Sie sind auf Seite 1von 13

GAS DESIGN STANDARD A-90

POLYETHYLENE GAS DISTRIBUTION SYSTEM DESIGN

Publication Date: 02-26-14 Rev. #06


This document also appears in the following manuals:
S Electric & Gas Service Requirements (Greenbook)
S Gas Applicant Design Manual

Purpose and Scope


This Gas Design Standard (GDS) provides design requirements for the Pacific Gas and Electric Company (Company)
polyethylene (PE) gas distribution system. Company PE installations meet the Code of Federal Regulations 49 (CFR)
192.321, “Installation of plastic pipe.”
Areas covered in this GDS include:
S General Information
S Materials: pipe, fittings, risers, valves and locating wire
S Polyethylene Pipe Placement
S Construction Methods: preferred PE joining methods, direct-burial plastic main and service
installation, mechanical insertion of polyethylene main and service and plastic service renewal.
S Records

General Information
1. Connections within the PE system may be made with the following:
S Heat iron socket and butt fusion (reference Gas Design Standard B-90, “Plastic System Socket and
Butt Fusion Fittings”)
S Heat iron saddle fusion (reference Gas Design Standard B-90.1, “Plastic System Saddle Fittings”)
S Electrofusion (reference Gas Design Standard B-90.3, “Electrofusion Fittings and Tapping Tees”)
S Mechanical fittings (reference Gas Design Standard B-91, “Transition Fittings for Polyethylene Pipe”
and Gas Design Standard, B-91.1, “Polyethylene (PE) System Mechanical Fittings”).
NOTE: Any connection to Aldyl-A pipe requires mechanical or electrofusion fittings ONLY. Heat iron fusion is
NOT allowed on Aldyl-A pipe.
S IF the SDR (wall thickness) of an Aldyl-A pipe is unknown,
THEN electrofusion must be used.
2. Evaluate cathodic protection impacts of the design: Utility Standard S0470, “Design and Construction of Gas
Distribution Facilities” requires a corrosion mechanic or gas operating supervisor to evaluate the cathodic
protection impacts and needs associated with a project during the design stage of the project.
a. All isolated steel pipe, risers, valves, and/or fittings within a PE pipe system must be cathodically protected.
Prefabricated risers, metallic components on plastic valves, tapping tees, and/or metallic bolts on plastic
fittings do NOT need to be protected. Refer to Gas Transmission and Distribution Manual - Corrosion Control
Volume.
3. Ensure plastic mains or services are not subjected to temperatures greater than 140ºF as described in
Gas Design Standard A-93, “Polyethylene Pipe Specifications and Design Considerations.”
4. To deactivate a plastic service see Gas Design Standard A-93.2, “Deactivation of Plastic Services.”

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 1 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Materials
Only pipeline components listed in the Company’s Gas Standards and Specifications, Gas Information Bulletins and
Flash emails are allowed in construction of the gas system.
1. Pipe
a. Pipe sizing:
S 2”, 4”, 6” or 8” PE main is preferred.
S New services and fully replaced services are to be 1” CTS or larger.
Exceptions: Existing 3/4” steel services may be replaced with inserted 1/2” CTS polyethylene, if the 1/2”
CTS polyethylene has the capacity to support current customer loads and is consistent with Gas Design
Standard A-93.3, “Plastic Excess Flow Valves,” when an excess flow valve (EFV) is required.
Existing 1/2” CTS PE service may be replaced by pipe splitting with 1/2” CTS as described in
Utility Procedure TD-4634P-01, “Polyethylene Service Splitting.”
Note: 1/2” CTS may ONLY be used for inserting, 1/2” CTS pipe splitting, partial service alterations, and leak
repairs to existing 1/2” CTS services.
S On applicant installed jobs, the Company may accept previously installed 1/2” CTS services
and 1/2” CTS service stubs installed prior to May 1, 2010, if those services and stubs have the
capacity to support the current customer loads, as approved by the local area engineer. See
Appendix 1 for the requirements that must be met to approve previously installed applicant
installations.
2. Fittings
a. Heat Iron Fusion Fittings are listed in Gas Design Standard B-90 and Gas Design Standard B-90.1.
b. Electrofusion Fittings are listed in Gas Design Standard B-90.3.
c. Approved PE-to-PE mechanical connections are listed in Gas Design Standard B-90.1, Gas Design Standard
B-91, and Gas Design Standard B-91.1.
d. Make PE-to-steel, PE-to-copper, or PE-to-cast-iron transition joints using the approved transition fittings
shown in:
S Gas Design Standard B-54, “Compression Couplings”
S Gas Design Standard B-91, “Transition Fittings for Polyethylene Pipe”
S Gas Design Standard, B-91.1, “Polyethylene (PE) System Mechanical Fittings”
S Gas Design Standard B-91.4, “Cast Iron to Steel Insulated Transition Couplings”
S Gas Design Standard B-91.5, “Cast Iron to Polyethylene Transition Fittings”
3. Risers
a. Pre-fabricated risers are listed in Gas Design Standard A-91, “Prefabricated Risers.”
4. Valves
a. Excess Flow Valves (EFVs) are listed in Gas Design Standard A-93.3.
b. PE valves are listed in Gas Design Standard F-90, “Polyethylene (PE) Valves.”
c. Contact the local area engineer to determine requirements when using steel valves within a PE system. For
example: when installing fire/emergency valves upstream and downstream of regulator stations.

When steel valves are installed in a PE system, vertical or horizontal steel legs must be welded to the steel
pipe or transition fittings to prevent the valve body from rotating (see examples in A-90 Attachment 1,
“Illustration of a Direct Burial Main and Service Installation”). Gas Design Standards and Specifications,
Section F provides information on steel valves.
5. PE Pipe Locating
a. For locating wire requirements see Gas Design Standard A-90.2, “Locating Wire Installation for Direct Burial
Plastic Mains and Services” and Gas Design Standard A-90.3, “Locating Wire Installation for Inserted Plastic
Mains and Services.”

Page 2 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Polyethylene Pipe System Design


1. Polyethylene Pipe Placement:
Horizontal distance:
a. Polyethylene distribution gas main must be installed a minimum horizontal distance of 10’ from the face or
foundation of any building.
S IF the main must be installed closer than 10’ to a foundation or building,
THEN contact the local area gas engineer to determine if additional protection for the gas main is required.
Burial depth:
a. Place gas only facilities in the distribution trench per GS Interim Standard 463-4, “Cover and Clearance
Requirements for Transmission Lines, Mains and Service Lines.”
b. Place joint trench gas facilities in the distribution trench per Utility Standard S5453, “Joint Trench.” Placement
in a Public Utility Easement (PUE) is preferred.
c. Plastic pipe is susceptible to buckling and crushing at specified depths due to the effects of soil stresses.
Plastic pipe may NOT be installed at a depth greater than 10’ unless the installation is evaluated for fill-stress
effects and is approved by the area senior gas distribution engineer.
Gas service placement:
a. Gas service is normally installed in a straight line at a right angle to the main, traversing from the main to the
meter.
S Offsets, diagonal runs, and bends should be avoided wherever possible.
S Where avoidable, service should NOT be installed under driveways or customer-paved areas.
b. When an applicant changes the service-point location (flop lots), take one of the following actions:
i. For short-side service stubs, cut off the service stub at the main per Gas Design Standard A-93.2. Install a
new service.
ii. For long-side service stubs:
S IF the street is not yet paved,
THEN cut off the service stub at the main per Gas Design Standard A-93.2. Install a new service.
S IF the street is paved and the walls of the new building are still opened,
THEN use the existing service-point location and have the applicant re-plumb the houseline to the
original service-point location.
S IF the street is paved and the walls of the new building are closed,
THEN consult the local area engineer to determine the change in service lay-out.
c. The final grade level for a pre-fabricated riser must be at or below the red burial line indicated on the riser as
described in Gas Design Standard A-91.
2. Typical Subdivision Design for PE Pipe
Figure 1 shows a “Typical Subdivision Design - Infill” and Figure 2 shows a “Typical Subdivision Design - End of
System Growth”
a. The local gas distribution engineer must specify main-line rib sizes and tie-in locations.
b. Do NOT terminate gas distribution facilities at the end of a development to clear paving or other improvements
unless the applicant requests an extension to serve adjacent future development. Terminate these facilities
approximately 5’ past the last service or to the next property line within the project area, unless approved by
the area senior gas distribution engineer.
c. To make sharp turns or offsets (smaller than the minimum bend radius in Table 2), install full-opening heat
fusion fittings per Gas Design Standard B-90 or electrofusion fittings per Gas Design Standard B-90.3.

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 3 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Proposed Development Existing Development

Take-Off From Existing Tie-In to Existing


Existing Main (To be sized by gas engineer)
Line Rib

Existing
2” IPS Main
2” IPS Rib
Main
Existing Road With Main

(Typical)

Tie-In to
Existing

Proposed
Main-Line Rib Place distribution main
(To be sized by gas engineer) in accordance with
Utility Standard S5453
(PUE Preferred).
Future Development Terminate main-line rib
at end of last service.
Figure 1
Typical Subdivision Design − Infill

d. Place the gas facilities in the distribution trench per Utility Standard S5453. Placement in a PUE is preferred.

Existing Main-Line Rib

Extend main 2” IPS (Typical)


to provide
back-tie. To
be sized by
PG&E gas Proposed Development
distribution
engineer.

To be sized by Gas
Proposed Road Engineer

Terminate Main line rib

Future Development
Figure 2
Typical Subdivision Design − End of System Growth

e. A subdivision design for end of system growth is shown in Figure 2. Extend the distribution main along the
proposed road to provide a back-tie to the proposed development.

Page 4 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

3. Branch Services
a. Branch services must be designed and installed as outlined in Gas Design Standard A-42, “Standard Branch
Service Installation.”
b. Branching may be used to provide service to NO more than two buildings. The meter installations must be
located on the adjacent sides of the two buildings served. Where a branch-service installation is justified, a
separate location for the gas meter and electric meter is permissible, if necessary.

Construction Methods
1. PE Joining Methods
a. The preferred joining methods for each size pipe are shown in Table 1.

Table 1 PE Pipe Joining Methods


Pipe/Tubing Size (Inches) Joining Method
1/2 CTS, 1 CTS, and 1-1/4 IPS Electrofusion, Heat Iron Socket Fusion or Mechanical Fittings
2 IPS Electrofusion, Heat Iron Socket Fusion, Heat Iron Butt Fusion or
Mechanical Fittings
3 IPS and Larger Heat Iron Butt Fusion and Electrofusion

2. Typical Direct-Burial Plastic Main and Service Installation


a. Do NOT install direct-buried plastic pipe beneath retaining structures, walls or footings, or adjacent to pile or
other structures subject to settlement.
b. Do NOT install direct-buried plastic pipe in unpaved areas where substantial wheel or equipment loading may
damage the pipe, unless approved by the local area gas engineer.
c. A warning tape is to be installed in direct-burial installations per Gas Design Standard L-16, “Gas Pipeline
Underground Warning Tape.”
Directional Changes
d. Changes in pipe direction must be made with elbows or tee fittings at street intersections (as illustrated in
A-90 Attachment 1). Roping may be used for directional changes at other locations, when necessary.
e. Bends in roped PE pipe must be installed in the trench with a radius greater than the minimum recommended
radius (Table 2). All bends must have a radius greater than: 20 times the pipe diameter for SDR 7 and 9 and
25 times the pipe diameter for SDR 10, 11, 11.5 and 13.5.
f. There must be NO fusion or mechanical joints within 3’ of any bend.

Table 2 PE Pipe Minimum Bend Radius


Nominal Pipe Size (Inches) Minimum Bend Radius for PE Pipe Unsupported by Casing
1/2 CTS 1-1/4’
1 CTS 2-1/4’
1-1/4 IPS 3-1/2’
2 IPS 5’
3 IPS 7’
4 IPS 9-1/2’
6 IPS 14’
8 IPS 18’

g. Ensure that plastic pipe containing fusions or mechanical joints is installed in a straight alignment. Plastic pipe
installations are in a straight alignment if the bend radius of the pipe is greater than 150 times the pipe
diameter.

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 5 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Locating Wire Service Valve, Tamper Proof, Insulated,


(See Gas Design Standard A-90.2) Per Gas Design Standard F-80

Prefabricated Service Riser


Coupling Shown for Stub or Riser Kit
Service Extension Only (See Gas Design Standard A-91)

Connect a locating wire according to


Gas Design Standard A-90.3
Plastic

Plastic Main

EFV
Figure 3
Plastic Service Installation

Figure 3 represents a typical lateral connection. See Gas Design Standard B-90.1 and Gas Design Standard B-90.3
for saddle fittings.
h. For future lateral lines, install a minimum 3’ stub with locating wire attached to an anode as described in
Gas Design Standard A-90.2
3. Mechanical Insertion of Polyethylene Main and Service
a. Refer to the documents below for information on specific casing applications and installations:
S Refer to Gas Design Standard A-75, “Gas Service and Mains in Plastic Casing” for the specific
installation requirements for plastic pipe in a plastic casing.
S Refer to Gas Design Standard A-33.1, “Plastic Gas Lines on Bridge Structures” for the specific
installation requirements for plastic lines on bridge structures.
S Casing size and other requirements for highway crossings are provided in Gas Design Standard
A-70, “Casings for Highway and Railroad Crossings.”
b. Do not transfer copper services to a new main or alter copper services (see Utility Standard TD-4801S,
“Service Replacement Criteria”). Replace copper services with 1” CTS or larger PE tubing. Install an excess
flow valve (EFV) per Gas Design Standard A-93.3. (see illustration in A-90 Attachment 1)
c. Plastic pipe is approved for double inserting into existing mains and services. This application is approved
provided the following conditions are met:
S Removing the previously inserted pipe is not practical or economical.
S Installation is made in accordance with Gas Design Standard A-75 or Gas Design Standard
A-93.1, “Plastic Gas Distribution System Construction and Maintenance,” as applicable,
particularly with respect to protecting and supporting the entry and exit points.
S Installation is mapped with both the casing size and casing material identified. An example is
shown in the mechanical insertion section of Gas Design Standard A-93.1.
d. Ensure that the minimum bend radius of PE pipe listed in Table 2 is not exceeded during insertion into a
casing.
e. Provide for future laterals by installing stubs or opening up the casing at appropriate locations (see Figure 4,
“Laterals Off Plastic Main Insert” and Figure 6, “Service Connections Off Plastic Main Insert”).
f. Plug the space between the plastic and the casing pipe (see Figure 5, “Tie-In to Steel”) with casing plugs or
cable protectors (see Gas Design Standard A-70, “Casings for Highway and Railroad Crossings” and Gas
Design Standard A-73, “Casing Insulator and End Seals Selection Chart”), duct seal, or other suitable means
not detrimental to PE pipe. See Gas Design Standard A-75 for the plastic casing/sleeve sealing requirements.

Page 6 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Min. 12”
Min.
12”
Old Main Old Main

Branching Saddle or Tee Future Extension


Coupling 36” to 48” Nipple
Plastic Branching Nipple Plastic Cap

Figure 4
Laterals Off Plastic Main Insert

Protect Plastic From Sharp Casing


Edges With Cable Protectors or
Casing Plugs (See Gas Design
3’ + Standard B-90.2)
Lateral
Steel Plastic Old Main Connection

Control Transition Fitting


Fitting (See Gas Design Standard B-91)
Steel
Existing Steel Figure 5 Tie-
In to Steel

Service Saddle Service Saddle


Tapping Tee Tapping Tee

Old Main Old Main

8”−12” Typical Plastic Steel


Service Service
Transfer Transfer
Service Insert in Excess Steel-to-Plastic Adapter
Conjunction With Flow Coupling (Compression
Main Insert Valve Type)
Steel Service
Plastic
Service Casing Coupling
Sleeve and Service Casing
Casing Plug (Steel or Plastic)
Figure 6
Service Connections Off Plastic Main Insert

4. Riser Insertion
a. Details for service head adapter installation are provided in Gas Design Standard B-91.
b. Whenever possible, the service riser must be relocated outside of the building (see Gas Design Standard
A-91). This section of Gas Design Standard A-90, “Plastic Main and Service Installation,” Figure 7, “Typical
Insert into Basement or Meter Box,” is intended for use on service renewals where a new service riser cannot
be relocated outside of the building.

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 7 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Curb Box per Gas Design Standard K-40

Sleeve Fusion or
Mechanical Vent
Service Tee Coupling

Steel
Plastic Pipe
Casing

Casing Plastic Casing Casing Plug


Plug Pipe Plug
Curb Valve and Support Base Fusion or Mechanical Coupling
(See Gas Design Standard F-90)
Detail A
Insulated Service Valve
(See Gas Design Standard F-80)
Insulated Service Valve
(See Gas Design
Standard F-80)
Plastic
Pipe
Service Head Adapter
(See Gas Design Standard B-91)

Steel
Casing r
See Table 3 on Page 9
Service Head Adapter
(See Gas Design Standard B-91)
Detail B Detail C
Typical Plastic Insert Inside
Building
Figure 7
Typical Plastic Insert Into Basement or Meter Box

c. Where possible, the sleeve should bridge the gap between the service tee and the casing pipe. The plastic
pipe must be supported by well-compacted sand or fine soil.
d. Use 1/2” CTS copper or stainless steel tubing as a vent pipe.
S The vent pipe must be inserted approximately 6” into the annulus between the casing pipe and
plastic pipe (see vent in Figure 7).
S The tubing may be slightly oval to fit into the annulus.
S Use care to avoid restricting the carrying capacity of the tubing.
S Insulate the tubing from the steel casing by wrapping the tubing with tape.
S Drill a 3/8” hole into the plastic extension of the curb valve box and insert the tubing with a slight
gooseneck to prevent dirt from clogging the vent.
e. Do NOT insert plastic pipe into a casing if the casing pipe radius is less than that shown in Table 3.
S IF the radius is less than Table 3,
THEN install a new riser with the proper bend radius.
f. Install the curb box so that external loads are not transmitted to the service. The valve box must NOT rest on
the service pipe or casing.

Page 8 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Table 3 Minimum Bend Radius in a Riser Casing for Specified Pipe Sizes
Pipe Size (Inches) Minimum Radius (Inches)
1/2 CTS 18
1 CTS 28
1-1/4 IPS 41-1/2

g. See Gas Design Standard A-44, “Service Connections to Cast Iron Main” for information on connecting plastic
to cast iron.
5. Records
a. The brand name of all plastic pipe lots installed at each location and the date it was manufactured must be
recorded in the permanent records. This may require multiple plastic stamps for construction drawings.
Figure 8 depicts a sample plastic stamp for construction drawings.
S Note the pipe’s brand and manufacturing date (MM/DD/YY format) on the foreman’s copy of the
completed estimate.
S Transcribe this information to the file copy.
S Record the brand and manufacturing date (MM/DD/YY format) of pipe used for service
installations in the “Remarks” section of the Form F5458-1, “Gas Service Record,” or the
Form TD-4110P-03-F01, “Leak Repair, Inspection, and Gas Quarterly Incident Report,” as
appropriate.
S See A-93 Attachment B, “Approved PE Pipe/Tubing Manufacturers and Plants” for a description
of print line information.

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 9 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

TEST AT 100−110 PSI FOR MINIMUM OF 5 MIN


Pressure Duration Initials Date of Test

Plastic Pipe Data


Footage and Size ____________/____________
SDR / Wall Thickness _________________________
Pipe Manufacture _________________________
Date Manufactured _________________________
□ PE 2406/2708 □ Other PE:
Footage and Size ____________/____________
SDR / Wall Thickness _________________________
Pipe Manufacture _________________________
Date Manufactured _________________________
□ PE 2406/2708 □ Other PE:

Foreman LAN ID: ____________ Date: _______/______/______


Foreman Signature: _______________________________________
List all plastic pipe by footage, size, manufacture and date
manufactured per Gas Design Standard A-93.1

Figure 8
Plastic Pipe Stamp

Page 10 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Target Audience
Gas planners, estimators, new business inspectors, gas distribution engineers, maintenance and construction,
general construction, materials inspectors, and personnel involved in PE pipe connection training and qualification.

Definitions
NA

Acronyms and Abbreviations


NA
Compliance Requirement/Regulatory Commitment
Installation of plastic pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49 CFR 192.321
References
Code Numbers for Steel Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-15
Plastic Gas Lines on Bridge Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-33.1
Piping Design and Test Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-34
Standard Branch Service Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-42
Service Connections to Cast Iron Main . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-44
Copper Pipeline Defects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-67
Casings for Highway and Railroad Crossings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-70
Casing Insulator and End Seals Selection Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-73
Gas Service and Mains in Plastic Casing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-75
Plastic Main and Service Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-90
Locating Wire Installation for Direct Burial Plastic Mains and Services . . . . . . . . . . . . . . . . . . . . A-90.2
Locating Wire Installation for Inserted Plastic Mains and Services . . . . . . . . . . . . . . . . . . . . . . . A-90.3
Prefabricated Risers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-91
Polyethylene Pipe Specifications and Design Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . A-93
Plastic Gas Distribution System Construction and Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . A-93.1
Deactivation of Plastic Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-93.2
Plastic Excess Flow Valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-93.3
Compression Couplings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-54
Plastic System Socket and Butt Fusion Fittings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-90
Plastic System Saddle Fittings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-90.1
Polyethylene (PE) System Accessories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-90.2
Electrofusion Fittings and Tapping Tees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-90.3
Transition Fittings for Polyethylene Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-91
Polyethylene (PE) System Mechanical Fittings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-91.1
Cast Iron to Steel Insulated Transition Couplings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-91.4
Meter Valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F-80
Polyethylene (PE) Valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F-90
Gas Meter Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . J-15
Gas Meter Room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . J-16
Plastic Valve Box for 3/4” - 4” Valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . K-40
Gas Pipeline Underground Warning Tape . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . L-16
Gas Service Record . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F5458-1
Cover and Clearance Requirements for Transmission Lines, Mains and Service Lines . . . . . . GS I.S. 463-4
Design and Construction of Gas Distribution Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S0470
Joint Trench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S5453
Leak Repair, Inspection, and Gas Quarterly Incident Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . TD-4110P-03-F01
Polyethylene Service Splitting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TD-4634P-01
Service Replacement Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TD-4801S
Squeezing Polyethylene (PE) pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . WP4170-02
Gas Design Standards and Specifications, Section F
Gas Transmission and Distribution Manual - Corrosion Control Volume
Plastic Pipe Institute (PPI) Handbook, Chapter 7, Underground Installation of PE Piping
ASTM F1973-08, Standard Specification for Factory Assembled Anodeless Risers and Transition Fittings
in Polyethylene (PE) and Polyamide 11 (PA11) and Polyamide 12 (PA12) Fuel Gas Distribution Systems

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 11 of 13
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Appendices
Appendix 1 − Application of New Installation and Design Requirements to Qualified Delayed
Applicant-Installed Work

Attachments
Illustration of a Direct Burial Main and Service Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-90 Attachment 1

Revision Notes
Revision 06 has the following changes:
1. Gas Design Standard A-93.1 and Gas Design Standard A-90 have been revised to organize all design information
for the plastic pipe system in Gas Design Standard A-90 and construction information into Gas Design Standard
A-93.1. Several items were moved from Gas Design Standard A-93.1 into the Gas Design Standard A-90 design
document including preferred joining methods and the minimum bend radius for pipe.
2. The title of the document has been changed from “Plastic Main and Service Installation” to “Polyethylene Gas
Distribution System Design”.
3. The document formatting has changed to clarify wording and group subjects. References have been updated and
some new references added to direct document users to additional information.
4. Incorporated 1” service requirements and installation information from TD-A-90B-001 to Appendix 1.
5. The instruction for inserting 1/4” CTS PE tubing for service replacement has been removed. 1/4” CTS PE pipe and
fittings are no longer approved for installation.
6. Removed detail for locating wire requirements. These requirements are now detailed in Gas Design Standard
A-90.2 and Gas Design Standard A-90.3.
7. Removed branch service installation information covered in Gas Design Standard A-42 and added
Gas Design Standard A-42 as a reference.
8. Added the requirement that any new gas main must be installed at the minimum horizontal distance of 10’ from the
nearest structure.
9. The preferred joining methods in Table 1 have been revised.
10. Added requirement for warning tape in direct burial installations per Gas Design Standard L-16.
11. Revised the bending radius for installed PE pipe in a typical direct-burial plastic main and service installation.
12. Revised Plastic Pipe Stamp in Figure 8 to add SDR/wall thickness.
Asset Type: Distribution
Function: Design, Construction and Maintenance
Gas Design Standard Contact: Gas Design Standard Responsibility List

Page 12 of 13 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Prepared by: AAJ7
Polyethylene Gas Distribution System Design A-90

Rev. #06 02-26-14

Appendix 1 − Application of New Installation and Design Requirements to Qualified


Delayed Applicant Installed Work
This appendix clarifies how to apply various new installation and design requirements to qualified delayed
applicant-installed gas projects, where the gas distribution main backbone and service stubs were installed and
inspected, but the service completions have not been completed for many months or years.
NOTE: This does NOT apply to any “At-risk” projects.
The Company has encountered “delayed” applicant-installed projects (e.g. subdivisions) where the gas distribution
main backbone and service stubs were installed and inspected, but the service completions have not been completed
for many months or years and the system has not been pressurized, energized and accepted by the Company. These
projects must meet the criteria:
S Job designs were previously approved by Company.
S Contracts were executed by the applicant with Company for the project.
S Company has inspected the work to date on the project.
Current installation and design requirements must be applied when a delayed project is actually pressurized and
placed in service.
This appendix addresses the following new requirements:
S Pipe locating requirements
S One-inch diameter services
S 1000-foot maximum spacing between Electrolysis Test Stations (ETS)
S Locating wire gauge requirements for plastic pipe installations
S Pressure testing
1. Locating Requirements
Applicant Installers are required to mark dead end gas mains and gas service stubs as described in Gas Design
Standard A-90.2 and Gas Design Standard A-90.3.
2. One inch services
The Company will accept previously-installed 1/2” services and 1/2” service stubs installed prior to May 1, 2010, if
those services and stubs have the capacity to support the current customer loads.
The gas service stub must be at least 1” in diameter if any of the following conditions exists:
S Customer gas load conditions require a larger size gas service. For example, 1” Excess Flow
Valves (EFVs) and services are required for service lengths of 122 feet or longer, per Gas Design
Standard A-93.3. Please note that Gas Design Standard A-93.3. also directs that EFVs are not to
be installed on stub completions.
S Branch services
S Changed or new customer gas loads that exceed the capacity of the previously designed service.
3. 1,000-ft. maximum spacing between ETS boxes
Applicant Installers are required to install ETS boxes every 1,000 feet (or closer) in accordance with Gas Design
Standard A-90.2.
4. Locating wire gauge requirements for plastic pipe installations
The Company will accept 14-gauge locating wire on existing plastic pipe service installations, installed prior to
August 1, 2009, as long as the wire passes continuity tests. Applicant installers are not required to replace existing
14-gauge wire (that pass continuity tests) with 10-gauge on plastic services and service stubs that have already
been installed. However, all new plastic services and service stubs must be installed with 10-gauge wire in
accordance with Gas Design Standard A-90.2 and Gas Design Standard A-90.3.
5. Pressure Test
Main and stubs are required to be tested per Gas Design Standard A-34.

Prepared by: AAJ7 PG&E Internal Information, SL2 ©2014 Pacific Gas & Electric Company. All Rights Reserved. Page 13 of 13

Das könnte Ihnen auch gefallen