Sl.
DESCRIPTION OF WORK QUANTITY UNIT RATE AMOUNT
No.
1 Providing and laying Tact coat using
80/100 ( VG 10) Grade bitumen at
the rate of 5 Kg. per 10 sqm over
the BT surface preparatory to
another bituminous construction
over it as per MORT & H
specification No. 111, 112, 501, 503
and 900.
20945.00 Sqm `14.44 `3,02,446
2 Bituminous Macadam of 50mm
thickness which shall be consists of
construction in a single course
compacted crushed aggregates
premixed with bituminous binder of
grade 60/70 ( VG 30) at the rate of
3.5 percent by weight of the total
mix to serve as base binder course
in accordance with the requirement
of the specifications and in
conformity with the drawing or as
directed by the Engineer as per
MOST no 111,112,501,504&900.
Abstract 1
`13,00,119
3
`48,80,657
Abstract 2
`48,80,657
Abstract 3
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
1 Providing and laying Tact coat using Emulsion Bitumen at the rate of 3 Kg. per 10 sqm
over the BT surface preparatory to another bituminous construction over it as per MORT
& H specification No. 111, 112, 501, 503 and 900.
Km.5/0 - 6/0
Km 5/2 1 x 1 200.00 5.500 1.000 1100.000 5500.000
Km 5/4 1 x 1 200.00 5.500 1.000 1100.000
Km 5/6 1 x 1 200.00 5.500 1.000 1100.000
Km 5/8 1 x 1 200.00 5.500 1.000 1100.000
Km 5/10 1 x 1 200.00 5.500 1.000 1100.000
Km.6/0 - 7/0
Km 6/2 1 x 1 200.00 5.500 1.000 1100.000 5545.000
Km 6/4 1 x 1 200.00 5.500 1.000 1100.000
Km 6/6 1 x 1 200.00 5.500 1.000 1100.000
Km 6/8 1 x 1 200.00 5.500 1.000 1100.000
Km 6/10 1 x 1 200.00 5.500 1.000 1100.000
(0+1.5)/2
Bus laybye 1 x 2 10.00 0.750 1.000 15.000
1 x 2 10.00 1.500 1.000 30.000
Km.7/0 - 7/8
Km 7/2 1 x 1 200.00 5.500 1.000 1100.000 4400.000
Km 7/4 1 x 1 200.00 5.500 1.000 1100.000
Km 7/6 1 x 1 200.00 5.500 1.000 1100.000
Km 7/8 1 x 1 200.00 5.500 1.000 1100.000
4220.000 20945.000
or say 20945.000 Sqm
Km.7/0 - 7/8
Km 7/2 1 x 1 110.00 5.500 0.050 30.250 181.500
Km 7/4 1 x 1 150.00 5.500 0.050 41.250
Km 7/6 1 x 1 200.00 5.500 0.050 55.000
Km 7/8 1 x 1 200.00 5.500 0.050 55.000
4080.000 181.500
or say 181.500 Cum
3 Advance patch work to an average thickness of 50mm using premixed 13.2mm IRC chips
over the existing BT surface using 44Kg of bitumen of grade 80/100 ( VG 10) per cum of
chips for premix and consolidation well including cost and conveyance of chips to work
site and including cost of bitumen which shall be procured by the contractor himself and
all labour charges etc., complete.
Average width
Km.4/0 - 5/0 1 x 7 3.60 2.70 0.050 3.402
Wheel tracks 1 x 8 2.70 2.30 0.050 2.484
1 x 5 3.20 2.70 0.050 2.160
1 x 4 2.70 1.80 0.050 0.972
1 x 9 3.30 3.00 0.050 4.455 13.473
Km.5/0 - 6/0
Km 5/2 1 x 1 200.00 5.500 1.000 1100.000 5500.000
Km 5/4 1 x 1 200.00 5.500 1.000 1100.000
Km 5/6 1 x 1 200.00 5.500 1.000 1100.000
Km 5/8 1 x 1 200.00 5.500 1.000 1100.000
Km 5/10 1 x 1 200.00 5.500 1.000 1100.000
Km.6/0 - 7/0
Km 6/2 1 x 1 200.00 5.500 1.000 1100.000 5545.000
Km 6/4 1 x 1 200.00 5.500 1.000 1100.000
Km 6/6 1 x 1 200.00 5.500 1.000 1100.000
Km 6/8 1 x 1 200.00 5.500 1.000 1100.000
Km 6/10 1 x 1 200.00 5.500 1.000 1100.000
(0+1.5)/2
1 x 2 10.00 0.750 1.000 15.000
1 x 2 10.00 1.500 1.000 30.000
Km.7/0 - 7/8
Km 7/2 1 x 1 200.00 5.500 1.000 1100.000 4400.000
Km 7/4 1 x 1 200.00 5.500 1.000 1100.000
Km 7/6 1 x 1 200.00 5.500 1.000 1100.000
Km 7/8 1 x 1 200.00 5.500 1.000 1100.000
4220.000 20945.000
or say 20945.000 Sqm
Sl.
DESCRIPTION OF WORK QUANTITY UNIT RATE AMOUNT
No.
1 Providing and laying Tact coat using 80/100 ( VG 10) Grade bitumen at the rate of 5 Kg. per
10 sqm over the BT surface preparatory to another bituminous construction over it as per
MORT & H specification No. 111, 112, 501, 503 and 900.
20945.00 302390.80
14.44
2 .Advance patch work to an average thickness of 50mm using premixed 13.2mm IRC chips
over the existing BT surface using 44Kg of bitumen of grade 80/100 ( VG 10) per cum of chips
for premix and consolidation well including cost and conveyance of chips to work site and
including cost of bitumen which shall be procured by the contractor himself and all labour
charges etc., complete.
47.12 125893.95
4 Semi Dence Bituminous Carpet of 25mm thickness which work shall consists of construction
in a single course compacted crushed aggregates premixed with bituminous binder of 60/70 (
VG 30) grade at the rate ( Design mix ) of percent by weight of the total mix to serve as base
binder course in accordance with the requirement of the specifications and in conformity with
the drawing or as directed by the Engineer as per MOST No 111,112, 501,504 & 900..
Kumbakonam - Rly station road to Cauveri bridge road KM 0/4 - 3/2 2.80
RMR Page 14
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
RMR Page 15
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
RMR Page 16
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
RMR Page 17
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
RMR Page 18
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
RMR Page 19
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
.
Providing and laying Tact coat using Emulsion Bitumen at the rate of 3 Kg. per 10 sqm over the BT surface preparatory to another bituminous
construction over it as per MORT & H specification No. 111, 112, 501, 503 and 900.
DESCRIPTION OF Km.4/0 - 5/0 Km.5/0 - 6/0 Km.6/0 - 7/0 Km.7/0 - 7/8 Km.7/0 - 7/8
QTY Unit
WORK RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT
3.00 Kg Cost of Emulsion Bitumen 35314.40 105.94 35316.09 105.95 35317.78 105.95 35319.47 105.96 35319.47 105.96
10.00 Sqm Labour and Hire charges. 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40
For 10 Sq. Metre 144.34 144.35 144.35 144.36 144.36
For 1 Sq. Metre `14.43 `14.44 `14.44 `14.44 `14.44
.Advance patch work to an average thickness of 50mm using premixed 13.2mm IRC chips over the existing BT surface using 44Kg of bitumen of grade 80/100 (
VG 10) per cum of chips for premix and consolidation well including cost and conveyance of chips to work site and including cost of bitumen which shall be procured
by the contractor himself and all labour charges etc., complete.
DESCRIPTION OF Km.4/0 - 5/0 Km.5/0 - 6/0 Km.6/0 - 7/0 Km.7/0 - 7/8 Km.7/0 - 7/8
QTY Unit
WORK RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT
0.50 cum Cost of IRC 45mm metal 972.35 486.175 975.25 487.63 978.15 489.08 981.05 490.53 981.05 490.53
Cost of IRC 13.2mm
0.50 cum 1140.35 570.175 1143.25 571.63 1146.15 573.08 1149.05 574.53 1149.05 574.53
metal
Cost of 80/100 ( VG 10)
44.00 Kg 33741.38 1484.62 33743.38 1484.71 33745.38 1484.80 33747.38 1484.88 33747.38 1484.88
Bitumen
1.00 cum Labour and Hire charges. 127.00 127.00 127.00 127.00 127.00 127.00 127.00 127.00 127.00 127.00
For 1cum `2,667.97 `2,670.97 `2,673.96 `2,676.94 `2,676.94
DATA Page 20
3.Providing laying and compacting well graded material on prepared sub-grade in accordance with the requirements of the specifications of MORT& H
No.111, 112, 401 and 900. The material shall be laid in one or more layers as sub-base or lower sub-base and upper sub-base as necessary according
to lines, grades and cross sections shown in the drawings or as indicated by the Engineer. (Gravel blanket for Berms )
DESCRIPTION OF Km.4/0 - 5/0 Km.5/0 - 6/0 Km.6/0 - 7/0 Km.7/0 - 7/8 Km.7/0 - 7/8
QTY Unit
WORK RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT RATE AMOUNT
1.00 Cum Cost of Gravel 403.85 403.85 407.15 407.15 410.45 410.45 413.75 413.75 413.75 413.75
1.00 Cum Labour charges. 8.44 8.44 8.44 8.44 8.44 8.44 8.44 8.44 8.44 8.44
Rate per cum `412.29 `415.59 `418.89 `422.19 `422.19
DATA Page 21
Improvements to Muthupet Voimedu Road Km 4/0 - 7/8
CMPSite
QTY Unit DESCRIPTION OF WORK
RATE AMOUNT
0.10 Cum Cost of 11.2mm Metal 800.20 80.02
0.16 Cum Cost of 6.7mm Metal 671.20 107.39
0.11 Cum Cost of 2.8mm Metal 628.20 69.10
28.00 Kg Cost of 60/70 ( VG 30) Gr. Bitumen 34623.45 969.46
10.00 Sqm Labour and Hire charges. 422.88 422.88
For 10 Sq. Metre 1648.85
For 1 Sq. Metre `164.89