Beruflich Dokumente
Kultur Dokumente
Kevin Coons
Senior Mechanical Engineer
Salt River Project
Coronado Generating Station
P.O. Box 1018
Saint Johns, AZ 85936
Joseph G. Dimmick
President
Leak Detection Services, Inc.
708 Melvin Avenue
Annapolis, MD 21401
Heat Rate and Maximum Load Capability Improvements Through
Cycle Isolation
ABSTRACT
Weekly maximum load tests, which started in August 1992 with the
installation of an on-line monitoring system, show that maximum load
had decreased approximately 4 MW during the six months prior to the
overhaul. During this time there were no significant changes in HP or
IP efficiencies, or any other directly-measured cycle parameters.
Therefore, this degradation was attributed to cycle isolation valve
leakage.
Page i of ii
TABLE OF CONTENTS
................................................................................................................................. Page
TABLE OF CONTENTS .................................................................................................. ii
Introduction.................................................................................................................... 1
Overall Performance Improvements ............................................................................ 1
Table 1 – Impact of Repairs on Cycle Performance............................................................1
Cycle-End Performance Degradation .......................................................................... 2
Figure 2 – Unit 1 Maximum Load Test Results ..................................................................2
Figure 3 – Unit 1 Turbine Efficiency Test Results..............................................................2
Figure 4 – Unit 1 VWO Turbine Pressure Ratios ...............................................................3
Cycle Isolation Valve Leakage Improvements ............................................................ 3
Valve Leakage Testing .................................................................................................. 4
Table 5 – Summary of Valve Leakage Survey Results .......................................................4
Valve Leakage Survey Conclusions ................................................................................................................4
Tested Valves and Traps ...................................................................................................................4
Other Problems..................................................................................................................................4
Valve Position.....................................................................................................................4
Valve Leak Survey Recommendations ............................................................................................................5
Tested Valves and Traps ...................................................................................................................5
Cycle Isolation Checklists .................................................................................................................5
Post-Outage Surveys .........................................................................................................................5
Valve Repairs ................................................................................................................. 6
Table 6 – Valves Repaired..................................................................................................6
Turbine Repairs ............................................................................................................. 6
Table 7 – Turbine Efficiency Improvements.......................................................................6
End Packing Replacements..............................................................................................................................7
Table 8 – End Packing Performance Improvements ...........................................................7
Feedwater Heater Improvements .....................................................................................................................7
Steam Flow Changes .......................................................................................................................................7
Comparison to Other Work........................................................................................... 8
Table 9 – Estimated Individual Valve Leakage Effects ......................................................8
Conclusions ................................................................................................................... 9
Appendix A Instrumentation and Test Procedures .................................................. 10
Instrumentation..............................................................................................................................................10
Test Procedures .............................................................................................................................................10
Page ii of ii
Introduction
Salt River Project's Coronado Unit 1 is a conventional, coal-fired plant rated at 410.94
mw and completed in 1979. It is located in Saint Johns Arizona. Weekly maximum load
tests, started in August 1992, after the installation of an on-line heat rate monitoring
system, showed that the maximum load capability had deteoriated by about 4 MW, with a
commensurate increase in heat rate.
During this time, HP and IP turbine efficiencies remained relatively constant. HP and IP
efficiencies were directly measured by the monitoring system. There were also no
changes in throttle flow nor in enthalpy.
Also, the VWO pressure ratios measured by the on-line monitoring system during the
weekly maximum-load tests had been essentially unchanged. It was therefore theorized
that the degradation was due to unaccounted losses, which meant leaking cycle isolation
valves.
Turbine Repairs
No work was done on the LP turbines. Work done during the overhaul improved
efficiency in both the HP and IP sections of the turbine, as shown in Table 7.
Major contributors to improved performance were:
• Replacement of radial spill strips in the HP/IP sections,
• Installation of Retractable interstage packing,
• Repair of Solid Particle Erosion (SPE) damage to the stationary diaphragms and,
• Repair of stationary diaphragm flow path SPE damage in the first stages of the IP
section.
Cover deposits were removed from the first three stages of the IP section, but these
deposits had very little impact on turbine performance.
Test Date: 15 Feb 1993 4 May 1993 Efficiency Increase
HP Efficiency 82.4 84.5 2.1%
IP Efficiency 91.5 93.2 1.7%
Table 7 – Turbine Efficiency Improvements
A steam path audit was done on the HP/IP sections using a computer program from
Encotech, Inc. The program quantified the impact of turbine component degradation.
Opening measurements were taken by an Encotech field engineer. Closing measurements
were taken by CGS engineering personnel.
1Branco,Maria, et al, "Heat Rate Recovery by Cycle Isolation Diagnosis and Correction," 1991 Heat Rate
Conference, EPRI
2Hopson,Warren H., et al, "The Best Buy in Heat Rate Recovery - Turbine Cycle Isolation Maintenance,"
EPRI Heat Rate Improvement Workshop, 1985