Key Plan

This drawing and any information or descriptive matter set out hereon is licensed THIS DRAWING TO BE PRINTED IN COLOUR
to the Qatar Railways Company and is confidential and subject to copyright.
It must not be disclosed, loaned, copied or used for manufacturing, tendering or
N
for any other purpose without written permission. © Qatar Railways Company

BLA
QI

EDUCATION CITY
STATION

FCU SCHEDULE

COOLING COIL MSHEIREB STATION


EXTERNAL MOTOR
SUPPLY AIR POWER
STATIC RATED
FLOW RATE COOLING CHW SUPPLY
EAT LAT CHW TEMP. PRESSURE POWER
LOAD FLOW
THREE PANEL
S.NO UNIT TAG AREA SERVING TYPE QTY SPEED FILTER
5.0 DBT (° WBT DBT WBT EWT LWT CONTROL GRADE
( l/s) (kW) (l/s) (Pa) (W) (V/Ph/Hz)
C) (° C) (° C) (° C) (° C) (° C)

158 M007-MUS-VAC-FCU-GPL-03 VAC-01 CEILING SUSPENDED & CONCEALED 1 112 27.9 18.2 14.2 13.1 1.9 6.0 14.9 0.05 75 148 240/1/50 YES G4

159 M007-MUS-VAC-FCU-GPL-04 CORRIDOR-03 CEILING SUSPENDED & CONCEALED 1 392 24.8 17.5 14.5 13.7 4.9 6.0 14.9 0.13 50 320 240/1/50 YES G4

160 M007-MUS-VAC-FCU-GPL-06 SUMP-03 CEILING SUSPENDED & CONCEALED 1 143 27.3 18.3 14.4 13.3 2.3 6.0 14.9 0.06 75 148 240/1/50 YES G4 Notes

161 M007-MUS-VAC-FCU-GPL-08 SPS LV RM-02(B-M) CEILING SUSPENDED & CONCEALED 1 437 28.7 18.0 13.6 12.4 8.0 6.0 14.9 0.22 100 320 240/1/50 YES G4

162 M007-MUS-VAC-FCU-GPL-10 VAC-04 CEILING SUSPENDED & CONCEALED 1 232 28.0 18.4 14.6 13.5 3.9 6.0 14.9 0.10 75 148 240/1/50 YES G4

163 M007-MUS-VAC-FCU-GPL-11&12 CORRIDOR-06 CEILING SUSPENDED & CONCEALED 2 100 22.2 16.7 14.3 13.7 1.0 6.0 14.9 0.03 50 148 240/1/50 YES G4

164 M007-MUS-VAC-FCU-GPL-13 TEL-01 CEILING SUSPENDED & CONCEALED 1 129 26.4 17.9 14.3 13.3 1.9 6.0 14.9 0.05 100 148 240/1/50 YES G4

165 M007-MUS-VAC-FCU-GPL-14 MSI-02 CEILING SUSPENDED & CONCEALED 1 173 26.4 17.8 14.3 13.3 2.6 6.0 14.9 0.07 75 148 240/1/50 YES G4

166 M007-MUS-VAC-FCU-GPL-15&16 PWT CEILING SUSPENDED & CONCEALED 2 240 27.8 18.4 14.5 13.5 4.0 6.0 14.9 0.11 75 168 240/1/50 YES G4

167 M007-MUS-VAC-FCU-GPL-17 VAC-03 CEILING SUSPENDED & CONCEALED 1 148 27.3 18.2 14.3 13.2 2.4 6.0 14.9 0.06 75 148 240/1/50 YES G4

168 M007-MUS-VAC-FCU-GPL-18 SUMP-02 CEILING SUSPENDED & CONCEALED 1 184 27.7 18.2 14.2 13.2 3.1 6.0 14.9 0.08 75 148 240/1/50 YES G4

169 M007-MUS-VAC-FCU-GPL-19 TO 25 VAC-02 CEILING SUSPENDED & CONCEALED 7 313 28.1 18.4 14.5 13.4 5.3 6.0 14.9 0.14 75 257 240/1/50 YES G4

170 M007-MUS-VAC-FCU-GPL-26 EL ROOM-01 CEILING SUSPENDED & CONCEALED 1 284 28.5 18.3 14.2 13.0 5.0 6.0 14.9 0.13 100 257 240/1/50 YES G4

171 M007-MUS-VAC-FCU-GPL-28 DCT BATTERY CEILING SUSPENDED & CONCEALED 1 392 20.3 15.2 13.6 12.6 3.1 6.0 14.9 0.08 100 320 240/1/50 YES G4

172 M007-MUS-VAC-FCU-GPL-29 SUMP-01 CEILING SUSPENDED & CONCEALED 1 179 27.6 18.4 14.5 13.4 3.0 6.0 14.9 0.08 75 148 240/1/50 YES G4

173 M007-MUS-VAC-FCU-GPL-30&31 CORRIDOR-05 CEILING SUSPENDED & CONCEALED 2 110 20.5 15.7 14.2 13.3 0.9 6.0 14.9 0.02 50 148 240/1/50 YES G4

174 M007-MUS-VAC-FCU-GPL-33 PRESS LOBBY-02 CEILING SUSPENDED & CONCEALED 1 363 24.7 17.5 14.6 13.7 4.5 6.0 14.9 0.12 50 257 240/1/50 YES G4

175 M007-MUS-VAC-FCU-GPL-34 PRESS LOBBY-03 CEILING SUSPENDED & CONCEALED 1 500 24.5 17.2 14.2 13.4 6.2 6.0 14.9 0.17 50 359 240/1/50 YES G4

176 M007-MUS-VAC-FCU-GPL-36 PRESS LOBBY-05 CEILING SUSPENDED & CONCEALED 1 351 24.2 17.3 14.4 13.6 4.2 6.0 14.9 0.11 50 257 240/1/50 YES G4

177 M007-MUS-VAC-FCU-GPL-38 SUMP-04 CEILING SUSPENDED & CONCEALED 1 82 27.4 18.9 15.8 14.8 1.2 6.0 14.9 0.03 50 148 240/1/50 YES G4

178 M007-MUS-VAC-FCU-GPL-39 VAC-10 CEILING SUSPENDED & CONCEALED 1 66 27.0 18.2 14.4 13.4 1.0 6.0 14.9 0.03 50 148 240/1/50 YES G4

179 M007-MUS-VAC-FCU-GPL-41 CORRIDOR-07 CEILING SUSPENDED & CONCEALED 1 175 21.2 16.1 14.3 13.5 1.5 6.0 14.9 0.04 50 148 240/1/50 YES G4

180 M007-MUS-VAC-FCU-GPL-42 TEL-02 CEILING SUSPENDED & CONCEALED 1 278 26.9 18.1 14.6 13.6 4.2 6.0 14.9 0.11 100 168 240/1/50 YES G4

181 M007-MUS-VAC-FCU-GPL-43 TO 50 VAC-08 CEILING SUSPENDED & CONCEALED 8 173 28.1 18.4 14.4 13.3 2.9 6.0 14.9 0.08 50 148 240/1/50 YES G4

182 M007-MUS-VAC-FCU-GPL-51 BATTERY RM-02 (B-MIDDLE) CEILING SUSPENDED & CONCEALED 1 518 20.1 15.0 13.5 12.4 4.1 6.0 14.9 0.11 100 359 240/1/50 YES G4

183 M007-MUS-VAC-FCU-GPL-52 VAC-09 CEILING SUSPENDED & CONCEALED 1 39 25.6 17.8 14.2 13.3 0.6 6.0 14.9 0.02 50 148 240/1/50 YES G4

184 M007-MUS-VAC-FCU-GPL-53 EL ROOM-02 CEILING SUSPENDED & CONCEALED 1 256 28.8 18.5 14.3 13.2 4.5 6.0 14.9 0.12 100 168 240/1/50 YES G4

185 M007-MUS-VAC-FCU-GPL-55 FSPH CEILING SUSPENDED & CONCEALED 1 456 28.0 18.5 14.7 13.6 7.6 6.0 14.9 0.20 75 320 240/1/50 YES G4
Reference drawings
186 M007-MUS-VAC-FCU-GPL-56 SUMP-05 CEILING SUSPENDED & CONCEALED 1 172 27.6 18.0 14.1 13.0 2.9 6.0 14.9 0.08 50 148 240/1/50 YES G4

187 M007-MUS-VAC-FCU-GPL-58 CORRIDOR-08 CEILING SUSPENDED & CONCEALED 1 75 25.1 17.8 14.4 13.6 1.0 6.0 14.9 0.03 50 148 240/1/50 YES G4

188 M007-MUS-VAC-FCU-GPL-59 PRESS LOBBY-06 CEILING SUSPENDED & CONCEALED 1 450 24.5 17.4 14.4 13.6 5.5 6.0 14.9 0.15 50 320 240/1/50 YES G4

189 M007-MUS-VAC-FCU-GPL-60 PRESS LOBBY-07 CEILING SUSPENDED & CONCEALED 1 403 24.4 17.3 14.4 13.6 4.9 6.0 14.9 0.13 50 320 240/1/50 YES G4

190 M007-MUS-VAC-FCU-GPL-61 PRESS LOBBY-08 CEILING SUSPENDED & CONCEALED 1 186 23.2 17.0 14.4 13.7 2.0 6.0 14.9 0.05 50 148 240/1/50 YES G4

191 M007-MUS-VAC-FCU-GPL-64 CORRIDOR-07B CEILING SUSPENDED & CONCEALED 1 209 21.4 15.8 14.5 13.2 1.7 6.0 14.9 0.05 50 148 240/1/50 YES G4

NOTES

1. THE EXTERNAL STATIC PRESSURE AND RATED MOTOR POWER INDICATED IN THIS SCHEDULE IS TENTATIVE ONLY.FINAL MOTOR POWER AND EXTERNAL STATIC PRESSURE SHALL BE PROVIDED AT SHOP DRAWING STAGE BY MEP CONTRACTOR. 5.0 19/04/2017 BV ISSUED FOR SONO RB RD
4.0 27/10/2016 BV ISSUED FOR SONO RB RD
2. ALL THE STARTERS/SOCKETS, INTERCONNECTING CABLING HAS BEEN INCLUDED IN ELECTRICAL SCOPE . ALL CONTROL WIRING HAS BEEN INCLUDED IN BACS SCOPE.
3.1 24/06/2016 BV FOR REVIEW & COMMENT (MUS_MEP_02) RB RD
3. ALL THE ABOVE UNITS SHALL CONSIST OF THE FOLLOWING COMPONENTS: a) SUPPLY AIR SIDE - PANEL FILTER SECTION, CHILLED WATER COOLING COIL SECTION, AND SUPPLY FAN SECTION AS PER SPECIFICATION 3.0 25/02/2016 BV ISSUED FOR SONO RB RD
2.1 31/01/2016 KMK FOR REVIEW & COMMENT (MUS_MEP_02) RB RD
4. ALL THE ABOVE UNITS SHALL BE LOW NOISE TYPE AND SUITABLE FOR ROOM NOISE CRITERIA 35 NC.DOUBLE SKIN TYPE.
2.0 25/10/2015 KMK ISSUED FOR SONO RB RD
5. ALL THE ABOVE UNITS SHALL BE SELECTED AT MEDIUM SPEED CAPACITY. 1.3 18/10/2015 KMK FOR REVIEW & COMMENT (MUS_MEP_02) RB RD
1.2 22/09/2015 KMK FOR REVIEW & COMMENT (MUS_MEP_02) RB RD
6. ALL THE ABOVE UNITS SHALL BE RATED TO MAXIMUM SYSTEM PRESSURES.
1.1 10/08/2015 KMK FOR REVIEW & COMMENT (MUS_MEP_02) RB RD
7. REFER THE HVAC LAYOUTS FOR GENERAL ARRANGEMENT OF THE UNITS. 1.0 01/07/2015 KMK ISSUED FOR TENDER RB RD

8. ALL THE UNITS MUST BE OVERSIZED BY 15% FROM THE ABOVE SCHEDULED CAPACITY. Rev Date Drawn Description Ch’k’d App’d

9. ESSENTIAL POWER SUPPLY REQUIRED FOR THE FOLLOWING CRITICAL ROOM FCU'S M007-MUS-VAC-FCU-MX-62 & M007-MUS-VAC-FCU-CL-87
“This document is issued for the party which
commissioned it and for specific purposes connected with
10. ALL FCU'S SHALL BE PROVIDED WITH THERMOSTAT CONTROL AS PER SPECIFICATION AND DRAWINGS.
the captioned project only. It should not be relied upon by
11. CONTRACTOR SHALL ENSURE MINIMUM ROOM NOISE CRITERIA WHEREVER FCU'S PLANNED INSIDE THE ROOM AND APPROPRIATE ACOUSTIC LINERS SHALL BE CONSIDERED IF REQUIRED. any other party or used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being

HI WALL UNITS used for any other purpose, or containing any error or
omission which is due to an error or omission in data
SUPPLY COOLING COIL
MOTOR supplied to us by other parties.”
AIR POWER
RATED
VOLUME SUPPLY
POWER Project
EACH COOLING CHW
UNIT TAG AREA SERVING TYPE QTY CHW TEMP.
LOAD FLOW QATAR INTEGRATED RAILWAYS PROJECT
EWT LWT
( l/s) (kW) (l/s) (W) (V/Ph/Hz)
(° C) (° C) MAJOR STATIONS
M007-MUS-VAC-SU-CL-01 PRESS LOBBY-02 HI WALL 1 611 6.80 6 14.9 0.18 494 240/1/50

M007-MUS-VAC-SU-CL-02 & 03 PRESS LOBBY-03 HI WALL 2 637 8.00 6 14.9 0.21 494 240/1/50 Station Name

M007-MUS-VAC-SU-CL-04 & 05 PRESS LOBBY-05 HI WALL 2 574 7.15 6 14.9 0.19 494 240/1/50
MSHEIREB STATION
M007-MUS-VAC-SU-CL-06 PRESS LOBBY-10 HI WALL 1 412 4.50 6 14.9 0.12 320 240/1/50

M007-MUS-VAC-SU-CL-07 & 08 PRESS LOBBY-11 HI WALL 2 545 6.75 6 14.9 0.18 359 240/1/50 Title

M007-MUS-VAC-SU-CL-09 PRESS LOBBY-12 HI WALL 1 415 4.60 6 14.9 0.12 320 240/1/50

M007-MUS-VAC-SU-CL-10 & 11 PRESS LOBBY-13 HI WALL 2 460 5.75 6 14.9 0.15 320 240/1/50 VAC SERVICES
M007-MUS-VAC-SU-CL-12 & 13 PRESS LOBBY-14 HI WALL 2 635 7.90 6 14.9 0.21 494 240/1/50
EQUIPMENT SCHEDULE
M007-MUS-VAC-SU-CL-14 TO 16 PRESS LOBBY-15 HI WALL 3 552 6.73 6 14.9 0.18 359 240/1/50

M007-MUS-VAC-SU-CL-17 TO 20 PRESS LOBBY-16 HI WALL 661 8.23 6 14.9 0.22 494 240/1/50
4
SHEET 8
M007-MUS-VAC-SU-CL-21 PRESS LOBBY-17 HI WALL 1 81 1.00 6 14.9 0.03 148 240/1/50

M007-MUS-VAC-SU-CL-22 SCR/FCC HI WALL 1 459 5.30 6 14.9 0.14 320 240/1/50

M007-MUS-VAC-SU-CL-23 CORRIDOR-06 HI WALL 1 245 2.10 6 14.9 0.06 168 240/1/50 Client

M007-MUS-VAC-SU-RGPL-01&02 CORRIDOR-01,02,03 & 09 HI WALL 2 297 3.20 6 14.9 0.09 257 240/1/50 QATAR RAILWAYS COMPANY
CL CORRIDOR,VAC
CORRIDOR-02,TVF
P.O. BOX 29988 Doha
M007-MUS-VAC-SU-RGPL-03 TO 05 HI WALL 3 761 9.50 6 14.9 0.25 595 240/1/50
CORRIDO-02,11
Qatar
NOTES

1. ALL THE SOCKETS SHALL BE PROVIDED FROM ELECTRICAL SCOPE AND INTERCONNECTING CABLING HAS BEEN INCLUDED IN VENDOR SCOPE . Designed RM Eng check RB

2. ALL THE ABOVE UNITS SHALL CONSIST OF THE FOLLOWING COMPONENTS: a) SUPPLY AIR SIDE - PANEL FILTER SECTION, Drawn BV Coordination TS
5.0
CHILLED WATER COOLING COIL SECTION, AND SUPPLY FAN SECTION AS PER SPECIFICATION
Dwg check RB Approved RD
NOTE:
3. ALL THE ABOVE UNITS SHALL BE LOW NOISE TYPE AND SUITABLE FOR ROOM NOISE CRITERIA 35 NC.
THIS DRAWING IS UPDATED BASED ON CURRENT ARCHITECTURAL/STRUCTURAL Scale at A1 Status Rev
4. ALL THE ABOVE UNITS SHALL BE SELECTED AT MEDIUM SPEED CAPACITY. CHANGES INCORPORATING GOLD LINE POP UP OPTIMISATION (RFC 1446), NEW
NTS 04 5.0
RETAIL STRATEGY (RFC 1575), WESTERN UNDERPASS (RFC 1566), TVS ICF
5. ALL THE ABOVE UNITS SHALL BE RATED TO MAXIMUM SYSTEM PRESSURES. (
M010-MSI-INM-11-ICF-00096)ALONG WITH FRONT OF HOUSE MEP/ARCHITECTURAL Drawing Number
COORDINATION.
6. REFER THE HVAC LAYOUTS FOR GENERAL ARRANGEMENT OF THE UNITS.
M007-MML-MHV-DWG-UCSTMUS-AA-23207