Dar Al Shifa Hospital – Khalifa City – Abu Dhabi
General Risk Assessment
Testing & Commissioning of ACS & CCTV – General Risk Assessment
Task Hazard Person at Risk Risk Control RA Post Control
Sizing of the scaffolding to be
Scaffold Collapse properly done as per the
Overloaded expected load.
Vertigo while Any person on or in To work within perimeters of
Scaffold Low
working at height vicinity of scaffold safety.
Falling of tools / Working area to be clean and
equipment visual inspection to be done
prior to start work.
Aluminum ladder (2 – 3 meters)
to be used only.
Ladder to be placed properly on
the floor with proper angle.
Any person on or in To work within perimeters of
Ladder Ladder slippage Low
vicinity of ladder safety.
Working area to be clean and
visual inspection to be done
prior to the start of work.
Ensure adequate supports.
Only approved heavy machinery
to be provided.
Defective / Provide adequate support of
damaged manpower for the lifting of
machinery heavy load, signaling, and
Heavy Machinery All area Low
Improper handling operating.
Misuse Deploy competent operator to
engage for the task.
To work within perimeters of
safety.
2 OF 2
Dar Al Shifa Hospital – Khalifa City – Abu Dhabi
General Risk Assessment
Testing & Commissioning of ACS & CCTV – General Risk Assessment
Task Hazard Person at Risk Risk Control RA Post Control
3 OF 2