk conveyor one weekend.
owned by Centennial Coal. (SW1) that feeds the underground bin was “It was a big job but we managed it, it works
Newstan’s engineering manager, Trevor targeted. extremely well,” Hartley said.
Hartley, recognised the need to solve the There was a lot of behind the scenes input
excess water problem. at Brain Industries.
“High water influxes are regular events at “We assembled the whole structure in our
Newstan’s longwall face,” Hartley said. yard once it was fabricated, with a bolt in every
“We are mining downdip with water hole,” Hobbs said.
migrating from the goaf.” “That is the only way you can be entirely
“Depending on longwall face gradients, confident that it will go together perfectly on
water accumulates from time to time in low site.”
points along the face. This water is difficult to That was a very important factor in a similar
remove by normal pumping methods.” unit that Brain has just delivered to BHP
“On start up the water is then transported Billiton’s San Juan Coal Mine in New Mexico,
along the AFC with the coal and ends up in our USA.
underground bin,” Hartley said. The Newstan dewatering system Mine executives visiting Australia from San
The bin provides surge capacity of 600 t and chute and loading station. Juan Coal asked Brain to design and supply a
is 30 m deep with an 8 m diameter, according dewatering system for them after seeing one
to Hartley. Vibrating feeders under the bin This conveyor is a three degree downhill operating at BHP Billiton’s Crinum Mine in
deposit coal directly onto the 1:3.5 inclined regenerative conveyor of 3000 tonnes per hour central Queensland.
main drift conveyor. capacity. If a tripper had to be introduced to “We designed the unit to retrofit to an
accommodate the dewatering system, then a existing transfer station on a trunk belt,”Hobbs
braking pulley could be installed to stop the said.
conveyor more efficiently and control another “It was all done to CAD drawings e-mailed
periodic problem — spillage caused by to us from the US,” Hobbs said,“and once again
overfilling the bin. it was fully assembled in our yard prior to
If the bin is full and the SW1 trunk conveyor being containerised for sea freight to Los
does not stop in a timely manner, the resulting Angles.”
overflow can bury the head end of the Both units were installed with minimum
conveyor. Relocating the brake unit from the disruption and downtime. Newstan’s unit
conveyor drive head to the tripper also has the continues to operate efficiently as it
advantage of reducing the effects of braking approaches its first year of service. San Juan’s
forces within the whole conveyor. unit is operating well after six months of
The San Juan dewatering system assembled A cut-through was identified towards the continuous duty.
prior to shipment to the USA. tail end of the SW1 with sufficient space and
roof height to install the system.
“Water gravitates to the bottom of the bin Hobb’s team formulated a design that
to form a slurry. This can cause a surge of wet incorporated tripper, head pulley, braking
coal onto the drift belt which the feeders just pulley and snubbing pulleys, dewatering
cannot control,” Hartley said. system, armoured soft landing chute, loading
Not only did this inundate the area under station, side walls, access ladders and
the bin with coal slurry but it would regularly platforms, all at an acceptable price. Brain Industries (Australia) Pty. Ltd.
cause material slippage on the drift belt The pulleys had to be interchangeable with Telephone: +61 2 9838 0511
resulting in large tonnage spills, lengthy those already in use within the pit and the Fax: +61 2 9838 0544
production stoppages and an on-going clean- loading station had to utilise existing idler Email: hobbs@brainindustries.com.au
up regime. rollers. Website: www.brainindustries.com.au

Das könnte Ihnen auch gefallen