Beruflich Dokumente
Kultur Dokumente
After considering additional releases in the amount of Besides the Real Estate Mortgages, penal clause which is also
P2,659,700.00, made to defendant Moonwalk, an accessory obligation must also be deemed extinguished
defendant Moonwalk delivered to the plaintiff a considering that the principal obligation was considered
promissory note for TWELVE MILLION TWO HUNDRED extinguished, and the penal clause being an accessory
FIFTY FOUR THOUSAND SEVEN HUNDRED PESOS obligation.
(P12,254,700.00) Annex `E', signed by Eusebio T.
Ramos, and the said Rosita U. Alberto and Rosita U. At the time of the payment made of the full obligation on
Alberto; October 10, 1979 together with the 12% interest by defendant-
appellee Moonwalk, its obligation was extinguished. It being
Moonwalk made a total payment of P23,657,901.84 to extinguished, there was no more need for the penal clause.
SSS for the loan principal of P12,254,700.00 released
to it. The last payment made by Moonwalk in the We advance the justification for the decision stating Article
amount of P15,004,905.74 were based on the 169:
Statement of Account;
"Art. 1169. Those obliged to deliver or to do something incur in
Plaintiff issued to defendant Moonwalk the Release of delay from the time the obligee judicially or extrajudicially
Mortgage for Moonwalk's mortgaged properties in demands from them the fulfillment of their obligation." There
Cavite and Rizal; are only three instances when demand is not necessary to
render the obligor in default. These are the following: "(1)
In letters to defendant Moonwalk,plaintiff alleged that When the obligation or the law expressly so declares; (2) When
it committed an honest mistake in releasing from the nature and the circumstances of the obligation it
defendant. appears that the designation of the time when the thing is to
be delivered or the service is to be rendered was a controlling
Ddefendant's counsel told plaintiff that it had motive for the establishment of the contract; or (3) When the
completely paid its obligations to SSS; demand would be useless, as when the obligor has rendered it
beyond his power to perform."
The trial court issued an order dismissing the complaint on
the ground that the obligation was already extinguished by
1
This case does not fall within any of the established exceptions. Toyota Shaw, Inc. later on assigned all its rights and interests
Hence, despite the provision in the promissory note that "(a)ll in the chattel mortgage to petitioner Rizal Commercial
amortization payments shall be made every first five (5) days of Banking Corporation (RCBC).
the calendar month until the principal and interest on the loan
or any portion thereof actually released has been fully paid," 10 All the checks dated April 1991 to January 1993 were
petitioner is not excused from making a demand. It has been thereafter encashed and debited by RCBC from private
established that at the time of payment of the full obligation, respondent's account, except for the check representing the
private respondent Moonwalk has long been delinquent in payment for August 1991, which was unsigned. Previously,
meeting its monthly arrears and in paying the full amount of the amount represented by such check was debited from
the loan itself as the obligation matured sometime in January, private respondent's account but was later recalled and re-
1977. But mere delinquency in payment does not necessarily credited, to him. Because of the recall, the last two checks,
mean delay in the legal concept. To be in default ". . . is dated February 10, 1993 and March 10, 1993, were no longer
different from mere delay in the grammatical sense, because it presented for payment. This was purportedly in conformity
involves the beginning of a special condition or status which with petitioner bank's procedure that once a client's account
has its own peculiar effects or results." was forwarded to its account representative, all remaining
checks outstanding as of the date the account was forwarded
Nowhere in this case did it appear that SSS demanded from were no longer presented for patent.
Moonwalk the payment of its monthly amortizations.What the
complaint itself showed was that SSS tried to enforce the On the theory that respondent defaulted in his payments, the
obligation sometime in September, 1977 by foreclosing the real check representing the payment for August 10, 1991 being
estate mortgages executed by Moonwalk in favor of SSS. But unsigned, petitioner demanded from private respondent the
this foreclosure did not push through upon Moonwalk's payment of the balance of the debt, including liquidated
requests and promises to pay in full.What is clear, therefore, is damages. The latter refused, prompting petitioner to file an
that Moonwalk was never in default because SSS never action for replevin and damages.
compelled performance.
ISSUE: WON private respondent may be held liable for the
Hence, no delay occurred and there was, therefore, no
alleged unpaid amount.
occasion when the penalty became demandable and
enforceable. Since there was no default in the performance of
RULING: NO.
the main obligation — payment of the loan — SSS was never
entitled to recover any penalty, not at the time it made the
Statement of Account and certainly, not after the It bears stressing that a contract of adhesion is just as binding
extinguishment of the principal obligation because then, all the as ordinary contracts. Contracts of adhesion are not
more that SSS had no reason to ask for the penalties. Thus, invalid per se; 7 they are not entirely prohibited. 8 The one
there could never be any occasion for waiver or even mistake in who adheres to the contract is in reality free to reject it
the application for payment because there was nothing for SSS entirely; if he adheres, he gives his consent. 9
to waive as its right to enforce the penalty did not arise.
While ambiguities in a contract of adhesion are to be
construed against the party that prepared the same, 10 this
G.R. No. 133107 March 25, 1999 rule applies only if the stipulations in such contract are
obscure or ambiguous. If the terms thereof are clear and
leave no doubt upon the intention of the contracting
RIZAL COMMERCIAL BANKING CORPORATION, petitioner,
parties, the literal meaning of its stipulations shall
vs.
control. 11 In the latter case, there would be no need for
COURT OF APPEALS and FELIPE LUSTRE, respondents.
construction.
7
That a contract of sale was entered into by the parties contract. The last stage is the consummation of the contract
is not disputed. Petitioner, however, maintains that its wherein the parties fulfill or perform the terms agreed upon
obligation to pay fully the purchase price was extinguished in the contract, culminating in the extinguishment thereof.
because the adverted contract was validly terminated due to
In the instant case, the formal quotation provided by
respondents failure to deliver the cylinder liners within the
respondent represented the negotiation phase of the
two-month period stated in the formal quotation dated 31
subject contract of sale between the parties. As of that time,
May 1989.
the parties had not yet reached an agreement as regards the
The threshold question, then, is: Was there late delivery terms and conditions of the contract of sale of the cylinder
of the subjects of the contract of sale to justify petitioner to liners. Petitioner could very well have ignored the offer or
disregard the terms of the contract considering that time tendered a counter-offer to respondent while the latter could
was of the essence thereof? have, under the pertinent provision of the Civil
Code,[38] withdrawn or modified the same. The parties were
In determining whether time is of the essence in a
at liberty to discuss the provisions of the contract of sale prior
contract, the ultimate criterion is the actual or apparent
to its perfection. In this connection, we turn to the
intention of the parties and before time may be so regarded testimonies of Pajarillo and Kanaan, Jr., that the terms of the
by a court, there must be a sufficient manifestation, either in
offer were, indeed, renegotiated prior to the issuance of
the contract itself or the surrounding circumstances of that
Purchase Order No. 13839.
intention.[29] Petitioner insists that although its purchase
orders did not specify the dates when the cylinder liners were During the hearing of the case on 28 January 1993,
supposed to be delivered, nevertheless, respondent should Pajarillo testified as follows: (I DON'T KNOW IF THIS PORTION
abide by the term of delivery appearing on the quotation it OF THE CASE IS IMPORTANT OR NOT BUT I'M LEAVING IT
submitted to petitioner.[30]Petitioner theorizes that the HERE IN CASE YOU WANT TO READ IT)
quotation embodied the offer from respondent while the
Q: You testified Mr. Witness, that you submitted a
purchase order represented its (petitioners) acceptance of
quotation with defendant Lorenzo Shipping
the proposed terms of the contract of sale.[31] Thus, petitioner
Corporation dated rather marked as Exhibit A
is of the view that these two documents cannot be taken
separately as if there were two distinct contracts.[32] We do stating the terms of payment and delivery of
the cylinder liner, did you not?
not agree.
A: Yes sir.
It is a cardinal rule in interpretation of contracts that if
the terms thereof are clear and leave no doubt as to the Q: I am showing to you the quotation which is
intention of the contracting parties, the literal meaning shall marked as Exhibit A there appears in the
control.[33]However, in order to ascertain the intention of the quotation that the delivery of the cylinder
parties, their contemporaneous and subsequent acts should liner will be made in two months time from
be considered.[34] While this Court recognizes the principle the time you received the confirmation of the
that contracts are respected as the law between the order. Is that correct?
contracting parties, this principle is tempered by the rule that
the intention of the parties is primordial[35] and once the A: Yes sir.
intention of the parties has been ascertained, that element is Q: Now, after you made the formal quotation
deemed as an integral part of the contract as though it has which is Exhibit A how long a time did the
been originally expressed in unequivocal terms.[36] defendant make a confirmation of the order?
HELD: In the present case, we cannot subscribe to the A: After six months.
position of petitioner that the documents, by themselves,
embody the terms of the sale of the cylinder liners. One can Q: And this is contained in the purchase order
easily glean the significant differences in the terms as stated given to you by Lorenzo Shipping
in the formal quotation and Purchase Order No. 13839 with Corporation?
regard to the due date of the down payment for the first
A: Yes sir.
cylinder liner and the date of its delivery as well as Purchase
Order No. 14011 with respect to the date of delivery of the Q: Now, in the purchase order dated November 2,
second cylinder liner. While the quotation provided by 1989 there appears only the date the terms
respondent evidently stated that the cylinder liners were of payment which you required of them of
supposed to be delivered within two months from receipt of 25% down payment, now, it is stated in the
the firm order of petitioner and that the 25% down payment purchase order the date of delivery, will you
was due upon the cylinder liners delivery, the purchase explain to the court why the date of delivery
orders prepared by petitioner clearly omitted these of the cylinder liner was not mentioned in the
significant items. The petitioners Purchase Order No. 13839 purchase order which is the contract between
made no mention at all of the due dates of delivery of the you and Lorenzo Shipping Corporation?
first cylinder liner and of the payment of 25% down payment.
Its Purchase Order No. 14011 likewise did not indicate the A: When Lorenzo Shipping Corporation inquired
due date of delivery of the second cylinder liner. from us for that cylinder liner, we have
inquired [with] our supplier in Japan to give
In the case of Bugatti v. Court of Appeals,[37] we us the price and delivery of that item. When
reiterated the principle that [a] contract undergoes three we received that quotation from our supplier
distinct stages preparation or negotiation, its perfection, and it is stated there that they can deliver within
finally, its consummation. Negotiation begins from the time two months but we have to get our
the prospective contracting parties manifest their interest in confirmed order within June.
the contract and ends at the moment of agreement of the
parties. The perfection or birth of the contract takes place Q: But were you able to confirm the order from
when the parties agree upon the essential elements of the your Japanese supplier on June of that year?
8
A: No sir. caused by the latter when it omitted the date of delivery of
the cylinder liners in the purchase orders and varied the term
Q: Why? Will you tell the court why you were not
with respect to the due date of the down payment,[41] said
able to confirm your order with your obscurity must be resolved against it.[42]
Japanese supplier?
Relative to the above discussion, we find the case
A: Because Lorenzo Shipping Corporation did not
of Smith, Bell & Co., Ltd. v. Matti,[43] instructive. There, we
give us the purchase order for that cylinder
held that
liner.
Q: And it was only on November 2, 1989 when When the time of delivery is not fixed or is stated in general
they gave you the purchase order? and indefinite terms, time is not of the essence of the
contract. . . .
A: Yes sir.
Q: So upon receipt of the purchase order from In such cases, the delivery must be made within a reasonable
Lorenzo Shipping Lines in 1989 did you time.
confirm the order with your Japanese
supplier after receiving the purchase order The law implies, however, that if no time is fixed, delivery
dated November 2, 1989? shall be made within a reasonable time, in the absence of
anything to show that an immediate delivery intended. . . .
A: Only when Lorenzo Shipping Corporation will
give us the down payment of 25%.[39]
We also find significant the fact that while petitioner
For his part, during the cross-examination conducted by alleges that the cylinder liners were to be used for dry dock
counsel for petitioner, Kanaan, Jr., testified in the following repair and maintenance of its M/V Dadiangas Express
manner: between the later part of December 1989 to early January
1990, the record is bereft of any indication that respondent
WITNESS: This term said 25% upon delivery.
was aware of such fact. The failure of petitioner to notify
Subsequently, in the final contract, what was
respondent of said date is fatal to its claim that time was of
agreed upon by both parties was 25% down
the essence in the subject contracts of sale.
payment.
In addition, we quote, with approval, the keen
Q: When?
observation of the Court of Appeals:
A: Upon confirmation of the order.
......................
...
Q: And when was the down payment supposed to In the instant case, the appellee should have provided for an
be paid? allowance of time and made the purchase order earlier if
indeed the said cylinder liner was necessary for the repair of
A: It was not stated when we were supposed to the vessel scheduled on the first week of January, 1990. In
receive that. Normally, we expect to receive fact, the appellee should have cancelled the first purchase
at the earliest possible time. Again, that order when the cylinder liner was not delivered on the date it
would depend on the customers. Even after now says was necessary. Instead it issued another purchase
receipt of the purchase order which was what order for the second set of cylinder liner. This fact negates
happened here, they re-negotiated the terms appellees claim that time was indeed of the essence in the
and sometimes we do accept that. consummation of the contract of sale between the
Q: Was there a re-negotiation of this term? parties.[44]
A: This offer, yes. We offered a final requirement Finally, the ten postdated checks issued in November
of 25% down payment upon delivery. 1989 by petitioner and received by the respondent as full
Q: What was the re-negotiated term? payment of the purchase price of the first cylinder liner
supposed to be delivered on 02 January 1990 fail to impress.
A: 25% down payment It is not an indication of failure to honor a commitment on
the part of the respondent. The earliest maturity date of the
Q: To be paid when?
checks was 18 January 1990. As delivery of said checks could
A: Supposed to be paid upon order.[40] produce the effect of payment only when they have been
cashed,[45] respondents obligation to deliver the first cylinder
The above declarations remain unassailed. Other than
liner could not have arisen as early as 02 January 1990 as
its bare assertion that the subject contracts of sale did not
claimed by petitioner since by that time, petitioner had yet to
undergo further renegotiation, petitioner failed to proffer
fulfill its undertaking to fully pay for the value of the first
sufficient evidence to refute the above testimonies of cylinder liner. As explained by respondent, it proceeded with
Pajarillo and Kanaan, Jr.
the placement of the order for the cylinder liners with its
Notably, petitioner was the one who caused the principal in Japan solely on the basis of its previously
preparation of Purchase Orders No. 13839 and No. 14011 yet harmonious business relationship with petitioner.
it utterly failed to adduce any justification as to why said
As an aside, let it be underscored that [e]ven where
documents contained terms which are at variance with those
time is of the essence, a breach of the contract in that
stated in the quotation provided by respondent. The only
respect by one of the parties may be waived by the other
plausible reason for such failure on the part of petitioner is
partys subsequently treating the contract as still in
that the parties had, in fact, renegotiated the proposed terms
force.[46] Petitioners receipt of the cylinder liners when they
of the contract of sale. Moreover, as the obscurity in the
were delivered to its warehouse on 20 April 1990 clearly
terms of the contract between respondent and petitioner was
9
indicates that it considered the contract of sale to be still In the first quarter of 1998, petitioner, Solar
subsisting up to that time. Indeed, had the contract of sale Harvest, Inc., entered into an agreement with
been cancelled already as claimed by petitioner, it no longer respondent, Davao Corrugated Carton Corporation, for
had any business receiving the cylinder liners even if said the purchase of corrugated carton boxes, specifically
receipt was subject to verification. By accepting the cylinder designed for petitioner's business of exporting fresh
liners when these were delivered to its warehouse, petitioner bananas, at US$1.10 each. The agreement was not
indisputably waived the claimed delay in the delivery of said reduced into writing. To get the production underway,
items. petitioner deposited, on March 31, 1998, US$40,150.00
in respondent's US Dollar Savings Account with
We, therefore, hold that in the subject contracts, time
Westmont Bank, as full payment for the ordered boxes.
was not of the essence. The delivery of the cylinder liners
on 20 April 1990 was made within a reasonable period of Despite such payment, petitioner did not
time considering that respondent had to place the order for receive any boxes from respondent. On January 3, 2001,
the cylinder liners with its principal in Japan and that the petitioner wrote a demand letter for reimbursement of
latter was, at that time, beset by heavy volume of work.[47] the amount paid. 3 On February 19, 2001, respondent
replied that the boxes had been completed as early as
There having been no failure on the part of the April 3, 1998 and that petitioner failed to pick them up
respondent to perform its obligation, the power to rescind from the former's warehouse 30 days from completion,
the contract is unavailing to the petitioner. Article 1191 of as agreed upon. Respondent mentioned that petitioner
the New Civil Code runs as follows: even placed an additional order of 24,000 boxes, out of
which, 14,000 had been manufactured without any
The power to rescind obligations is implied in reciprocal advanced payment from petitioner. Respondent then
ones, in case one of the obligors should not comply with demanded petitioner to remove the boxes from the
what is incumbent upon him. factory and to pay the balance of US$15,400.00 for the
additional boxes and P132,000.00 as storage fee.
The law explicitly gives either party the right to rescind
In reply, petitioner denied that it made a second
the contract only upon the failure of the other to perform the
order of 24,000 boxes and that respondent already
obligation assumed thereunder.[48] The right, however, is not
completed the initial order of 36,500 boxes and 14,000
an unbridled one.
boxes out of the second order. It maintained that
In other words, the party who deems the contract respondent only manufactured a sample of the ordered
violated may consider it resolved or rescinded, and act boxes and that respondent could not have produced
accordingly, without previous court action, but it proceeds at 14,000 boxes without the required pre-payments. 6
its own risk. For it is only the final judgment of the
During trial, petitioner presented Que as its sole
corresponding court that will conclusively and finally settle witness. Que testified that he ordered the boxes from
whether the action taken was or was not correct in law. But
respondent and deposited the money in respondent's
the law definitely does not require that the contracting party
account. 7 He specifically stated that, when he visited
who believes itself injured must first file suit and wait for a
respondent's factory, he saw that the boxes had no print
judgment before taking extrajudicial steps to protect its of petitioner's logo. 8 A few months later, he followed-up
interest. Otherwise, the party injured by the others breach
the order and was told that the company had full
will have to passively sit and watch its damages accumulate
production, and thus, was promised that production of
during the pendency of the suit until the final judgment of
the order would be rushed. He told respondent that it
rescission is rendered when the law itself requires that he
should indeed rush production because the need for the
should exercise due diligence to minimize its own
boxes was urgent. Thereafter, he asked his partner,
damages.[50]
Alfred Ong, to cancel the order because it was already
Here, there is no showing that petitioner notified late for them to meet their commitment to ship the
respondent of its intention to rescind the contract of sale bananas to China. 9 On cross-examination, Que further
between them. Quite the contrary, respondents act of testified that China Zero Food, the Chinese company that
proceeding with the opening of an irrevocable letter of credit ordered the bananas, was sending a ship to Davao to get
on 23 February 1990 belies petitioners claim that it notified the bananas, but since there were no cartons, the ship
respondent of the cancellation of the contract of sale. Truly, could not proceed. He said that, at that time, bananas
no prudent businessman would pursue such action knowing from Tagum Agricultural Development Corporation
that the contract of sale, for which the letter of credit was (TADECO) were already there. He denied that petitioner
opened, was already rescinded by the other party. made an additional order of 24,000 boxes. He explained
that it took three years to refer the matter to counsel
WHEREFORE, premises considered, the instant Petition because respondent promised to pay. 10
for Review on Certiorari is DENIED. The Decision of the Court
of Appeals, dated 28 April 2000, and its Resolution, dated 06 For respondent, BienvenidoEstanislao
October 2000, are hereby AFFIRMED. No costs. (Estanislao) testified that he met Que in Davao in
October 1998 to inspect the boxes and that the latter got
samples of them. In February 2000, they inspected the
[G.R. No. 176868. July 26, 2010.] boxes again and Que got more samples. Estanislao said
that petitioner did not pick up the boxes because the
SOLAR HARVEST, INC., petitioner, vs. ship did not arrive. 11 Jaime Tan (Tan), president of
DAVAO CORRUGATED CARTON respondent, also testified that his company finished
CORPORATION, respondent. production of the 36,500 boxes on April 3, 1998 and that
petitioner made a second order of 24,000 boxes. He said
that the agreement was for respondent to produce the
FACTS: boxes and for petitioner to pick them up from the
warehouse. 12 He also said that the reason why
10
petitioner did not pick up the boxes was that the ship demands from them the fulfillment of
that was to carry the bananas did not their obligation.
arrive. 13 According to him, during the last visit of Que
and Estanislao, he asked them to withdraw the boxes Evident from the records and even from the
immediately because they were occupying a big space in allegations in the complaint was the lack of demand by
his plant, but they, instead, told him to sell the cartons as petitioner upon respondent to fulfill its obligation to
rejects. He was able to sell 5,000 boxes at P20.00 each manufacture and deliver the boxes. The Complaint only
for a total of P100,000.00. They then told him to apply alleged that petitioner made a "follow-up" upon
the said amount to the unpaid balance. respondent, which, however, would not qualify as a
demand for the fulfillment of the obligation. Petitioner's
In its March 2, 2004 Decision, the Regional Trial witness also testified that they made a follow-up of the
Court (RTC) ruled that respondent did not commit any boxes, but not a demand. Note is taken of the fact that,
breach of faith that would justify rescission of the with respect to their claim for reimbursement, the
contract and the consequent reimbursement of the Complaint alleged and the witness testified that a
amount paid by petitioner. The RTC said that respondent demand letter was sent to respondent. Without a
was able to produce the ordered boxes but petitioner previous demand for the fulfillment of the obligation,
failed to obtain possession thereof because its ship did petitioner would not have a cause of action for
not arrive. It thus dismissed the complaint and rescission against respondent as the latter would not
respondent's counterclaims, disposing as follows: yet be considered in breach of its contractual obligation.
Petitioner filed a notice of appeal with the CA. As correctly observed by the CA, aside from the
On September 21, 2006, the CAdenied the pictures of the finished boxes and the production report
appeal for lack of merit. 15 The appellate court held that thereof, there is ample showing that the boxes had
petitioner failed to discharge its burden of proving what already been manufactured by respondent. There is the
it claimed to be the parties' agreement with respect to testimony of Estanislao who accompanied Que to the
the delivery of the boxes. According to the CA, it was factory, attesting that, during their first visit to the
unthinkable that, over a period of more than two years, company, they saw the pile of petitioner's boxes and Que
petitioner did not even demand for the delivery of the took samples thereof. Que, petitioner's witness, himself
boxes. The CA added that even assuming that the confirmed this incident. He testified that Tan pointed the
agreement was for respondent to deliver the boxes, boxes to him and that he got a sample and saw that it
respondent would not be liable for breach of contract as was blank. Que's absolute assertion that the boxes were
petitioner had not yet demanded from it the delivery of not manufactured is, therefore, implausible and
the boxes. 16 suspicious.
ISSUE:WON Solar Harvest, Inc. may rescind the contract. In sum, the Court finds that petitioner failed to establish a
cause of action for rescission, the evidence having shown that
HELD:NO. respondent did not commit any breach of its contractual
Petitioner's claim for reimbursement is actually obligation. As previously stated, the subject boxes are still
one for rescission (or resolution) of contract under Article within respondent's premises. To put a rest to this dispute,
1191 of the Civil Code, which reads: we therefore relieve respondent from the burden of having
to keep the boxes within its premises and, consequently, give
Art. 1191. The power to rescind it the right to dispose of them, after petitioner is given a
obligations is implied in reciprocal ones, period of time within which to remove them from the
in case one of the obligors should not premises.
comply with what is incumbent upon him.
NOTE: Yung case involves breach of contract, contract
The injured party may choose between
talagasiyabeshybakai-judge niyoakonamaliyung digest ko.
the fulfillment and the rescission of the
Walakasing topic nanakalagay kung saang topic siyamagfa-fall
obligation, with the payment of damages
so i-assume nasa Art. 1170 itong case naito – Fraud and
in either case. He may also seek
damages.
rescission, even after he has chosen
fulfillment, if the latter should become
[G.R. No. 150843. March 14, 2003]
impossible.
The court shall decree the rescission CATHAY PACIFIC AIRWAYS, LTD., petitioner, vs. SPOUSES
claimed, unless there be just cause DANIEL VAZQUEZ and MARIA LUISA MADRIGAL
authorizing the fixing of a period. VAZQUEZ, respondents.
13
(1)Yes. The upgrading Cathay breached its contract of The Court of Appeals awarded each of the Vazquezes
carriage with Vazquezes, who declined said upgrade, since moral damages in the amount of P250,000. Article 2220 of
Cathay insisted to the upgrade. the Civil Code provides:
A contract is a meeting of minds between two persons
Article 2220. Willful injury to property may be a legal ground
whereby one agrees to give something or render some
for awarding moral damages if the court should find that,
service to another for a consideration. There is no contract
under the circumstances, such damages are justly due. The
unless the following requisites concur: (1) consent of the
same rule applies to breaches of contract where the
contracting parties; (2) an object certain which is the subject
defendant acted fraudulently or in bad faith.
of the contract; and (3) the cause of the obligation which is
established.[4] Undoubtedly, a contract of carriage existed
between Cathay and the Vazquezes. They voluntarily and Moral damages include physical suffering, mental
freely gave their consent to an agreement whose object was anguish, fright, serious anxiety, besmirched reputation,
the transportation of the Vazquezes from Manila to Hong wounded feelings, moral shock, social humiliation, and similar
Kong and back to Manila, with seats in the Business Class injury. Although incapable of pecuniary computation, moral
Section of the aircraft, and whose cause or consideration was damages may be recovered if they are the proximate result
the fare paid by the Vazquezes to Cathay. of the defendants wrongful act or omission.[11] Thus, case
law establishes the following requisites for the award of
The only problem is the legal effect of the upgrading of moral damages: (1) there must be an injury clearly sustained
the seat accommodation of the Vazquezes. Did it constitute a by the claimant, whether physical, mental or psychological;
breach of contract? (2) there must be a culpable act or omission factually
established; (3) the wrongful act or omission of the defendant
Breach of contract is defined as the failure without legal
is the proximate cause of the injury sustained by the
reason to comply with the terms of a contract.[5] It is also
claimant; and (4) the award for damages is predicated on any
defined as the [f]ailure, without legal excuse, to perform any
of the cases stated in Article 2219 of the Civil Code.[12]
promise which forms the whole or part of the contract. [6]
Moral damages predicated upon a breach of contract
In previous cases, the breach of contract of carriage
of carriage may only be recoverable in instances where the
consisted in either the bumping off of a passenger with
carrier is guilty of fraud or bad faith or where the mishap
confirmed reservation or the downgrading of a passengers
resulted in the death of a passenger.[13] Where in breaching
seat accommodation from one class to a lower class. In this
the contract of carriage the airline is not shown to have acted
case, what happened was the reverse. The contract between
fraudulently or in bad faith, liability for damages is limited to
the parties was for Cathay to transport the Vazquezes to
the natural and probable consequences of the breach of the
Manila on a Business Class accommodation in Flight CX-
obligation which the parties had foreseen or could have
905. After checking-in their luggage at the Kai Tak Airport in
reasonably foreseen. In such a case the liability does not
Hong Kong, the Vazquezes were given boarding cards
include moral and exemplary damages.[14]
indicating their seat assignments in the Business Class
Section. However, during the boarding time, when the In this case, we have ruled that the breach of contract
Vazquezes presented their boarding passes, they were of carriage, which consisted in the involuntary upgrading of
informed that they had a seat change from Business Class to the Vazquezes seat accommodation, was not attended by
First Class. It turned out that the Business Class was fraud or bad faith. The Court of Appeals award of moral
overbooked in that there were more passengers than the damages has, therefore, no leg to stand on.
number of seats. Thus, the seat assignments of the Vazquezes
were given to waitlisted passengers, and the Vazquezes, The deletion of the award for exemplary damages by
being members of the Marco Polo Club, were upgraded from the Court of Appeals is correct. It is a requisite in the grant of
Business Class to First Class. exemplary damages that the act of the offender must be
accompanied by bad faith or done in wanton, fraudulent or
We note that in all their pleadings, the Vazquezes never malevolent manner.[15] Such requisite is absent in this case.
denied that they were members of Cathays Marco Polo Club. Moreover, to be entitled thereto the claimant must first
They knew that as members of the Club, they had priority for establish his right to moral, temperate, or compensatory
upgrading of their seat accommodation at no extra cost when damages.[16] Since the Vazquezes are not entitled to any of
an opportunity arises. But, just like other privileges, such these damages, the award for exemplary damages has no
priority could be waived. The Vazquezes should have been legal basis. And where the awards for moral and exemplary
consulted first whether they wanted to avail themselves of damages are eliminated, so must the award for attorneys
the privilege or would consent to a change of seat fees.[17]
accommodation before their seat assignments were given to
other passengers. Normally, one would appreciate and The most that can be adjudged in favor of the Vazquezes
accept an upgrading, for it would mean a better for Cathays breach of contract is an award for nominal
accommodation. But, whatever their reason was and damages under Article 2221 of the Civil Code, which reads as
however odd it might be, the Vazquezes had every right to follows:
decline the upgrade and insist on the Business Class
accommodation they had booked for and which was Article 2221 of the Civil Code provides:
designated in their boarding passes. They clearly waived
their priority or preference when they asked that other Article 2221. Nominal damages are adjudicated in order that
passengers be given the upgrade. It should not have been a right of the plaintiff, which has been violated or invaded by
imposed on them over their vehement objection. By the defendant, may be vindicated or recognized, and not for
insisting on the upgrade, Cathay breached its contract of the purpose of indemnifying the plaintiff for any loss suffered
carriage with the Vazquezes. by him.
14
upgrading their Business Class accommodation to First Class commercial establishments beneath the NPC transmission
because of their valued status as Marco Polo members, we lines along Baesa, Quezon City. After deliberating on NPC's
reduce the award for nominal damages to P5,000. letter, Meralco decided to comply with NPC's requestand
thereupon issued notices of disconnection to all
Before writing finis to this decision, we find it well-worth
establishments affected including plaintiffs Leoncio Ramoy,
to quote the apt observation of the Court of Appeals
Matilde Ramoy/Matild, Rosemarie Ramoy, Ofelia Durian, Jose
regarding the awards adjudged by the trial court:
Valiza, and Cyrene S. Panado.
We are not amused but alarmed at the lower courts Plaintiff Leoncio Ramoy testified that he and his wife are the
unbelievable alacrity, bordering on the scandalous, to award registered owners of a parcel of land covered by TCT No.
excessive amounts as damages. In their complaint, appellees 326346, a portion of which was occupied by plaintiffs
asked for P1 million as moral damages but the lower court Rosemarie Ramoy, Ofelia Durian, Jose Valiza and Cyrene S.
awarded P4 million; they asked for P500,000.00 as exemplary Panado as lessees. When the Meralco employees were
damages but the lower court cavalierly awarded a disconnecting plaintiffs' power connection, plaintiffLeoncio
whooping P10 million; they asked for P250,000.00 as Ramoy objected by informing the Meralco foreman that his
attorneys fees but were awarded P2 million; they did not ask property was outside the NPC property and pointing out the
for nominal damages but were awarded P200,000.00. It is as monuments showing the boundaries of his property.
if the lower court went on a rampage, and why it acted that However, he was threatened and told not to interfere by the
way is beyond all tests of reason. In fact the excessiveness of armed men who accompanied the Meralco employees. After
the total award invites the suspicion that it was the result of the electric power in Ramoy's apartment was cut off, the
prejudice or corruption on the part of the trial court. plaintiffs-lessees left the premises.
The presiding judge of the lower court is enjoined to hearken During the ocular inspection ordered by the Court and
to the Supreme Courts admonition in Singson vs. CA (282 attended by the parties, it was found out that the residence
SCRA 149 [1997]), where it said: of plaintiffs-spouses Leoncio and Matilde Ramoy was indeed
outside the NPC property.The record also shows that at the
The well-entrenched principle is that the grant of moral request of NPC, defendant Meralco re-connected the electric
damages depends upon the discretion of the court based on service of four customers previously disconnected none of
the circumstances of each case. This discretion is limited by whom was any of the plaintiffs.
the principle that the amount awarded should not be
palpably and scandalously excessive as to indicate that it was The RTC decided in favor of MERALCO by dismissing herein
the result of prejudice or corruption on the part of the trial respondents' claim for moral damages, exemplary damages
court. and attorney's fees. However, the RTC ordered MERALCO to
restore the electric power supply of
and in Alitalia Airways vs. CA (187 SCRA 763 [1990], where it respondents.Respondents then appealed to the CA on
was held: grounds that it erred in finding MERALCO not negligent when
it disconnected power supply and in not awarding damages
Nonetheless, we agree with the injunction expressed by the to defendants.
Court of Appeals that passengers must not prey on
international airlines for damage awards, like trophies in a ISSUE: WON MERALCO is liable for damages
safari. After all neither the social standing nor prestige of the
passenger should determine the extent to which he would Ruling:
suffer because of a wrong done, since the dignity affronted in
the individual is a quality inherent in him and not conferred YES. Clearly, respondents' cause of action against MERALCO is
by these social indicators. [19] anchored on culpa contractual or breach of contract for the
latter's discontinuance of its service to respondents under
Article 1170 of the Civil Code which provides:
MERALCO V Ramoy
Article 1170. Those who in the performance of their
MANILA ELECTRIC COMPANY, Petitioner, vs.
obligations are guilty of fraud, negligence, or delay, and those
MATILDEMACABAGDAL RAMOY, BIENVENIDO RAMOY,
who in any manner contravene the tenor thereof, are liable
ROMANA RAMOY-RAMOS, ROSEMARIE RAMOY, OFELIA
for damages.
DURIAN and CYRENE PANADO, Respondents.
Facts:
In culpa contractual x x x the mere proof of the existence of
the contract and the failure of its compliance justify, prima
The evidence on record has established that in the year 1987
facie, a corresponding right of relief. The law, recognizing the
the National Power Corporation (NPC) filed with the MTC
obligatory force of contracts, will not permit a party to be set
Quezon City a case for ejectment against several persons
free from liability for any kind of misperformance of the
allegedly illegally occupying its properties in Baesa, Quezon
contractual undertaking or a contravention of the tenor
City. Among the defendants in the ejectment case was
thereof. A breach upon the contract confers upon the injured
Leoncio Ramoy, one of the plaintiffs in the case at bar.
party a valid cause for recovering that which may have been
lost or suffered. The remedy serves to preserve the interests
The MTC Branch 36, Quezon City rendered judgment for the
of the promissee that may include his "expectation interest,"
plaintiff [MERALCO] and "ordering the defendants to
which is his interest in having the benefit of his bargain by
demolish or remove the building and structures they built on
being put in asgood a position as he would have been in had
the land of the plaintiff and to vacate the premises."
the contract been performed, or his "reliance interest," which
is his interest in being reimbursed for loss caused by reliance
NPC wrote Meralco requesting for the "immediate
on the contract by being put in as good a position as he would
disconnection of electric power supply to all residential and
15
have been in had the contract not been made; or his If payment is made to our office, demand
"restitution interest," which is his interest in having restored for an OFFICIAL RECEIPT.
to him any benefit that he has conferred on the other party.
Indeed, agreements can accomplish little, either for their On December 17, 1984, respondent insurance company
makers or for society, unless they are made the basis for issued collector's provisional receipt No. 9300 to petitioner-
action. The effect of every infraction is to create a new duty, insured for the amount of P1,609.65 3 On the lower portion of
that is, to make recompense to the one who has been injured the receipt the following is written in capital letters:
by the failure of another to observe his contractual obligation
unless he can show extenuating circumstances, like proof of Note: This collector's provisional receipt will
his exercise of due diligence x x x or of the attendance of be confirmed by our official receipt. If our
fortuitous event, to excuse him from his ensuing liability. official receipt is not received by you within
7 days, please notify us. 4
Article 1173 also provides that the fault or negligence of the
obligor consists in the omission of that diligence which is
On June 29, 1985, respondent insurance company, through
required by the nature of the obligation and corresponds with
manager, Teofilo M. Malapit, sent petitioner-insured
the circumstances of the persons, of the time and of the
Endorsement No. BG-002/85 which "cancelled flat" Policy No.
place.
PA BG-20015 "for non-payment of premium effective as of
inception dated." 5 The same endorsement also credited "a
To repeat, it was not enough for MERALCO to merely rely on
return premium of P1,609.65 plus documentary stamps and
the Decision of the MTC without ascertaining whether it had
premium tax" to the account of the insured. Shocked by the
become final and executory. Moreover, if it were true that
cancellation of the policy, petitioner-insured confronted
the decision was final and executory, the most prudent thing
Carlito Ang, agent of respondent insurance company, and
for MERALCO to have done was to coordinate with the proper
demanded the issuance of an official receipt. Ang told
court officials in determining which structures are covered by
petitioner-insured that the cancellation of the policy was a
said court order. Likewise, there is no evidence on record to
mistake but he would personally see to its rectification.
show that this was done by MERALCO.
However, petitioner-insured failed to receive any official
receipt from Prudential.
The utmost care and diligence required of MERALCO
necessitates such great degree of prudence on its part, and
petitioner-insured sent respondent insurance company a
failure to exercise the diligence required means that
letter demanding that he be insured under the same terms
MERALCO was at fault and negligent in the performance of its
and conditions as those contained in Policy No. PA-BG-20015
obligation.
commencing upon its receipt of his letter, or that the current
commercial rate of increase on the payment he had made
This being so, MERALCO is liable for damages under Article
under provisional receipt No. 9300 be returned within five
1170 of the Civil Code.
days. 6 Areola also warned that should his demands be
unsatisfied, he would sue for damages.
G.R. No. 95641 September 22, 1994
On July 17, 1985, he received a letter from production
manager Malapit informing him that the "partial payment" of
SANTOS B. AREOLA and LYDIA D. AREOLA, petitioners-
P1,000.00 he had made on the policy had been "exhausted
appellants,
pursuant to the provisions of the Short Period Rate Scale".
vs.
Malapit warned Areola that should be fail to pay the balance,
COURT OF APPEALS and PRUDENTIAL GUARANTEE AND
the company's liability would cease to operate. 7
ASSURANCE, INC., respondents-appellees.
Assistant Vice President emphasized that the official receipt
FACTS:
should have been issued seven days from the issuance of the
provisional receipt but because no official receipt had been
Petitioner-insured, Santos Areola, a lawyer from Dagupan issued in Areola's name, there was reason to believe that no
City, bought from Prudential Guarantee and Assurance, Inc. payment had been made. Apologizing for the inconvenience,
(hereinafter referred to as Prudential), a personal accident Ampil expressed the company's concern by agreeing "to hold
insurance policy covering the one-year period between noon you cover (sic) under the terms of the referenced policy until
of November 28, 1984 and noon of November 28, such time that this matter is cleared." 8
1985. 1 Under the terms of the statement of account issued
by respondent insurance company, petitioner-insured was
On August 3, 1985, Ampil wrote Areola another letter
supposed to pay the total amount of P1,609.65. At the lower
confirming that the amount of P1,609.65 was in fact received
left-hand corner of the statement of account, the following is
by Prudential on December 17, 1984. Hence, Ampil informed
legibly printed:
Areola that Prudential was "amenable to extending the
insurance coverage up to December 17, 1985 or one year
This Statement of Account must not be from the date when payment was received." Apologizing
considered a receipt. Official Receipt will be again for the inconvenience caused Areola, Ampil exhorted
issued to you upon payment of this account. him to indicate his conformity to the proposal by signing on
the space provided for in the letter. 9
If payment is made to our representative,
demand for a Provisional Receipt and if our The letter was personally delivered by Carlito Ang to Areola
Official Receipts is (sic) not received by you on August 13, 1985 10 but unfortunately, Areola and his wife,
within 7 days please notify us. Lydia, as early as August 6, 1985 had filed a complaint for
breach of contract with damages before the lower court.
16
In its Answer, respondent insurance company admitted that latter. The construction will cost P60,000 which Herce agreed
the cancellation of petitioner-insured's policy was due to the upon. Pursuant to the agreement, Herce paid the down
failure of Malapit to turn over the premiums collected. payment of P30,000 and an installment payment of P15,000,
However, it argued that, by acknowledging the inconvenience leaving a balance of P15,000.
caused on petitioner-insured and after reinstating the Due to the refusal and failure of respondent to pay for
cancelled policy prior to the filing of the complaint, the balance, petitioner filed a complaint to collect the
respondent insurance company had complied with its amount.
obligation under the contract. Hence, it concluded that Respondent denied the claim saying that he had already
petitioner-insured no longer has a cause of action against it, paid the amount to the San Pedro General Merchandising Inc.
therefore cannot be held liable for damages arising from (SPGMI) which constructed the deep well to which the
breach of contract, having demonstrated fully well its windmill system was to be connected. According to him, since
fulfillment of its obligation. the deep well is part of the system, the payment should be
credited to his account by the petitioner. Moreover, the
ISSUE: WON Areola may sue Prudential for damages. balance should also be offset by the defects in the windmill
system which caused the structure to collapse after their
RULING: YES. place was hit by a strong wind.
Petitioner denied that the deep well was included in the
contract, that the P60,000 covered only the windmill
Malapit's fraudulent act of misappropriating the premiums
assembly. He also disowned any obligation to repair or
paid by petitioner-insured is beyond doubt directly imputable
reconstruct the system since it was delivered in good
to respondent insurance company. A corporation, such as
condition, and the collapse was due to a typhoon, a force
respondent insurance company, acts solely thru its
majeure, thus cannot be held liable.
employees. The latters' acts are considered as its own for
The trial court found that the deep well was not
which it can be held to account.
included in the contract. And that the petitioner has no
obligation to reconstruct the windmill since there was no
Consequently, respondent insurance company is liable by way
convincing proof that the same collapsed due to a defect.
of damages for the fraudulent acts committed by Malapit. Its
The CA, on the other hand, ruled that the contract
earlier act of reinstating the insurance policy can not
mentioned of the term deep well and thus part of the
obliterate the injury inflicted on petitioner-insured.
agreement. And it rejected the claim of force majeure,
Respondent company should be reminded that a contract of
commanding petitioner to reconstruct the windmill.
insurance creates reciprocal obligations for both insurer and
insured. Reciprocal obligations are those which arise from the
Issue: (pertinent to the topic)
same cause and in which each party is both a debtor and a
WON petitioner is obliged to rebuild or reconstruct the
creditor of the other, such that the obligation of one is
windmill system
dependent upon the obligation of the other.
Held:
Under the law governing reciprocal obligations, particularly Yes. Art 1174 of the Civil Code states that the event
the second paragraph of Article 1191, the injured party, should be the sole and proximate cause of the loss or
petitioner-insured in this case, is given a choice between destruction of the object of the contract. In Nakpil vs. CA,
fulfillment or rescission of the obligation in case one of the four(4) requisites must concur: (a) the cause of the breach of
obligors, such as respondent insurance company, fails to the obligation must be independent of the will of the debtor;
comply with what is incumbent upon him. However, said (b) the event must be either unforeseeable or unavoidable;
article entitles the injured party to payment of damages, (c) the event must be such as to render it impossible for the
regardless of whether he demands fulfillment or rescission debtor to fulfill his obligation in a normal manner; and (d) the
of the obligation. debtor must be free from any participation in or aggravation
of the injury to the creditor.
The nature of damages to be awarded, however, would be in Petitioner failed to show that the collapse of the
the form of nominal damages. Although the erroneous windmill was due solely to a fortuitous event. The evidence
cancellation of the insurance policy constituted a breach of does not even disclose that there was a typhoon on the day
contract, private respondent insurance company, within a the windmill collapsed. Petitioner merely stated the presence
reasonable time took steps to rectify the wrong committed by of a “strong wind.” But the strong wind cannot be considered
reinstating the insurance policy of petitioner. Moreover, no in this case as fortuitous nor unforeseeable nor unavoidable.
actual or substantial damage or injury was inflicted on On the contrary windmills are build in areas where there is a
petitioner Areola at the time the insurance policy was presence of strong winds, otherwise windmills will not work.
cancelled. Nominal damages are "recoverable where a legal Moreover, the windmill system is newly constructed, it is less
right is technically violated and must be vindicated against an likely to collapse unless it has an inherent defect.
invasion that has produced no actual present loss of any kind,
or where there has been a breach of contract and no
substantial injury or actual damages whatsoever have been or NAKPIL & SONS V. COURT OF APPEALS
can be shown.
FACTS
Yes. The Commissioner said that even if it can be proved that According to Justice Hugo E. Gutierrez, [gandangsinabinya as
the defects in the construction alone (and not in the plans a whole huhu, sayangkinailangankoicutkasi di
and design) caused the damage to the building, still the namanimportantelahat, magandalanghahaha]“x xxThe
deficiency in the original design and jack of specific provisions evidence reveals defects and deficiencies in design and
against torsion in the original plans and the overload on the construction. There is no mystery about these acts of
ground floor columns (found by an the experts including the negligence. The collapse of the PBA building was no wonder
original designer) certainly contributed to the damage which performed by God. It was a result of the imperfections in the
occurred. work of the architects and the people in the construction
company. The findings of the lower Court on the cause of the
The applicable law governing the rights and liabilities of the collapse are more rational and accurate. Instead of laying the
parties herein is Article 1723 of the New Civil Code. On the blame solely on the motions and forces generated by the
other hand, the general rule is that no person shall be earthquake, it also examined the ability of the PBA building,
responsible for events which could not be foreseen or which as designed and constructed, to withstand and successfully
though foreseen, were inevitable (Article 1174, New Civil weather those forces.
Code). There is no dispute that the earthquake of August 2,
1968 is a fortuitous event or an act of God. To exempt the As already discussed, the destruction was not purely an act of
obligor from liability under Article 1174 of the Civil Code, for God. Truth to tell hundreds of ancient buildings in the vicinity
were hardly affected by the earthquake. Only one thing spells
18
out the fatal difference; gross negligence and evident bad decision to either court in expectation of favorable judgment,
faith in the performance of their respective tasks, without but with intent of attacking its jurisdiction should the decision
which the damage would not have occurred. be unfavorable (Tyson Tan, et al. vs. Filipinas Compañia de
Seguros) et al., L-10096, Res. on Motion to Reconsider, March
Defendant and third-party defedants are hereby solidarily 23, 1966). Consequently, we are limited in this appeal to the
liable under Art. 1723. issues of law raised in the appellant's brief.
FACTS: The present case comes by direct appeal from a 2) Whether or not it was error for the Court to have
decision of the Court of First Instance of Manila (Case No. permitted the plaintiff-appellee to introduce
44572) adjudging the defendant-appellant, Luzon Stevedoring additional evidence of damages after said party had
Corporation, liable in damages to the plaintiff-appellee rested its case.
Republic of the Philippines.
HELD: As to the first question, considering that the Nagtahan
In the early afternoon of August 17, 1960, barge L-1892, bridge was an immovable and stationary object and
owned by the Luzon Stevedoring Corporation was being uncontrovertedly provided with adequate openings for the
towed down the Pasig river by tugboats "Bangus" and passage of water craft, including barges like of appellant's, it
"Barbero"1 also belonging to the same corporation, when the is undeniable that the unusual event that the barge,
barge rammed against one of the wooden piles of the exclusively controlled by appellant, rammed the bridge
Nagtahan bailey bridge, smashing the posts and causing the supports raises a presumption of negligence on the part of
bridge to list. The river, at the time, was swollen and the appellant or its employees manning the barge or the tugs
current swift, on account of the heavy downpour of Manila that towed it. For in the ordinary course of events, such a
and the surrounding provinces on August 15 and 16, 1960. thing does not happen if proper care is used. In Anglo
American Jurisprudence, the inference arises by what is
known as the "res ipsa loquitur" rule (Scott vs. London Docks
Sued by the Republic of the Philippines for actual and
Co., 2 H & C 596; San Juan Light & Transit Co. vs. Requena,
consequential damage caused by its employees, amounting
224 U.S. 89, 56 L. Ed., 680; Whitwell vs. Wolf, 127 Minn. 529,
to P200,000 (Civil Case No. 44562, CFI of Manila), defendant
149 N.W. 299; Bryne vs. Great Atlantic & Pacific Tea Co., 269
Luzon Stevedoring Corporation disclaimed liability therefor,
Mass. 130; 168 N.E. 540; Gribsby vs. Smith, 146 S.W. 2d 719).
on the grounds that it had exercised due diligence in the
selection and supervision of its employees; that the damages
to the bridge were caused by force majeure; that plaintiff has The appellant strongly stresses the precautions taken by it
no capacity to sue; and that the Nagtahan bailey bridge is an on the day in question: that it assigned two of its most
obstruction to navigation. powerful tugboats to tow down river its barge L-1892; that it
assigned to the task the more competent and experienced
among its patrons, had the towlines, engines and equipment
After due trial, the court rendered judgment on June 11,
double-checked and inspected; that it instructed
1963, holding the defendant liable for the damage caused by
its patrons to take extra precautions; and concludes that it
its employees and ordering it to pay to plaintiff the actual
had done all it was called to do, and that the accident,
cost of the repair of the Nagtahan bailey bridge which
therefore, should be held due to force majeure or fortuitous
amounted to P192,561.72, with legal interest thereon from
event.
the date of the filing of the complaint.
19
Otherwise stated, the appellant, Luzon Stevedoring lost card, along with the principal card, as a "Hot Card" or
Corporation, knowing and appreciating the perils posed by "Cancelled Card" in its master file.
the swollen stream and its swift current, voluntarily entered On 06 October 1988, Luis tendered
into a situation involving obvious danger; it therefore
a despedida lunch for a close friend, a Filipino-American,
assured the risk, and can not shed responsibility merely
and another guest at the Bahia Rooftop Restaurant of the
because the precautions it adopted turned out to be
Hotel Intercontinental Manila. To pay for the lunch, Luis
insufficient. Hence, the lower Court committed no error in presented his FAREASTCARD to the attending waiter who
holding it negligent in not suspending operations and in
promptly had it verified through a telephone call to the
holding it liable for the damages caused.
bank's Credit Card Department. Since the card was not
honored, Luis was forced to pay in cash the bill
It avails the appellant naught to argue that the dolphins, like amounting to P588.13. Naturally, Luis felt embarrassed
the bridge, were improperly located. Even if true, these by this incident.
circumstances would merely emphasize the need of even
higher degree of care on appellant's part in the situation In a letter, dated 11 October 1988, private
involved in the present case. The appellant, whose barges respondent Luis Luna, through counsel, demanded from
and tugs travel up and down the river everyday, could not FEBTC the payment of damages. Adrian V. Festejo, a vice-
safely ignore the danger posed by these allegedly improper president of the bank, expressed the bank's apologies to
constructions that had been erected, and in place, for years. Luis. In his letter, dated 03 November 1988, Festejo, in
part, said:
On the second point: appellant charges the lower court with xxxxxxxxx
having abused its discretion in the admission of plaintiff's
"An investigation of your case however,
additional evidence after the latter had rested its case. There
revealed that FAREASTCARD failed to
is an insinuation that the delay was deliberate to enable the
inform you about its security policy.
manipulation of evidence to prejudice defendant-appellant.
Furthermore, an overzealous employee of
the Bank's Credit Card Department did
We find no merit in the contention. Whether or not further not consider the possibility that it may
evidence will be allowed after a party offering the evidence have been you who was presenting the
has rested his case, lies within the sound discretion of the card at that time (for which reason, the
trial Judge, and this discretion will not be reviewed except in unfortunate incident occurred)." 1
clear case of abuse.3
On 30 March 1990, the RTC of Pasig, given the
In the present case, no abuse of that discretion is shown. foregoing factual settings, rendered a decision ordering
What was allowed to be introduced, after plaintiff had rested FEBTC to pay private respondents (a) P300,000.00 moral
its evidence in chief, were vouchers and papers to support an damages; (b) P50,000.00 exemplary damages; and (c)
item of P1,558.00 allegedly spent for the reinforcement of P20,000.00 attorney's fees.
the panel of the bailey bridge, and which item already On appeal to the Court of Appeals, the appellate
appeared in Exhibit GG. Appellant, in fact, has no reason to court affirmed the decision of the trial court.
charge the trial court of being unfair, because it was also able
to secure, upon written motion, a similar order dated ISSUE:WON private respondents are entitled of moral
November 24, 1962, allowing reception of additional damages.
evidence for the said defendant-appellant.4 HELD:NO.
Concededly, the bank was remiss in indeed
WHEREFORE, finding no error in the decision of the lower neglecting to personally inform Luis of his own card’s
Court appealed from, the same is hereby affirmed. Costs cancellation. Nothing in the findings of the trial court and
against the defendant-appellant. the appellate court, however, can sufficiently indicate
any deliberate intent on the part of FEBTC to cause harm
to private respondents. Neither could FEBTC's negligence
[G.R. No. 108164. February 23, 1995.] in failing to give personal notice to Luis be considered so
gross as to amount to malice or bad faith.
FAR EAST BANK AND TRUST "xxxxxxxxx.
COMPANY, petitioner, vs. THE
"The distinction between fraud, bad faith
HONORABLE COURT OF APPEALS, LUIS A.
or malice in the sense of deliberate or
LUNA and CLARITA S. LUNA, respondents.
wanton wrong doing and negligence (as
mere carelessness) is too fundamental in
FACTS: our law to be ignored (Arts. 1170-1172);
their consequences being clearly
Some time in October 1986, private respondent differentiated by the Code.
Luis A. Lunaapplied for, and was accorded, a
FAREASTCARD issued by petitioner Far East Bank and "'ART. 2201. In contracts and
Trust Company ("FEBTC") at its Pasig Branch. Upon his quasi-contracts, the damages for
request, the bank also issued a supplemental card to which the obligor who acted in
private respondent Clarita S. Luna. good faith is liable shall be those
that are the natural and
In August 1988, Clarita lost her credit card.
probable consequences of the
FEBTC was forthwith informed. In order to replace the
breach of the obligation, and
lost card, Clarita submitted an affidavit of loss. In cases of
which the parties have foreseen
this nature, the bank’s internal security procedures and
or could have reasonably
policy would appear to be to meanwhile so record the
20
foreseen at the time the continued even after plaintiff was discharged from
obligation was constituted. the hospital when not even a word of consolation
was heard from them. Plaintiff waited for more
'In case of fraud, bad faith, than one (1) year for the defendants to perform
malice or wanton attitude, the their moral obligation but the wait was fruitless.
obligor shall be responsible for This indifference and total lack of concern of
all damages which may be defendants served to exacerbate plaintiff's miserable
reasonably attributed to the condition.
non-performance of the
obligation."
xxxx
The Court finds, therefore, the award of moral
damages made by the court a quo, affirmed by the 11.0. Defendants are responsible for ensuring the
appellate court, to be inordinate and substantially devoid safety of its students while the latter are within the
of legal basis. University premises. And that should anything
WHEREFORE, the petition for review is given untoward happens to any of its students while they
due course. The appealed decision is MODIFIED by are within the University's premises shall be the
deleting the award of moral and exemplary damages to responsibility of the defendants. In this case,
private respondents; in its stead, petitioner is ordered to defendants, despite being legally and morally bound,
pay private respondent Luis A. Luna an amount of miserably failed to protect plaintiff from injury and
P5,000.00 by way of nominal damages. In all other thereafter, to mitigate and compensate plaintiff for
respects, the appealed decision is AFFIRMED. No costs. said injury;
G.R. No. 179337 April 30, 2008 12.0. When plaintiff enrolled with defendant FEU, a
contract was entered into between them. Under
this contract, defendants are supposed to ensure
JOSEPH SALUDAGA, petitioner,
that adequate steps are taken to provide an
vs.
atmosphere conducive to study and ensure the
FAR EASTERN UNIVERSITY and EDILBERTO C. DE JESUS in his
safety of the plaintiff while inside defendant FEU's
capacity as President of FEU, respondents.
premises. In the instant case, the latter breached
this contract when defendant allowed harm to befall
DECISION upon the plaintiff when he was shot at by, of all
people, their security guard who was tasked to
YNARES-SANTIAGO, J.: maintain peace inside the campus.12
FACTS:Petitioner Joseph Saludaga was a sophomore law In Philippine School of Business Administration v. Court of
student of respondent Far Eastern University (FEU) when he Appeals,13 we held that:
was shot by Alejandro Rosete (Rosete), one of the security
guards on duty at the school premises on August 18, 1996. When an academic institution accepts students for
Petitioner was rushed to FEU-Dr. Nicanor Reyes Medical enrollment, there is established a contract between
Foundation (FEU-NRMF) due to the wound he them, resulting in bilateral obligations which both
sustained.6Meanwhile, Rosete was brought to the police parties are bound to comply with. For its part, the
station where he explained that the shooting was accidental. school undertakes to provide the student with an
He was eventually released considering that no formal education that would presumably suffice to equip
complaint was filed against him. him with the necessary tools and skills to pursue
higher education or a profession. On the other hand,
Petitioner thereafter filed a complaint for damages against the student covenants to abide by the school's
respondents on the ground that they breached their academic requirements and observe its rules and
obligation to provide students with a safe and secure regulations.
environment and an atmosphere conducive to learning.
Respondents, in turn, filed a Third-Party Complaint7 against Institutions of learning must also meet the implicit or
Galaxy Development and Management Corporation (Galaxy), "built-in" obligation of providing their students with
the agency contracted by respondent FEU to provide security an atmosphere that promotes or assists in attaining
services within its premises and Mariano D. Imperial its primary undertaking of imparting knowledge.
(Imperial), Galaxy's President, to indemnify them for Certainly, no student can absorb the intricacies of
whatever would be adjudged in favor of petitioner, if any; physics or higher mathematics or explore the realm
and to pay attorney's fees and cost of the suit. On the other of the arts and other sciences when bullets are flying
hand, Galaxy and Imperial filed a Fourth-Party Complaint or grenades exploding in the air or where there
against AFP General Insurance.8 looms around the school premises a constant threat
to life and limb. Necessarily, the school must ensure
Petitioner is suing respondents for damages based on the that adequate steps are taken to maintain peace and
alleged breach of student-school contract for a safe learning order within the campus premises and to prevent
environment. The pertinent portions of petitioner's the breakdown thereof.14
Complaint read:
It is undisputed that petitioner was enrolled as a sophomore
6.0. At the time of plaintiff's confinement, the law student in respondent FEU. As such, there was created a
defendants or any of their representative did not contractual obligation between the two parties. On
bother to visit and inquire about his condition. This petitioner's part, he was obliged to comply with the rules and
abject indifference on the part of the defendants regulations of the school. On the other hand, respondent
21
FEU, as a learning institution is mandated to impart Article 1170 of the Civil Code provides that those who are
knowledge and equip its students with the necessary skills to negligent in the performance of their obligations are liable for
pursue higher education or a profession. At the same time, it damages. Accordingly, for breach of contract due to
is obliged to ensure and take adequate steps to maintain negligence in providing a safe learning environment,
peace and order within the campus. respondent FEU is liable to petitioner for damages. It is
essential in the award of damages that the claimant must
It is settled that in culpa contractual, the mere proof of the have satisfactorily proven during the trial the existence of the
existence of the contract and the failure of its compliance factual basis of the damages and its causal connection to
justify, prima facie, a corresponding right of relief. 15 In the defendant's acts.18
instant case, we find that, when petitioner was shot inside
the campus by no less the security guard who was hired to In the instant case, it was established that petitioner spent
maintain peace and secure the premises, there is a prima P35,298.25 for his hospitalization and other medical
facie showing that respondents failed to comply with its expenses.19 While the trial court correctly imposed interest
obligation to provide a safe and secure environment to its on said amount, however, the case at bar involves an
students. obligation arising from a contract and not a loan or
forbearance of money. As such, the proper rate of legal
In order to avoid liability, however, respondents aver that the interest is six percent (6%) per annum of the amount
shooting incident was a fortuitous event because they could demanded. Such interest shall continue to run from the filing
not have reasonably foreseen nor avoided the accident of the complaint until the finality of this Decision.20 After this
caused by Rosete as he was not their employee; 16and that Decision becomes final and executory, the applicable rate
they complied with their obligation to ensure a safe learning shall be twelve percent (12%) per annum until its satisfaction.
environment for their students by having exercised due
diligence in selecting the security services of Galaxy. The other expenses being claimed by petitioner, such as
transportation expenses and those incurred in hiring a
ISSUE: WON FEU is liable for damages for breach of its personal assistant while recuperating were however not duly
obligation to provide students with a safe and secure learning supported by receipts.21 In the absence thereof, no actual
atmosphere. damages may be awarded. Nonetheless, temperate damages
under Art. 2224 of the Civil Code may be recovered where it
HELD: YES. After a thorough review of the records, we find has been shown that the claimant suffered some pecuniary
that respondents failed to discharge the burden of proving loss but the amount thereof cannot be proved with certainty.
that they exercised due diligence in providing a safe learning Hence, the amount of P20,000.00 as temperate damages is
environment for their students. They failed to prove that they awarded to petitioner.
ensured that the guards assigned in the campus met the
requirements stipulated in the Security Service Agreement. As regards the award of moral damages, there is no hard and
Indeed, certain documents about Galaxy were presented fast rule in the determination of what would be a fair amount
during trial; however, no evidence as to the qualifications of of moral damages since each case must be governed by its
Rosete as a security guard for the university was offered. own peculiar circumstances.22 The testimony of petitioner
about his physical suffering, mental anguish, fright, serious
Respondents also failed to show that they undertook steps to anxiety, and moral shock resulting from the shooting
ascertain and confirm that the security guards assigned to incident23 justify the award of moral damages. However,
them actually possess the qualifications required in the moral damages are in the category of an award designed to
Security Service Agreement. It was not proven that they compensate the claimant for actual injury suffered and not to
examined the clearances, psychiatric test results, 201 files, impose a penalty on the wrongdoer. The award is not meant
and other vital documents enumerated in its contract with to enrich the complainant at the expense of the defendant,
Galaxy. Total reliance on the security agency about these but to enable the injured party to obtain means, diversion, or
matters or failure to check the papers stating the amusements that will serve to obviate the moral suffering he
qualifications of the guards is negligence on the part of has undergone. It is aimed at the restoration, within the limits
respondents. A learning institution should not be allowed to of the possible, of the spiritual status quo ante, and should be
completely relinquish or abdicate security matters in its proportionate to the suffering inflicted. Trial courts must then
premises to the security agency it hired. To do so would result guard against the award of exorbitant damages; they should
to contracting away its inherent obligation to ensure a safe exercise balanced restrained and measured objectivity to
learning environment for its students. avoid suspicion that it was due to passion, prejudice, or
corruption on the part of the trial court.24 We deem it just
and reasonable under the circumstances to award petitioner
Consequently, respondents' defense of force majeure must
moral damages in the amount of P100,000.00.
fail. In order for force majeure to be considered,
respondents must show that no negligence or misconduct
was committed that may have occasioned the loss. An act of Likewise, attorney's fees and litigation expenses in the
God cannot be invoked to protect a person who has failed to amount of P50,000.00 as part of damages is reasonable in
take steps to forestall the possible adverse consequences of view of Article 2208 of the Civil Code.25 However, the award
such a loss. One's negligence may have concurred with an act of exemplary damages is deleted considering the absence of
of God in producing damage and injury to another; proof that respondents acted in a wanton, fraudulent,
nonetheless, showing that the immediate or proximate cause reckless, oppressive, or malevolent manner.
of the damage or injury was a fortuitous event would not
exempt one from liability. When the effect is found to be None of the foregoing exceptions was established in the
partly the result of a person's participation - whether by instant case; hence, respondent De Jesus should not be held
active intervention, neglect or failure to act - the whole solidarily liable with respondent FEU.
occurrence is humanized and removed from the rules
applicable to acts of God.17
22
Incidentally, although the main cause of action in the instant does not, by itself, render the client responsible as
case is the breach of the school-student contract, petitioner, an employer of the security guards concerned and
in the alternative, also holds respondents vicariously liable liable for their wrongful acts or omissions.31
under Article 2180 of the Civil Code, which provides:
Respondents and Galaxy were able to litigate their respective
Art. 2180. The obligation imposed by Article 2176 is claims and defenses in the course of the trial of petitioner's
demandable not only for one's own acts or complaint. Evidence duly supports the findings of the trial
omissions, but also for those of persons for whom court that Galaxy is negligent not only in the selection of its
one is responsible. employees but also in their supervision. Indeed, no
administrative sanction was imposed against Rosete despite
xxxx the shooting incident; moreover, he was even allowed to go
on leave of absence which led eventually to his
Employers shall be liable for the damages caused by disappearance.34 Galaxy also failed to monitor petitioner's
their employees and household helpers acting within condition or extend the necessary assistance, other than the
the scope of their assigned tasks, even though the P5,000.00 initially given to petitioner. Galaxy and Imperial
former are not engaged in any business or industry. failed to make good their pledge to reimburse petitioner's
medical expenses.
xxxx
For these acts of negligence and for having supplied
respondent FEU with an unqualified security guard, which
The responsibility treated of in this article shall cease
resulted to the latter's breach of obligation to petitioner, it is
when the persons herein mentioned prove that they
proper to hold Galaxy liable to respondent FEU for such
observed all the diligence of a good father of a family
damages equivalent to the above-mentioned amounts
to prevent damage.
awarded to petitioner.
We agree with the findings of the Court of Appeals that
Unlike respondent De Jesus, we deem Imperial to be solidarily
respondents cannot be held liable for damages under Art.
liable with Galaxy for being grossly negligent in directing the
2180 of the Civil Code because respondents are not the
affairs of the security agency. It was Imperial who assured
employers of Rosete. The latter was employed by Galaxy. The
petitioner that his medical expenses will be shouldered by
instructions issued by respondents' Security Consultant to
Galaxy but said representations were not fulfilled because
Galaxy and its security guards are ordinarily no more than
they presumed that petitioner and his family were no longer
requests commonly envisaged in the contract for services
interested in filing a formal complaint against them. 35
entered into by a principal and a security agency. They cannot
be construed as the element of control as to treat
respondents as the employers of Rosete.28 WHEREFORE, the petition is GRANTED. The June 29, 2007
Decision of the Court of Appeals in CA-G.R. CV No. 87050
nullifying the Decision of the trial court and dismissing the
As held in Mercury Drug Corporation v. Libunao:29
complaint as well as the August 23, 2007 Resolution denying
the Motion for Reconsideration are REVERSED and SET
In Soliman, Jr. v. Tuazon,30 we held that where the
ASIDE. The Decision of the Regional Trial Court of Manila,
security agency recruits, hires and assigns the works
Branch 2, in Civil Case No. 98-89483 finding respondent FEU
of its watchmen or security guards to a client, the
liable for damages for breach of its obligation to provide
employer of such guards or watchmen is such
students with a safe and secure learning atmosphere,
agency, and not the client, since the latter has no is AFFIRMED with the following MODIFICATIONS:
hand in selecting the security guards. Thus, the duty
to observe the diligence of a good father of a family
a. respondent Far Eastern University (FEU) is ORDERED to pay
cannot be demanded from the said client:
petitioner actual damages in the amount of P35,298.25, plus
6% interest per annum from the filing of the complaint until
… [I]t is settled in our jurisdiction that
the finality of this Decision. After this decision becomes final
where the security agency, as here, recruits,
and executory, the applicable rate shall be twelve percent
hires and assigns the work of its watchmen (12%) per annum until its satisfaction;
or security guards, the agency is the
employer of such guards or watchmen.
b. respondent FEU is also ORDERED to pay petitioner
Liability for illegal or harmful acts
temperate damages in the amount of P20,000.00; moral
committed by the security guards attaches
damages in the amount of P100,000.00; and attorney's fees
to the employer agency, and not to the
and litigation expenses in the amount of P50,000.00;
clients or customers of such agency. As a
general rule, a client or customer of a
security agency has no hand in selecting c. the award of exemplary damages is DELETED.
who among the pool of security guards or
watchmen employed by the agency shall be The Complaint against respondent Edilberto C. De Jesus
assigned to it; the duty to observe the is DISMISSED. The counterclaims of respondents are
diligence of a good father of a family in the likewise DISMISSED.
selection of the guards cannot, in the
ordinary course of events, be demanded Galaxy Development and Management Corporation (Galaxy)
from the client whose premises or property and its president, Mariano D. Imperial are ORDERED to jointly
are protected by the security guards. and severally pay respondent FEU damages equivalent to the
above-mentioned amounts awarded to petitioner.
The fact that a client company may give instructions
or directions to the security guards assigned to it, SO ORDERED.
23
G.R. No. 185798 January 13, 2014 demand for refund on October 08, 1998 until fully
paid,
FIL-ESTATE PROPERTIES, INC. AND FIL-ESTATE NETWORK
INC., Petitioners, b) ONE HUNDRED THOUSAND PESOS (P100,000.00)
vs. as moral damages,
SPOUSES CONRADO AND MARIA VICTORIA
RONQUILLO, Respondents. c) FIFTY THOUSAND PESOS (P50,000.00) as
attorney’s fees,
DECISION
d) The costs of suit, and
PEREZ, J.:
e) An administrative fine of TEN THOUSAND PESOS
Before the Court is a petition for review on certiorari under (P10,000.00) payable to this Office fifteen (15) days
Rule 45 of the 1997 Rules .of Civil Procedure assailing the upon receipt of this decision, for violation of Section
Decision1 of the Court of Appeals in CA-G.R. SP No. 100450 20 in relation to Section 38 of PD 957.3
which affirmed the Decision of the Office of the President in
O.P. Case No. 06-F-216. The Arbiter considered petitioners’ failure to develop the
condominium project as a substantial breach of their
As culled from the records, the facts are as follow: obligation which entitles respondents to seek for rescission
with payment of damages. The Arbiter also stated that mere
Petitioner Fil-Estate Properties, Inc. is the owner and economic hardship is not an excuse for contractual and legal
developer of the Central Park Place Tower while co-petitioner delay.
Fil-Estate Network, Inc. is its authorized marketing agent.
Respondent Spouses Conrado and Maria Victoria Ronquillo Petitioners appealed the Arbiter’s Decision through a petition
purchased from petitioners an 82-square meter condominium for review pursuant to Rule XII of the 1996 Rules of Procedure
unit at Central Park Place Tower in Mandaluyong City for a of HLURB. On 17 February 2005, the Board of Commissioners
pre-selling contract price of FIVE MILLION ONE HUNDRED of the HLURB denied4 the petition and affirmed the Arbiter’s
SEVENTY-FOUR THOUSAND ONLY (P5,174,000.00). On 29 Decision. The HLURB reiterated that the depreciation of the
August 1997, respondents executed and signed a Reservation peso as a result of the Asian financial crisis is not a fortuitous
Application Agreement wherein they deposited P200,000.00 event which will exempt petitioners from the performance of
as reservation fee. As agreed upon, respondents paid the full their contractual obligation.
downpayment of P1,552,200.00 and had been paying
the P63,363.33 monthly amortizations until September 1998. Petitioners filed a motion for reconsideration but it was
denied5 on 8 May 2006. Thereafter, petitioners filed a Notice
Upon learning that construction works had stopped, of Appeal with the Office of the President. On 18 April 2007,
respondents likewise stopped paying their monthly petitioners’ appeal was dismissed6 by the Office of the
amortization. Claiming to have paid a total of P2,198,949.96 President for lack of merit. Petitioners moved for a
to petitioners, respondents through two (2) successive reconsideration but their motion was denied 7 on 26 July
letters, demanded a full refund of their payment with 2007.
interest. When their demands went unheeded, respondents
were constrained to file a Complaint for Refund and Damages Petitioners sought relief from the Court of Appeals through a
before the Housing and Land Use Regulatory Board (HLURB). petition for review under Rule 43 containing the same
Respondents prayed for reimbursement/refund arguments they raised before the HLURB and the Office of
of P2,198,949.96 representing the total amortization the President:
payments, P200,000.00 as and by way of moral damages,
attorney’s fees and other litigation expenses. I.
On 21 October 2000, the HLURB issued an Order of Default THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN
against petitioners for failing to file their Answer within the AFFIRMING THE DECISION OF THE HONORABLE HOUSING
reglementary period despite service of summons.2 AND LAND USE REGULATORY BOARD AND ORDERING
PETITIONERS-APPELLANTS TO REFUND RESPONDENTS-
Petitioners filed a motion to lift order of default and attached APPELLEES THE SUM OF P2,198,949.96 WITH 12% INTEREST
their position paper attributing the delay in construction to FROM 8 OCTOBER 1998 UNTIL FULLY PAID, CONSIDERING
the 1997 Asian financial crisis. Petitioners denied committing THAT THE COMPLAINT STATES NO CAUSE OF ACTION
fraud or misrepresentation which could entitle respondents AGAINST PETITIONERS-APPELLANTS.
to an award of moral damages.
II.
On 13 June 2002, the HLURB, through Arbiter Atty. Joselito F.
Melchor, rendered judgment ordering petitioners to jointly THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN
and severally pay respondents the following amount: AFFIRMING THE DECISION OF THE OFFICE BELOW ORDERING
PETITIONERS-APPELLANTS TO PAY RESPONDENTS-APPELLEES
a) The amount of TWO MILLION ONE HUNDRED THE SUM OF P100,000.00 AS MORAL DAMAGES
NINETY-EIGHT THOUSAND NINE HUNDRED FORTY AND P50,000.00 AS ATTORNEY’S FEES CONSIDERING THE
NINE PESOS & 96/100 (P2,198,949.96) with interest ABSENCE OF ANY FACTUAL OR LEGAL BASIS THEREFOR.
thereon at twelve percent (12%) per annum to be
computed from the time of the complainants’ III.
24
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN only resorted to "suspension and reformatting as a testament
AFFIRMING THE DECISION OF THE HOUSING AND LAND USE to their commitment to their buyers." Petitioners attribute
REGULATORY BOARD ORDERING PETITIONERS-APPELLANTS the delay to the 1997 Asian financial crisis that befell the real
TO PAY P10,000.00 AS ADMINISTRATIVE FINE IN THE estate industry. Invoking Article 1174 of the New Civil Code,
ABSENCE OF ANY FACTUAL OR LEGAL BASIS TO SUPPORT petitioners maintain that they cannot be held liable for a
SUCH FINDING.8 fortuitous event.
On 30 July 2008, the Court of Appeals denied the petition for Petitioners contest the payment of a huge amount of interest
review for lack of merit. The appellate court echoed the on account of suspension of development on a project. They
HLURB Arbiter’s ruling that "a buyer for a liken their situation to a bank which this Court, in Overseas
condominium/subdivision unit/lot unit which has not been Bank v. Court of Appeals,12 adjudged as not liable to pay
developed in accordance with the approved interest on deposits during the period that its operations are
condominium/subdivision plan within the time limit for ordered suspended by the Monetary Board of the Central
complying with said developmental requirement may opt for Bank.
reimbursement under Section 20 in relation to Section 23 of
Presidential Decree (P.D.) 957 x x x."9 The appellate court Lastly, petitioners aver that they should not be ordered to
supported the HLURB Arbiter’s conclusion, which was pay moral damages because they never intended to cause
affirmed by the HLURB Board of Commission and the Office of delay, and again blamed the Asian economic crisis as the
the President, that petitioners’ failure to develop the direct, proximate and only cause of their failure to complete
condominium project is tantamount to a substantial breach the project. Petitioners submit that moral damages should
which warrants a refund of the total amount paid, including not be awarded unless so stipulated except under the
interest. The appellate court pointed out that petitioners instances enumerated in Article 2208 of the New Civil Code.
failed to prove that the Asian financial crisis constitutes a Lastly, petitioners refuse to pay the administrative fine
fortuitous event which could excuse them from the because the delay in the project was caused not by their own
performance of their contractual and statutory obligations. deceptive intent to defraud their buyers, but due to
The appellate court also affirmed the award of moral unforeseen circumstances beyond their control.
damages in light of petitioners’ unjustified refusal to satisfy
respondents’ claim and the legality of the administrative fine, Three issues are presented for our resolution: 1) whether or
as provided in Section 20 of Presidential Decree No. 957. not the Asian financial crisis constitute a fortuitous event
which would justify delay by petitioners in the performance
Petitioners sought reconsideration but it was denied in a of their contractual obligation; 2) assuming that petitioners
Resolution10 dated 11 December 2008 by the Court of are liable, whether or not 12% interest was correctly imposed
Appeals. on the judgment award, and 3) whether the award of moral
damages, attorney’s fees and administrative fine was proper.
Aggrieved, petitioners filed the instant petition advancing
substantially the same grounds for review: It is apparent that these issues were repeatedly raised by
petitioners in all the legal fora. The rulings were consistent
A. that first, the Asian financial crisis is not a fortuitous event
that would excuse petitioners from performing their
THE HONORABLE COURT OF APPEALS ERRED WHEN IT contractual obligation; second, as a result of the breach
AFFIRMED IN TOTO THE DECISION OF THE OFFICE OF THE committed by petitioners, respondents are entitled to rescind
PRESIDENT WHICH SUSTAINED RESCISSION AND REFUND IN the contract and to be refunded the amount of amortizations
FAVOR OF THE RESPONDENTS DESPITE LACK OF CAUSE OF paid including interest and damages; and third, petitioners
ACTION. are likewise obligated to pay attorney’s fees and the
administrative fine.
B.
This petition did not present any justification for us to deviate
GRANTING FOR THE SAKE OF ARGUMENT THAT THE from the rulings of the HLURB, the Office of the President and
PETITIONERS ARE LIABLE UNDER THE PREMISES, THE the Court of Appeals.
HONORABLE COURT OF APPEALS ERRED WHEN IT AFFIRMED
THE HUGE AMOUNT OF INTEREST OF TWELVE PERCENT Indeed, the non-performance of petitioners’ obligation
(12%). entitles respondents to rescission under Article 1191 of the
New Civil Code which states:
C.
Article 1191. The power to rescind obligations is implied in
THE HONORABLE COURT OF APPEALS LIKEWISE ERRED WHEN reciprocal ones, in case one of the obligors should not comply
IT AFFIRMED IN TOTO THE DECISION OF THE OFFICE OF THE with what is incumbent upon him.
PRESIDENT INCLUDING THE PAYMENT OF P100,000.00 AS
MORAL DAMAGES, P50,000.00 AS ATTORNEY’S FEES The injured party may choose between the fulfillment and
AND P10,000.00 AS ADMINISTRATIVE FINE IN THE ABSENCE the rescission of the obligation, with payment of damages in
OF ANY FACTUAL OR LEGAL BASIS TO SUPPORT SUCH either case. He may also seek rescission, even after he has
CONCLUSIONS.11 chosen fulfillment, if the latter should become impossible.
Petitioners insist that the complaint states no cause of action More in point is Section 23 of Presidential Decree No. 957,
because they allegedly have not committed any act of the rule governing the sale of condominiums, which provides:
misrepresentation amounting to bad faith which could entitle
respondents to a refund. Petitioners claim that there was a Section 23. Non-Forfeiture of Payments.1âwphi1 No
mere delay in the completion of the project and that they installment payment made by a buyer in a subdivision or
25
condominium project for the lot or unit he contracted to buy We likewise affirm the award of attorney’s fees because
shall be forfeited in favor of the owner or developer when the respondents were forced to litigate for 14 years and incur
buyer, after due notice to the owner or developer, desists expenses to protect their rights and interest by reason of the
from further payment due to the failure of the owner or unjustified act on the part of petitioners. 18 The imposition
developer to develop the subdivision or condominium project of P10,000.00 administrative fine is correct pursuant to
according to the approved plans and within the time limit for Section 38 of Presidential Decree No. 957 which reads:
complying with the same. Such buyer may, at his option, be
reimbursed the total amount paid including amortization Section 38. Administrative Fines. The Authority may prescribe
interests but excluding delinquency interests, with interest and impose fines not exceeding ten thousand pesos for
thereon at the legal rate. (Emphasis supplied). violations of the provisions of this Decree or of any rule or
regulation thereunder. Fines shall be payable to the Authority
Conformably with these provisions of law, respondents are and enforceable through writs of execution in accordance
entitled to rescind the contract and demand reimbursement with the provisions of the Rules of Court.
for the payments they had made to petitioners.
Finally, we sustain the award of moral damages. In order that
Notably, the issues had already been settled by the Court in moral damages may be awarded in breach of contract cases,
the case of Fil-Estate Properties, Inc. v. Spouses the defendant must have acted in bad faith, must be found
Go13 promulgated on 17 August 2007, where the Court stated guilty of gross negligence amounting to bad faith, or must
that the Asian financial crisis is not an instance of caso have acted in wanton disregard of contractual
fortuito. Bearing the same factual milieu as the instant case, obligations.19 The Arbiter found petitioners to have acted in
G.R. No. 165164 involves the same company, Fil-Estate, albeit bad faith when they breached their contract, when they
about a different condominium property. The company failed to address respondents’ grievances and when they
likewise reneged on its obligation to respondents therein by adamantly refused to refund respondents' payment.
failing to develop the condominium project despite
substantial payment of the contract price. Fil-Estate advanced In fine, we find no reversible error on the merits in the
the same argument that the 1997 Asian financial crisis is a impugned Court of Appeals' Decision and Resolution.
fortuitous event which justifies the delay of the construction
project. First off, the Court classified the issue as a question WHEREFORE, the petition is PARTLY GRANTED. The appealed
of fact which may not be raised in a petition for review Decision is AFFIRMED with the MODIFICATION that the legal
considering that there was no variance in the factual findings interest to be paid is SIX PERCENT (6%) on the amount due
of the HLURB, the Office of the President and the Court of computed from the time of respondents' demand for refund
Appeals. Second, the Court cited the previous rulings of Asian on 8 October 1998.
Construction and Development Corporation v. Philippine
Commercial International Bank14 and Mondragon Leisure and
SO ORDERED.
Resorts Corporation v. Court of Appeals15 holding that the
1997 Asian financial crisis did not constitute a valid
justification to renege on obligations. The Court expounded:
In said case, the Court ordered the refund of the total By way of security, the individual petitioners executed several
amortizations paid by respondents plus 6% legal interest Continuing Guaranty/Comprehensive Surety Agreements19 in
computed from the date of demand. The Court also awarded favor of Allied Bank. Petitioners failed to settle their
attorney’s fees. We follow that ruling in the case before us. obligations under the aforementioned promissory note and
trust receipts, hence, Allied Bank, through counsel, sent them
The resulting modification of the award of legal interest is, demand letters, seeking payment of the total amount
also, in line with our recent ruling in Nacar v. Gallery of P51,064,093.62, but to no avail. Thus, Allied Bank was
Frames,17 embodying the amendment introduced by the prompted to file a complaint for collection of sum of
Bangko Sentral ng Pilipinas Monetary Board in BSP-MB money21 (subject complaint) against Metro Concast.
Circular No. 799 which pegged the interest rate at 6% Petitioners admitted their indebtedness to Allied Bank but
regardless of the source of obligation. denied liability for the interests and penalties charged,
26
claiming to have paid the total sum of P65,073,055.73 by way the outset, the Court must dispel the notion that the MoA
of interest charges for the period covering 1992 to 1997.24 would have any relevance to the performance of petitioners’
obligations to Allied Bank. The MoA is a sale of assets
They also alleged that the economic reverses suffered by the contract, while petitioners’ obligations to Allied Bank arose
Philippine economy in 1998 as well as the devaluation of the from various loan transactions. Absent any showing that the
peso against the US dollar contributed greatly to the downfall terms and conditions of the latter transactions have been, in
of the steel industry, directly affecting the business of Metro any way, modified or novated by the terms and conditions in
Concast and eventually leading to its cessation. Hence, in the MoA, said contracts should be treated separately and
order to settle their debts with Allied Bank, petitioners distinctly from each other, such that the existence,
offered the sale of Metro Concast’s remaining assets, performance or breach of one would not depend on the
consisting of machineries and equipment, to Allied Bank, existence, performance or breach of the other.
which the latter, however, refused. Instead, Allied Bank
advised them to sell the equipment and apply the proceeds of Fortuitous events by definition are extraordinary events not
the sale to their outstanding obligations. Accordingly, foreseeable or avoidable. It is therefore, not enough that the
petitioners offered the equipment for sale, but since there event should not have been foreseen or anticipated, as is
were no takers, the equipment was reduced into ferro scrap commonly believed but it must be one impossible to foresee
or scrap metal over the years. In 2002, Peakstar Oil or to avoid. The mere difficulty to foresee the happening is
Corporation (Peakstar), represented by one Crisanta Camiling not impossibility to foresee the same. To constitute a
(Camiling), expressed interest in buying the scrap metal. fortuitous event, the following elements must concur: (a) the
During the negotiations with Peakstar, petitioners claimed cause of the unforeseen and unexpected occurrence or of the
that Atty. Peter Saw (Atty. Saw), a member of Allied Bank’s failure of the debtor to comply with obligations must be
legal department, acted as the latter’s agent. Eventually, with independent of human will; (b) it must be impossible to
the alleged conformity of Allied Bank, through Atty. Saw, a foresee the event that constitutes the caso fortuito or, if it
Memorandum of Agreement25 was drawn between Metro can be foreseen, it must be impossible to avoid; (c) the
Concast, represented by petitioner Jose Dychiao, and occurrence must be such as to render it impossible for the
Peakstar, through Camiling, under which Peakstar obligated debtor to fulfill obligations in a normal manner; and (d) the
itself to purchase the scrap metal for a total consideration obligor must be free from any participation in the aggravation
of P34,000,000.00. of the injury or loss.40 (Emphases supplied)
Unfortunately, Peakstar reneged on all its obligations under While it may be argued that Peakstar’s breach of the MoA
the MoA. In this regard, petitioners asseverated that: was unforseen by petitioners, the same us clearly not
"impossible"to foresee or even an event which is
(a) their failure to pay their outstanding loan obligations to independent of human will." Neither has it been shown that
Allied Bank must be considered as force majeure ; and said occurrence rendered it impossible for petitioners to pay
their loan obligations to Allied Bank and thus, negates the
(b) since Allied Bank was the party that accepted the terms former’s force majeure theory altogether. In this regard,
and conditions of payment proposed by Peakstar, petitioners petitioners’ liability must perforce stand. Considering,
must therefore be deemed to have settled their obligations to however, that Allied Bank’s extra-judicial demand on
Allied Bank. petitioners appears to have been made only on December 10,
1998, the computation of the applicable interests and penalty
charges should be reckoned only from such date.
Claiming that the subject complaint was falsely and
maliciously filed, petitioners prayed for the award of moral
damages and exemplary damages, attorney’s fees, and G.R. No. L-7859 February 12, 1913
payment for other litigation expenses, including costs of suit.
VICTORIA SEOANE, administratrix of The Intestate Estate of
The Issue Eduardo Fargas,Plaintiff-Appellee, vs. CATALINA FRANCO,
administratrix of The Intestate Estate of Manuel
Franco, Defendant-Appellant.
whether or not the loan obligations incurred by the
petitioners under the subject promissory note and various
trust receipts have already been extinguished.. Ramon Salinas, for appellant.
Gibbs, McDonough and Blanco, for appellee.
The Court’s Ruling: NO.
MORELAND, J. :chanrobles virtual law library
Article 1231 of the Civil Code states that obligations are
extinguished either by payment or performance, the loss of This is an appeal from a judgment of the Court of First
the thing due, the condonation or remission of the debt, the Instance of Zamboanga in favor of the plaintiff, holding that
confusion or merger of the rights of creditor and debtor, the right of action upon the mortgage debt which was the
compensation or novation. basis of the claim presented against the plaintiff's estate had
prescribed.chanroblesvirtualawlibrary chanrobles virtual law
library
Petitioners classify Peakstar’s default as a form of force
majeure in the sense that they have, beyond their control,
lost the funds they expected to have received from the The mortgage in question was executed on the 13th of
Peakstar (due to the MoA) which they would, in turn, use to October, 1884, to secure the payment of the sum of
pay their own loan obligations to Allied Bank. They further P4,876.01, the mortgagor agreeing to pay the sum "little by
state that Allied Bank was equally bound by Metro Concast’s little." The claim appears to have been presented to the
MoA with Peakstar since its agent, Atty. Saw, actively plaintiff's intestate on the 8th of August, 1911. Nothing has
represented it during the negotiations and execution of the been paid either of principal or of
said agreement. Petitioners’ arguments are untenable. At
27
interest.chanroblesvirtualawlibrary chanrobles virtual law which must be fixed by the
library courts.chanroblesvirtualawlibrary chanrobles virtual law
library
We are of the opinion that this case falls within the provisions
of article 1128 of the Civil Code, which reads as follows: The only action which can be maintained under the terms of
the contract is that bywhich it is sought to be obtain from the
1128. When the obligation does not fix a term, but it can be judge the determination of this period, and not the unlawful
inferred from its nature and circumstance that there was an detainer action which has been brought - an action which
intention of granting it to the debtor, the courts shall fix the presupposes the expiration of the term and makes it the duty
duration of such a of the judge to simply the decree the eviction. To maintain
term.chanroblesvirtualawlibrary chanrobles virtual law library the latter action it is sufficient to show the expiration of the
term of the contract, whether conventional or legal; in order
The courts shall also fix the duration of a term when it may to decree the relief to be granted in the former action it is
have been left at the will of the debtor. necessary for the judge to look into the character and
conditions of the mutual undertakings with a view to
supplying the lacking element of a time at which the lease is
The obligation in question seems to leave the duration of the
to expire.
period for the payment thereof to the will of the debtor. It
appears also that it was the intention of the instrument to
give the debtor time within which to pay the obligation. In The case of Barreto vs. The City of Manila (7 Phil. Rep., 416)
such cases this court has held, on several occasions, that the dealt with a case where the terms of a donation did not fix
obligation is not due and payable until an action has been the time of the performance of the condition placed upon the
commenced by the mortgagee against the mortgagor for the donation, and the court held that the period must be
purpose of having the court fix the date on and after which determined by the court in a proper action in accordance
the instrument shall be payable and the date of maturity is with article 1128 of the Civil Code, saying (p. 420):
fixed in pursuance thereof. The case of Eleizegui vs. The
Manila Lawn Tennis Club (2 Phil. Rep., 309), in which the The contract having fixed no period in which the condition
opinion was written by the Chief Justice of the court, is the should be fulfilled, the provisions of article 1128 of the Civil
leading case upon the subject. In that case the question was Code are applicable and it is the duty of the court to fix a
over the duration of a lease concerning "a piece of land for a suitable time for its fulfillment. Eleizegui vs. The Manila Lawn
fixed consideration and to endure at the will of the lessee." In Tennis Club, 2 Phil. Rep., 309. (11 Phil. Rep., 624. 1 )
discussing the question the court said (p. 310):
In the case of Levy Hermanos vs. Paterno (18 Phil. Rep., 353)
With respect to the term of the lease the present question the court said (p. 355):
has arisen. In its discussion three theories have been
presented: One which makes the duration depend upon the The defendant having bound himself to pay his debt to the
will of the lessor, who, upon one month's notice given to the plaintiffs in partial payments, as set forth in the note in
lessee, may terminate the lease so stipulated; another which, question, it is seen that the obligation is one of payment by
on the contrary, makes it dependent upon the will of the installments, since its fulfillment cannot be required
lessee, as stipulated; and the third, in accordance with which immediately nor does its existence depend upon the
the right is reserved to the court to fix the duration of the happening of any particular event. But, thought the obligation
term. is one of payment by installments, nevertheless no fixed day
was specified for its fulfillment, so that the period for
The clause on which the case turns is as follows (p. 312): payment is undetermined or was not fixed by the parties
when they executed the contract. Besides, it is evident that
Mr. Williamson, or whoever may succeed him as secretary of the term for payment was granted for the exclusive benefit of
the club, may terminate this lease whenever desired without the defendant and for his own convenience, as by the
other formality than that of giving a month's notice. The language of the document, the plaintiffs gained nothing by
owners of the land undertake to maintain the club as tenant the fact that the debt was not immediately demandable. Nor
as long as the latter shall see fit. was any interest stipulated on the debt during the time that it
should remain unpaid by the defendant. For the foregoing
reasons, and in whatever manner this case be considered, it is
Considering the case the court said (314):
unquestionable that it falls within the provisions of article
1128 of the Civil Code. . .
The Civil Code has made provision for such a case in all kinds
.chanroblesvirtualawlibrary chanrobles virtual law library
of obligations. In speaking in general of obligations with a
term it has supplied the deficiency of the former law with
The obligation being manifestly defective with regard to the
respect to the "duration of the term when it has been left to
duration of the period granted to the debtor, that is, to the
the will of the debtor," and provides that in this case the term
defendant, that defect must be cured by the courts through
shall be fixed by the courts. (Art. 1128, sec. 2.) In every
judicial decision which shall determine the said duration,
contract, as laid down by the authorities, there is always a
under the power expressly granted them for such purpose by
creditor who is entitled to demand the performance, and a
the legal provisions just above
debtor upon whom rests the obligation to perform the
transcribed.chanroblesvirtualawlibrary chanrobles virtual law
undertaking. In bilateral contracts the contracting parties are
library
mutually creditors and debtors. Thus, in this contract of lease,
the lessee is the creditor with respect to the rights
enumerated in article 1554, and is the debtor with respect to The trial court, therefore, acted in accordance with the law in
the obligations imposed by articles 1555 and 1561. The term exercising the said power in the present case, by fixing the
within which performance of the latter obligation is due is duration of the period on the basis that the payment of the
what has been left to the will of the debtor. This term it is debt should be made at the rate of P200 a month; and we see
28
no abuse of judicial discretion of fixing such a rate, as they appeared and expressed our opinion of what the
considering the importance of the obligation and the absence result of the case would be upon the merits if it subsequently
of any stipulation of interest in favor of the creditors. came before us upon the same facts. In that case we said (p.
17):
From these decisions it is clear that the instrument sued upon
in the case at bar is one which leaves the period of payment We believe, however, that, for the information of the parties
at the will of the mortgagor. Such being the case, an action interested in the subject matter of this action and to the end
should have been brought for the purpose of having the court that unnecessary litigation may be avoided, the opinion of
set a date on which the instrument should become due and the court should be given upon the facts presented in this
payable. Until such action was prosecuted no suit could be case. Knowing what our opinion is upon these facts it is
brought for the recovery of the amount named in the probable that the heirs will not care to pursue the litigation
instrument. It is, therefore, clear that this action is further unless, which is somewhat unlikely, they are able to
premature. The instrument has been sued upon before it is present new facts. We, therefore, proceed to a consideration
due. The action must accordingly be of the case upon the merits as presented by the record.
dismissed.chanroblesvirtualawlibrary chanrobles virtual law
library The judgment is affirmed, with the costs against the
appellant. So ordered.chanroblesvirtualawlibrary
Ordinarily when an action of this sort is dismissed the plaintiff
may at once begin his action for the purpose of fixing a date
upon which the instrument shall become due. From the
undisputed facts in this case and from the facts and
conditions that very probably cannot be charged hereafter, it
is our present opinion that such action is itself prescribed.
Section 38 of the Code of Civil Procedure reads as follows:
SEC. 38. To what this chapter does not apply. - This chapter
shall not apply to actions already commenced, or to cases
wherein the right of action has already accrued; but the
statutes in force when the action or right of action accrued
shall be applicable to such cases according to the subject of
the action and without regard to the form; nor shall this
chapter apply in the case of a continuing and subsisting trust,
nor to an action by the vendee of real property in possession
thereof to obtain the conveyance of it: Provided,
nevertheless, That all rights of action which have already
accrued, except those named in the last preceding paragraph,
must be vindicated by the commencement of an action or
proceeding to enforce the same within ten years after this Act
comes into effect.
29