M&E Works Risk Management

Item Trades Description

1 ACMV
a Procurement
Scope of work for commissioning
specialist
Scope for BMS

Scope for electrical


Fire safing
Chiller factory test report
Plinth construction

b Design & Technical


Fire damper damper location vs fire
compartmentation
Installation of VCD's
Chilled water pipe hydraulic
calculation

Duct static pressure calculation

Silencer selection

Noise and vibration compliance


Requirement for dielectric
connection
Sequence/ mode of operation

Diffuser selection
Provision for air balancing test
point
Inertia base for horizontal pumps
Vibration isolation for piping

space humidity & pressure control

c Operation
Equipment site access
Spatial coordination
Pipe welding must be bevelled
installation of AAV, condensate

Provision for flushing (bypass,


connections, water supply, drains,
etc)
Protection of material/equipment
stored or installed
Provision for duct cleaning/ testing
Provision for chemical dosing system

d T&C, Handover
Fire damper testing
Provision for temporary filter (AHU/
FCU)
Equipment start-up

Ceiling access for balancing

Control system
Pumping system
Water quality for cooling tower

ELEC
Procurement
Genset load test
Switchgear, transformer, MSB
factory test
Scope with other trades

Scope for BMS


Fire safing
Ceiling cutting holes for light
fittings
Plinth construction

Design & Technical


Overall electrical loads
main/submain distribution system
panel board construction standard
underfloor trunking

Lighting level
Lighting control

Sequence of operation
Earting system

Operation
back box installation
dedicated trunking
type of material
earth link for trunking
verticality for wall chasing
accessories for containment
support frame for panels
support for light fittings

T&C, Handover
Lighting level

FP

CWS

BMS

Design Stage I/O points

Spare Points

Construction Stage
BMS panel

wire termination

sensor installation
Testing and
Commissioning BMS system T&C
Drawings BMS

ELV

ICT

Gases

Lift
10/3/2010

Action required Actioned

As QA/QC or physically involved

Control valves, control interfacing,


High level interface for chillers, VDS's
Termination, starter panel
Provision in BOQ
Completion and submission
AHU, chiller, pumps sizing

Ensure provision of fire damper as per


BOMBA requirement
Location of VCD to be in correspond
with
Subcon engineer to prepare the
calculation based on current system
layout and submit to consultant/AZRB
for verification
Subcon engineer to prepare the
calculation based on current system
layout and submit to consultant/AZRB
for verification
The selection must be in conformance
to noice criteria a specific spaces and
within pressure drop allowance

To ensure physical and BMS provision


is all taken care
flow & noise criteria

within plantroom and say 5m from


vibration source

Water must always below electrical


AAV connect to drains, slope for
condensate
Backflushing

dosing points

remove AHU wedge for motor


vibration isolator, check rotation for
fans
Temporary for VCD/VAV/balancing
valves, permanent for fire damper
chilled water valves, MD
flow verification
TDS level, sensors

starter panel for ACMV, loads/location


for others, roller shutter, automatic
door, PA rack, FCU, BSS, camera, ICT
high level and low level interface

genset, diesel tank sizing

MD, TCL, essential


bus duct, cables, aluminium, copper
Form 2B, 3B, 4B
sizes, ways, flushfloor, underfloor,
cover types (recess depth according
to finishes)
Lux calculation
BMS interface, motion sensor, day
light sensor, scheduling, modes
(normal, holidays, festives), contactor
for circuits
genset synchronising, incoming
power
cable or rebar

level, depth, screw length


normal, essential, emergency
galvanised trunking,

access box, elbows


wall mounted
min 4 support for square fittings

Check the I/O points thoroughly, cross


check with the project's technical
specifications.
For every BMS panel, there is always
provision for spare points. Check with
technical specs on how much spare to
be provided. This is vital to ensure we
have enough points available should
there be any changes

check the panel drawing with the


actual panel
make sure wire pulling and
termination are according to the
drawing and then allow for continuity
test
approval from the consultant about
the sensor location is important prior
to installation. ( always remember to
install at a location where it is easily
accessible for maintenance
purposes )
please ensure that all the services
associated with BMS system are
already install and tested beforehand.