CUPIAGUA CPF

Power Transformers
Function Test Certificate
AC-1 No.: HC-1 No.: Certs No.
FE-06
Sheet 1 of 1

AREA / LOCATION: SYSTEM:


P & ID No.: REV SERVICE:
DATA SHEET No.: REV TAG No.
MANUFACTURER: CERTIFICATION CLASSIFICATION: NO HAZARDOUS
MODEL No.: TYPE No.:
SERIAL No.: S.L.D.No.:
CIRCUIT No. SWB: CUBICLE REF.:

Chk Check Description N/A INTL DATE


1. Confirm bushing seals correct with no leaks.
2. Confirm bus bar / cable terminations correctly installed.
3. Confirm HV cable terminations correctly installed.
4. Check winding temperature contacts operation and wiring correct.
5. Check pressure relief device alarm switch operation and wiring correct.
6. Check liquid level relay operation
6. Record resistance from LV studs of transformer to switchboard incoming bus bar.
R/L1 Ohms Y/L2 Ohms B/L3 Ohms
7. Check Transformer correctly earthed and record resistance
Between tank and structure .......….......... Ohms
LV star point and structure .......................Ohms
8. Insulation Resistance: With secondary cable / bus bar connected

HV to EARTH LV to EARTH HV to LV
M.Ohms M.Ohms M.Ohms
9. Pressure Test: HV to LV + E
Record leakage current mA
10. Insulation Resistance as 8 above after pressure test.
HV to EARTH LV to EARTH HV to LV
M.Ohms M.Ohms M.Ohms
11 Check off-line operation of tap changer.
12. Energise primary at 480 V and record secondary volts.
R -Y Y-B R-B R-N Y-N B-N
V V V V V V
13. Check phase rotation RYB at LV incoming switchboard terminations.
REMARKS:

Completed by Approved by Accepted by


(Technician) (Supervisor) (Completions)
COMPANY
SIGNATURE
PRINT NAME
DATE

Rev 01