Sie sind auf Seite 1von 29

SSS V Moonwalk Development and Housing Corp the payment by Moonwalk of its indebtedness to SSS and by

the latter's act of cancelling the real estate mortgages


"On February 20, 1980, the Social Security System, SSS for executed in its favor by defendant Moonwalk.
brevity, filed a complaint in the Court of First Instance of Rizal
against Moonwalk Development & Housing Corporation,
Moonwalk for short, alleging that the former had committed ISSUE: WON defendants are still liable to pay for penalty as
an error in failing to compute the 12% interest due on claimed by plaintiffs
delayed payments on the loan of Moonwalk — resulting in a
chain of errors in the application of payments made by Ruling:
Moonwalk and, in an unpaid balance on the principal loan
agreement in the amount of P7,053.77 and, also in not NO. What is sought to be recovered in this case is not the 12%
reflecting in its statement or account an unpaid balance on interest on the loan but the 12% penalty for failure to pay on
the said penalties for delayed payments in the amount of time the amortization.
P7,517,178.21 as of October 10, 1979.
A penalty is demandable in case of non performance or late
Moonwalk answered denying SSS' claims and asserting that performance of the main obligation. In other words in order
SSS had the opportunity to ascertain the truth but failed to do that the penalty may arise there must be a breach of the
so. obligation either by total or partial non fulfillment or there is
non fulfillment in point of time which is called mora or delay.
Stipulation of Facts: The debtor therefore violates the obligation in point of time if
there is mora or delay. Now, there is no mora or delay unless
Plaintiff approved the application of defendant there is a demand. It is noteworthy that in the present case
Moonwalk for an interim loan in the amount of THIRTY during all the period when the principal obligation was still
MILLION PESOS (P30,000,000.00) for the purpose of subsisting, although there were late amortizations there was no
developing and constructing a housing project in the demand made by the creditor, plaintiff-appellant for the
provinces of Rizal and Cavite; payment of the penalty. Therefore up to the time of the letter
of plaintiff-appellant there was no demand for the payment of
Out of the approved loan of THIRTY MILLION PESOS the penalty, hence the debtor was no in mora in the payment
(P30,000,000.00), the sum of P9,595,000.00 was of the penalty.
released to defendant Moonwalk as of November 28,
1973; Plaintiff-appellant issued its statement of account (Exhibit F)
showing the total obligation of Moonwalk as P15,004,905.74,
Third Amended Deed of First Mortgage was executed. and forthwith demanded payment from defendant-appellee.
Because of the demand for payment, Moonwalk made several
Defendants Rosita U. Alberto and Rosita U. Alberto, payments on September 29, October 9 and 19, 1979
mother and daughter respectively,substituted respectively, all in all totalling P15,004,905.74 which was a
Associated Construction and Surveys Corporation, complete payment of its obligation. Because of this payment
Philippine Model Homes Development Corporation, the obligation of Moonwalk was considered extinguished, and
Mariano Z. Velarde and Eusebio T. Ramos, as solidary pursuant to said extinguishment, the real estate mortgages
obligors; given by Moonwalk were released.

After considering additional releases in the amount of Besides the Real Estate Mortgages, penal clause which is also
P2,659,700.00, made to defendant Moonwalk, an accessory obligation must also be deemed extinguished
defendant Moonwalk delivered to the plaintiff a considering that the principal obligation was considered
promissory note for TWELVE MILLION TWO HUNDRED extinguished, and the penal clause being an accessory
FIFTY FOUR THOUSAND SEVEN HUNDRED PESOS obligation.
(P12,254,700.00) Annex `E', signed by Eusebio T.
Ramos, and the said Rosita U. Alberto and Rosita U. At the time of the payment made of the full obligation on
Alberto; October 10, 1979 together with the 12% interest by defendant-
appellee Moonwalk, its obligation was extinguished. It being
Moonwalk made a total payment of P23,657,901.84 to extinguished, there was no more need for the penal clause.
SSS for the loan principal of P12,254,700.00 released
to it. The last payment made by Moonwalk in the We advance the justification for the decision stating Article
amount of P15,004,905.74 were based on the 169:
Statement of Account;
"Art. 1169. Those obliged to deliver or to do something incur in
Plaintiff issued to defendant Moonwalk the Release of delay from the time the obligee judicially or extrajudicially
Mortgage for Moonwalk's mortgaged properties in demands from them the fulfillment of their obligation." There
Cavite and Rizal; are only three instances when demand is not necessary to
render the obligor in default. These are the following: "(1)
In letters to defendant Moonwalk,plaintiff alleged that When the obligation or the law expressly so declares; (2) When
it committed an honest mistake in releasing from the nature and the circumstances of the obligation it
defendant. appears that the designation of the time when the thing is to
be delivered or the service is to be rendered was a controlling
Ddefendant's counsel told plaintiff that it had motive for the establishment of the contract; or (3) When the
completely paid its obligations to SSS; demand would be useless, as when the obligor has rendered it
beyond his power to perform."
The trial court issued an order dismissing the complaint on
the ground that the obligation was already extinguished by

1
This case does not fall within any of the established exceptions. Toyota Shaw, Inc. later on assigned all its rights and interests
Hence, despite the provision in the promissory note that "(a)ll in the chattel mortgage to petitioner Rizal Commercial
amortization payments shall be made every first five (5) days of Banking Corporation (RCBC).
the calendar month until the principal and interest on the loan
or any portion thereof actually released has been fully paid," 10 All the checks dated April 1991 to January 1993 were
petitioner is not excused from making a demand. It has been thereafter encashed and debited by RCBC from private
established that at the time of payment of the full obligation, respondent's account, except for the check representing the
private respondent Moonwalk has long been delinquent in payment for August 1991, which was unsigned. Previously,
meeting its monthly arrears and in paying the full amount of the amount represented by such check was debited from
the loan itself as the obligation matured sometime in January, private respondent's account but was later recalled and re-
1977. But mere delinquency in payment does not necessarily credited, to him. Because of the recall, the last two checks,
mean delay in the legal concept. To be in default ". . . is dated February 10, 1993 and March 10, 1993, were no longer
different from mere delay in the grammatical sense, because it presented for payment. This was purportedly in conformity
involves the beginning of a special condition or status which with petitioner bank's procedure that once a client's account
has its own peculiar effects or results." was forwarded to its account representative, all remaining
checks outstanding as of the date the account was forwarded
Nowhere in this case did it appear that SSS demanded from were no longer presented for patent.
Moonwalk the payment of its monthly amortizations.What the
complaint itself showed was that SSS tried to enforce the On the theory that respondent defaulted in his payments, the
obligation sometime in September, 1977 by foreclosing the real check representing the payment for August 10, 1991 being
estate mortgages executed by Moonwalk in favor of SSS. But unsigned, petitioner demanded from private respondent the
this foreclosure did not push through upon Moonwalk's payment of the balance of the debt, including liquidated
requests and promises to pay in full.What is clear, therefore, is damages. The latter refused, prompting petitioner to file an
that Moonwalk was never in default because SSS never action for replevin and damages.
compelled performance.
ISSUE: WON private respondent may be held liable for the
Hence, no delay occurred and there was, therefore, no
alleged unpaid amount.
occasion when the penalty became demandable and
enforceable. Since there was no default in the performance of
RULING: NO.
the main obligation — payment of the loan — SSS was never
entitled to recover any penalty, not at the time it made the
Statement of Account and certainly, not after the It bears stressing that a contract of adhesion is just as binding
extinguishment of the principal obligation because then, all the as ordinary contracts. Contracts of adhesion are not
more that SSS had no reason to ask for the penalties. Thus, invalid per se; 7 they are not entirely prohibited. 8 The one
there could never be any occasion for waiver or even mistake in who adheres to the contract is in reality free to reject it
the application for payment because there was nothing for SSS entirely; if he adheres, he gives his consent. 9
to waive as its right to enforce the penalty did not arise.
While ambiguities in a contract of adhesion are to be
construed against the party that prepared the same, 10 this
G.R. No. 133107 March 25, 1999 rule applies only if the stipulations in such contract are
obscure or ambiguous. If the terms thereof are clear and
leave no doubt upon the intention of the contracting
RIZAL COMMERCIAL BANKING CORPORATION, petitioner,
parties, the literal meaning of its stipulations shall
vs.
control. 11 In the latter case, there would be no need for
COURT OF APPEALS and FELIPE LUSTRE, respondents.
construction.

paragraph 11 of the Chattel Mortgage Contract :


Facts:
11. In case the MORTGAGOR fails to pay any
of the installments, or to pay the interest
On March 10, 1993, private respondent Atty. Felipe Lustre
that may be due as provided in the said
purchased a Toyota Corolla from Toyota Shaw, Inc. for which
promissory note, the whole amount
he made a down payment of P164,620.00, the balance of the
remaining unpaid therein shall immediately
purchase price to be paid in 24 equal monthly installments.
become due and payable and the mortgage
Private respondent thus issued 24 postdated checks for the
on the property (ies) herein-above described
amount of P14,976.00 each. The first was dated April 10,
may be foreclosed by the MORTGAGEE, or
1991; subsequent checks were dated every 10th day of each
the MORTGAGEE may take any other legal
succeeding month.
action to enforce collection of the obligation
hereby secured, and in either case the
To secure the balance, private respondent executed a MORTGAGOR further agrees to pay the
promissory note 1 and a contract of chattel mortgage 2 over MORTGAGEE an additional sum of 25% of
the vehicle in favor of Toyota Shaw, Inc. The contract of the principal due and unpaid, as liquidated
chattel mortgage, in paragraph 11 thereof, provided for an damages, which said sum shall become part
acceleration clause stating that should the mortgagor default thereof. The MORTGAGOR hereby waives
in the payment of any installment, the whole amount reimbursement of the amount heretofore
remaining unpaid shall become due. In addition, the paid by him/it to the MORTGAGEE.
mortgagor shall be liable for 25% of the principal due as
liquidated damages.
The above terms leave no room for construction. All that is
required is the application thereof. By virtue of paragraph 11
2
above, petitioner submits that it "was justified in treating the However, no delivery was done that morning. Barzaga,
entire balance of the obligation as due and already upset, decided to dismiss his workers. He went to the
demandable." 15 Despite demand by petitioner, however, police station and lodged a complaints against Alviar and was
private respondent refused to pay the balance of the debt. entered in the police blotter. He then returned to the
Petitioner, in sum imputes delay on the part of private hardware. He saw the delivery truck but the materials he
respondent. bought are not yet loaded. He cancelled his transaction with
the store and went to other stores for materials. He was able
We do not subscribe to petitioner's theory. (Hindi daw guilty to buy from other stores. But since it was already late, he
of delay si private respondent) decided to start the construction on Dec. 23. Unfortunately,
the completion of the niche will not make it in time. The
Art. 170 of the Civil Code states that those who in the niche was completed in the the afternoon of Dec. 26. Unable
performance of their obligations are guilty of delay are liable to fulfill his wife’s dying wish, he filed a complaint for
for damages. The delay in the performance of the obligation, damages against Alviar.
however, must be either malicious or negligent. 16Thus, Alviar contended that no specific time of delivery was
assuming that private respondent was guilty of delay in the agreed upon between them, pointing out that the sale
payment of the value of unsigned check, private respondent invoices did not contain any stipulation as to the exact time of
cannot be held liable for damages. There is no imputation, delivery. Moreover, he also averred that the delivery truck
much less evidence, that private respondent acted with suffered a flat tire.
malice or negligence in failing to sign the check. Indeed, we RTC favored Barzaga. However upon appeal, the CA
agree with the Court of Appeals finding that such omission favored Alviar.
was mere "in advertence" on the part of private respondent.
Toyota salesperson Jorge Geronimo testified that he even Issue:
verified whether private respondent had signed all the checks WON respondent is liable for damages as to the delayed
and in fact returned three or four unsigned checks to him for deliveries.
signing. Even when the checks were delivered to petitioner, it
did not object to the unsigned check. In view of the lack of Held:
malice or negligence on the part of private respondent, Yes. The Court finds negligence on the part of Alviar
petitioner's blind and mechanical invocation of paragraph which caused the delay in the performance of his contractual
11 of the contract of chattel mortgage was unwarranted. obligation. Barzaga is entitled to be indemnified for damages
caused by the delay and breach of contract. The law expressly
provides that those who in the performance of their
As pointed out by the trial court, this whole controversy could
obligation are guilty of fraud, negligence, or delay and those
have been avoided if only petitioner bothered to call up
who in any manner contravene the tenor thereof, are liable
private respondent and ask him to sign the check. Good faith
for damages.
not only in compliance with its contractual obligations, 18 but
There was a verbal agreement on the specific time of
also in observance of the standard in human relations, for
delivery. The reason why Barzaga bought the materials
every person "to act with justice, give everyone his due, and
because of the assurance that the same will be delivered on
observe honesty and good faith." 19 behooved the bank to do
the specified time. Barzaga’s requested time and the
so.
storekeeper’s assurance constituted a positive verbal
commitment.
As to the flat tire, the Court held that private respondent
BARZAGA V CA
had no right to manipulate petitioner’s timetable and
G.R. No. 115129
substitute it with his own. Petitioner had a deadline to meet.
The flat tire is inexcusable and unacceptable. In fact, it was
Facts:
foreseeable and should have been reasonably guarded
On December 19, 1990, the wife of Ignacio Barzaga
against. The nature of respondent’s business requires that he
succumb to her ailment after prolonged pain and suffering.
should be ready at all times to meet contingencies of this
Before her death, she expressed her wish that she be laid to
kind.
rest before Christmas day, so her family will be spared from
Moreover, it was also found out that there was a
keeping vigil on her remains during Christmas.
withholding of information. Petitioner was not told that the
On Decemeber 21, 1990, as a fulfillment of his departed
delivery truck had previously delivered materials from a
wife’s wish, Petitioner Barzaga went to the hardware store of
distant location, which is also a reason of the delay. If
Respondent Angelito Alviar to inquire the availability of
petitioner was informed of such, he would have not
certain materials that will be used in the construction of the
committed in buying from their store. The deliberate
niche. He also asked if said materials can be delivered
suppression of this information is a manifestation of a certain
immediately. The storekeeper told him that she has to check
degree of bad faith on the part of the respondent’s
the pending deliveries for the following day.
storekeeper
In the morning of the next day, Barzaga returned to the
This case is clearly one of non-performance of a
hardware store and bought the said materials. He requested
reciprocal obligation. In their contract, the petitioner had
that the said materials be delivered at 8 o’clock in the
complied fully by paying for the purchase. It was incumbent
morning at the Memorial Cemetery of Dasmarinas, Cavite.
upon the respondent to immediately fulfill his obligaiton to
The storekeeper agreed to deliver the materials on the deliver the goods..
requested time. Upon paying, Barzaga left and joined his
workers at the cemetery.
An hour have passed from the agreed time, no materials
POLO S. PANTALEON vs. AMERICAN EXPRESS
was delivered. Barzaga returned to the hardware store and
INTERNATIONAL, INC.
inquired about the delay. The storekeeper, told him that the
delivery truck is not yet around but have already left the
garage. She also assured him that the materials will be FACTS
delivered that morning.
3
The petitioner, lawyer Polo Pantaleon, his wife Julialinda, CA rendered a decision reversing the award of damages in
daughter Anna Regina and son Adrian Roberto, joined an favor of Pantaleon, holding that respondent had not
escorted tour of Western Europe in October 1991. The last breached its obligations to petitioner. Hence, this petition.
day of the tour, the group arrived at the Coster Diamond
House in Amsterdambefore 9:00 a.m. The group had agreed ISSUE
that the visit to Coster should end by 9:30 a.m. to allow
enough time to take in a guided city tour of Amsterdam. The WON respondenthad committed a breach of its obligations to
group was led to the store’s showroom to allow them to Pantaleon
purchase. Mrs.Pantaleonpurchased a diamond close enough
to the2.5 karat diamond brilliant cut she wanted, as well asa
HELD
pendant and a chain, all of which totaledU.S.
$13,826.00.Mr.Pantaleon presented his American Express
Yes. The RTC had concluded, based on the testimonial
credit card together with his passport to the Coster sales
representations of Pantaleon and respondent’s credit
clerk. This occurred 15 minutes before the tour group was
authorizer, Edgardo Jaurigue, thatthe normal approval time
slated to depart from the store. After the usual process, the
for purchases was "a matter of seconds." Based on that
charge purchase was referred electronically to respondent’s
standard, respondent had been in clear delay with respect to
Amsterdam office. 10mins later, the store clerk informed
the subject transactions. However, it made two critical
Pantaleon that his AmexCard had not yet been approved. It
conclusions in favor of respondent:First, the appellate court
was already 9:40 a.m., and he was already worried about
ruled that the delay was not attended by bad faith, malice, or
further inconveniencing the tour group that was already
gross negligence. Second, it ruled that respondent "had
waiting for them, Pantaleon asked the store clerk to cancel
the sale but the manager asked them to wait. After 15 exercised diligent efforts to effect the approval" of the
purchases, which were "not in accordance with the charge
minutes, the store manager informed Pantaleon that
pattern" petitioner had established for himself, as
respondent had demanded bank references. Pantaleon
exemplified by the fact that at Coster, he was "making his
supplied the names of his depositary banks.
very first single charge purchase of US$13,826," and "the
record of [petitioner]’s past spending with [respondent] at
30 minutes after the tour group was supposed to have left
the time does not favorably support his ability to pay for such
the store, Coster decided to release the items even without
purchase."17
respondent’s approval of the purchase. The spouses
Pantaleon returned to the bus. The tour group’s visible
On the premise that there was an obligation on the part of
irritation was aggravated when the tour guide announced
respondent "to approve or disapprove with dispatch the
that the city tour was to be cancelled due to lack of time, as
charge purchase," petitioner argues that the failure to timely
they had to catch a 3PMferry.Mrs.Pantaleon ended up
approve or disapprove the purchase constituted
weeping, while husband had to take a tranquilizer to calm his
morasolvendi on the part of respondent in the performance
nerves.It later emerged that the Approval Code for
of its obligation. For its part, respondent characterizes the
Pantaleon’s purchase was transmitted to respondent’s
depiction by petitioner of its obligation to him as "to approve
Amsterdam office 78 minutes from the time the purchases
purchases instantaneously or in a matter of seconds."
were electronically transmitted by the jewelry store to
respondent’s Amsterdam office.After the tour the Pantaleon
family proceeded to the United States before returning to Petitioner correctly cites that under morasolvendi, the three
Manila. While in the United States, Pantaleon continued to requisites for a finding of default are that:
use his AmEx card, several times without hassle or delay,
but with two other incidents similar to the Amsterdam A. The obligation is demandable and liquidated;
brouhaha;one was while purchasing golf equipment which he B. The debtor delays performance; and
cancelled [because 30mins na, and still no approval] and C. The creditor judicially or extrajudicially requires the
borrowed money from his friend instead, and another while debtor’s performance.
purchasing shoes for his children [20mins had transpired
before approval]. Petitioner asserts that the Court of Appeals had wrongly
applied the principle of moraaccipiendi, which relates to
After coming back to Manila, Pantaleon sent a letter through delay on the part of the obligee in accepting the performance
counsel to the respondent, demanding an apology for the of the obligation by the obligor.
"inconvenience, humiliation and embarrassment he and his
family thereby suffered" for respondent’s refusal to provide The requisites of moraaccipiendi are:
credit authorization for the aforementioned purchases.In
response, respondent sent a letter stating among others that A. An offer of performance by the debtor who has the
the delay in authorizing the purchase from Coster was required capacity;
attributable to the circumstance that the charged purchase B. The offer must be to comply with the prestationas it
of US $13,826.00 "was out of the usual charge purchase should be performed; and
pattern established.” Since respondent refused to accede to C. The creditor refuses the performance without just
Pantaleon’s demand for an apology, the aggrieved cardholder cause.
instituted an action for damages with the RTC of Makati City.
RTC rendered a decision in favor of Pantaleon, awarding him The error of the appellate court, argues petitioner, is in
P500,000.00 as moral damages, P300,000.00 as exemplary relying on the invocation by respondent of "just cause" for
damages, P100,000.00 as attorney’s fees, and P85,233.01 as the delay, since while just cause is determinative of
expenses of litigation. Respondent filed a Notice of Appeal, moraaccipiendi, it is not so with the case of morasolvendi.
while Pantaleon moved for partial reconsideration, praying
that the trial court award the increased amount of moral
Generally, the relationship between a credit card provider
and exemplary damages he had prayed for. RTC denied, and
and its card holders is that of creditor-debtor, with the card
thereafter gave due course to respondent’s Notice of Appeal.
4
company as the creditor extending loans and credit to the RTC.Those circumstances are fairly unusual, and should not
card holder, who as debtor is obliged to repay the creditor. give rise to a general entitlement for damages under a more
In order for us to appreciate that respondent was in mundane set of facts.
morasolvendi, we will have to first recognize that there was
indeed an obligation on the part of respondent to act on We sustain the amount of moral damages awarded to
petitioner’s purchases with "timely dispatch," or for the petitioner by the RTC. There is no hard-and-fast rule in
purposes of this case, within a period significantly less than determining what would be a fair and reasonable amount of
the one hour it apparently took before the purchase at Coster moral damages, since each case must be governed by its own
was finally approved.The findings of the trial court, to our peculiar facts, however, it must be commensurate to the loss
mind, amply established that the tardiness on the part of or injury suffered.28 Petitioner’s original prayer for
respondent in acting on petitioner’s purchase at Coster did P5,000,000.00 for moral damages is excessive under the
constitute culpable delay on its part in complying with its circumstances, and the amount awarded by the trial court of
obligation to act promptly on its customer’s purchase P500,000.00 in moral damages more seemly.1avvphi1
request, whether such action be favorable or
unfavorable.The Court is convinced that defendant’s delay Likewise, we deem exemplary damages available under the
constitutes breach of its contractual obligation to act on his circumstances, and the amount of P300,000.00 appropriate.
use of the card abroad "with special handling” meaning with There is similarly no cause though to disturb the determined
priority. award of P100,000.00 as attorney’s fees, and P85,233.01 as
expenses of litigation.
Notwithstanding the popular notion that credit card
purchases are approved "within seconds," there really is no LORENZO SHIPPING CORP., petitioner, vs. BJ MARTHEL
strict, legally determinative point of demarcation on how long INTERNATIONAL, INC., respondent.
must it take for a credit card company to approve or
disapprove a customer’s purchase, much less one specifically FACTS:
contracted upon by the parties. Yet this is one of those
instances when it would be a long enough time for the This is a petition for review seeking to set aside the
customer to walk to a bank a kilometer away, withdraw Decision[1] of the Court of Appeals in CA-G.R. CV No. 54334
money over the counter, and return to the store. The and its Resolution denying petitioners motion for
culpable failure of respondent herein is not the failure to reconsideration.
timely approve petitioner’s purchase, but the more
elemental failure to timely act on the same, whether Petitioner Lorenzo Shipping Corporation is a domestic
favorably or unfavorably. Even assuming that respondent’s corporation engaged in coastwise shipping. It used to own
credit authorizers did not have sufficient basis on hand to the cargo vessel M/V Dadiangas Express.
make a judgment, we see no reason why respondent could Upon the other hand, respondent BJ Marthel
not have promptly informed petitioner the reason for the International, Inc. is a business entity engaged in trading,
delay, and duly advised him that resolving the same could marketing, and selling of various industrial commodities. It is
take some time. In that way, petitioner would have had also an importer and distributor of different brands of
informed basis on whether or not to pursue the transaction engines and spare parts.
at Coster, given the attending circumstances.
From 1987 up to the institution of this case, respondent
x xx supplied petitioner with spare parts for the latters marine
engines. Sometime in 1989, petitioner asked respondent for
a quotation for various machine parts. Acceding to this
Otherwise[kung hindimabilisang approval ng credit card
request, respondent furnished petitioner with a formal
purchases], the object of credit or charge cards would be lost;
quotation,[2] thus:
it would be so inconvenient to use that buyers and
consumers would be better off carrying bundles of currency
or traveller’s checks, which can be delivered and accepted M
quickly. Such right was not accorded to plaintiff in the ay 31, 1989
instances complained off for reasons known only to M
defendant at that time. This, to the Court’s mind, amounts to INQ-6093
a wanton and deliberate refusal to comply with its
contractual obligations, or at least abuse of its rights, under LORENZO SHIPPING LINES
the contract. Pier 8, North Harbor
Manila
It should be emphasized that the reason why petitioner is
entitled to damages is not simply because respondent SUBJECT: PARTS FOR ENGINE MODEL
incurred delay, but because the delay, for which culpability MITSUBISHI 6UET 52/60
lies under Article 1170, led to the particular injuries under
Article 2217 of the Civil Code for which moral damages are Dear Mr. Go:
remunerative. Moral damages do not avail to soothe the
plaints of the simply impatient, so this decision should not be We are pleased to submit our offer for your above subject
cause for relief for those who time the length of their credit requirements.
card transactions with a stopwatch. The somewhat unusual
attending circumstances to the purchase at Coster – that Description Qty. Unit Price Total Price
there was a deadline for the completion of that purchase by
petitioner before any delay would redound to the injury of his
Nozzle Tip 6 pcs. P 5,520.00
several traveling companions – gave rise to the moral shock,
33,120.00
mental anguish, serious anxiety, wounded feelings and social
humiliation sustained by the petitioner, as concluded by the
5
Plunger & Barrel 6 pcs. 27,630.00
165,780.00 M
Cylinder Head 2 pcs. 1,035,000.00 a
2,070,000.00 n
Cylinder Liner 1 set a
477,000.00 g
e
TOTAL PRICE r
FOB
P2,745,900.00 Petitioner thereafter issued to respondent Purchase
MANILA Order No. 13839,[3] dated 02 November 1989, for the
procurement of one set of cylinder liner, valued at P477,000,
___________ to be used for M/V Dadiangas Express. The purchase order
was co-signed by Jose Go, Jr., petitioners vice-president, and
DELIVERY: Within 2 months after receipt of firm
Henry Pajarillo. Quoted hereunder is the pertinent portion of
order. the purchase order:
TERMS: 25% upon delivery, balance payable in 5 bi-
monthly equal
Name of Description Qty. Amount
Installment[s] not to exceed 90
days.
CYL. LINER M/E 1 SET P477,000.00
We trust you find our above offer acceptable and look
forward to your most valued order. NOTHING FOLLOW
INV. #
V
e TERM OF PAYMENT: 25% DOWN PAYMENT
r 5 BI-MONTHLY
y INSTALLMENT[S]
Instead of paying the 25% down payment for the first
t cylinder liner, petitioner issued in favor of respondent ten
r postdated checks[4] to be drawn against the formers account
u with Allied Banking Corporation. The checks were supposed
l to represent the full payment of the aforementioned cylinder
y liner.

y Subsequently, petitioner issued Purchase Order No.


o 14011,[5] dated 15 January 1990, for yet another unit of
u cylinder liner. This purchase order stated the term of
r payment to be 25% upon delivery, balance payable in 5 bi-
s monthly equal installment[s].[6] Like the purchase order of 02
, November 1989, the second purchase order did not state the
date of the cylinder liners delivery.
( On 26 January 1990, respondent deposited petitioners
S check that was postdated 18 January 1990, however, the
G same was dishonored by the drawee bank due to
D insufficiency of funds. The remaining nine postdated checks
) were eventually returned by respondent to petitioner.

H The parties presented disparate accounts of what


E happened to the check which was previously dishonored.
N Petitioner claimed that it replaced said check with a good
R one, the proceeds of which were applied to its other
Y obligation to respondent. For its part, respondent insisted
that it returned said postdated check to petitioner.
P
Respondent thereafter placed the order for the two
A
cylinder liners with its principal in Japan, Daiei Sangyo Co.
J
Ltd., by opening a letter of credit on 23 February 1990 under
A
its own name with the First Interstate Bank of Tokyo.
R
I On 20 April 1990, Pajarillo delivered the two cylinder
L liners at petitioners warehouse in North Harbor, Manila. The
L sales invoices[7] evidencing the delivery of the cylinder liners
O both contain the notation subject to verification under which
the signature of Eric Go, petitioners warehouseman,
S appeared.
a
l Respondent thereafter sent a Statement of Account
e dated 15 November 1990[8] to petitioner. While the other
s items listed in said statement of account were fully paid by
petitioner, the two cylinder liners delivered to petitioner on
6
20 April 1990 remained unsettled. Consequently, Mr. Prior to the commencement of trial, petitioner filed a
Alejandro Kanaan, Jr., respondents vice-president, sent a Motion (For Leave To Sell Cylinder Liners)[21] alleging therein
demand letter dated 02 January 1991[9] to petitioner that [w]ith the passage of time and with no definite end in
requiring the latter to pay the value of the cylinder liners sight to the present litigation, the cylinder liners run the risk
subjects of this case. Instead of heeding the demand of of obsolescence and deterioration[22] to the prejudice of the
respondent for the full payment of the value of the cylinder parties to this case. Thus, petitioner prayed that it be allowed
liners, petitioner sent the former a letter dated 12 March to sell the cylinder liners at the best possible price and to
1991[10] offering to pay only P150,000 for the cylinder liners. place the proceeds of said sale in escrow. This motion,
In said letter, petitioner claimed that as the cylinder liners unopposed by respondent, was granted by the trial court
were delivered late and due to the scrapping of the M/V through the Order of 17 March 1991.[23]
Dadiangas Express, it (petitioner) would have to sell the
After trial, the court a quo dismissed the action, the
cylinder liners in Singapore and pay the balance from the
decretal portion of the Decision stating:
proceeds of said sale.
Shortly thereafter, another demand letter dated 27 WHEREFORE, the complaint is hereby dismissed, with costs
March 1991[11] was furnished petitioner by respondents against the plaintiff, which is ordered to pay P50,000.00 to
counsel requiring the former to settle its obligation to the defendant as and by way of attorneys fees.[24]
respondent together with accrued interest and attorneys
fees. The trial court held respondent bound to the quotation
Due to the failure of the parties to settle the matter, it submitted to petitioner particularly with respect to the
respondent filed an action for sum of money and damages terms of payment and delivery of the cylinder liners. It also
before the Regional Trial Court (RTC) of Makati City. In its declared that respondent had agreed to the cancellation of
complaint,[12]respondent (plaintiff below) alleged that the contract of sale when it returned the postdated checks
despite its repeated oral and written demands, petitioner issued by petitioner. Respondents counterclaims for moral,
obstinately refused to settle its obligations. Respondent exemplary, and compensatory damages were dismissed for
prayed that petitioner be ordered to pay for the value of the insufficiency of evidence.
cylinder liners plus accrued interest of P111,300 as of May Respondent moved for the reconsideration of the trial
1991 and additional interest of 14% per annum to be courts Decision but the motion was denied for lack of
reckoned from June 1991 until the full payment of the merit.[25]
principal; attorneys fees; costs of suits; exemplary damages;
actual damages; and compensatory damages. Aggrieved by the findings of the trial court, respondent
filed an appeal with the Court of Appeals[26] which reversed
On 25 July 1991, and prior to the filing of a responsive and set aside the Decision of the court a quo. The appellate
pleading, respondent filed an amended complaint with court brushed aside petitioners claim that time was of the
preliminary attachment pursuant to Sections 2 and 3, Rule 57 essence in the contract of sale between the parties herein
of the then Rules of Court.[13] Aside from the prayer for the considering the fact that a significant period of time had
issuance of writ of preliminary attachment, the amendments lapsed between respondents offer and the issuance by
also pertained to the issuance by petitioner of the postdated petitioner of its purchase orders. The dispositive portion of
checks and the amounts of damages claimed. the Decision of the appellate court states:
In an Order dated 25 July 1991,[14] the court a
quo granted respondents prayer for the issuance of a WHEREFORE, the decision of the lower court is REVERSED and
preliminary attachment. On 09 August 1991, petitioner filed SET ASIDE. The appellee is hereby ORDERED to pay the
an Urgent Ex-Parte Motion to Discharge Writ of appellant the amount of P954,000.00, and accrued interest
Attachment[15] attaching thereto a counter-bond as required computed at 14% per annum reckoned from May, 1991.[27]
by the Rules of Court. On even date, the trial court issued an
Order[16] lifting the levy on petitioners properties and the The Court of Appeals also held that respondent could
garnishment of its bank accounts. not have incurred delay in the delivery of cylinder liners as no
demand, judicial or extrajudicial, was made by respondent
Petitioner afterwards filed its Answer[17] alleging therein upon petitioner in contravention of the express provision of
that time was of the essence in the delivery of the cylinder Article 1169 of the Civil Code which provides:
liners and that the delivery on 20 April 1990 of said items was
late as respondent committed to deliver said items within
Those obliged to deliver or to do something incur in delay
two (2) months after receipt of firm order[18] from petitioner.
from the time the obligee judicially or extrajudicially demands
Petitioner likewise sought counterclaims for moral damages,
from them the fulfillment of their obligation.
exemplary damages, attorneys fees plus appearance fees,
and expenses of litigation.
Likewise, the appellate court concluded that there was
Subsequently, respondent filed a Second Amended no evidence of the alleged cancellation of orders by
Complaint with Preliminary Attachment dated 25 October petitioner and that the delivery of the cylinder liners on 20
1991.[19] The amendment introduced dealt solely with the April 1990 was reasonable under the circumstances.
number of postdated checks issued by petitioner as full
payment for the first cylinder liner it ordered from ISSUES: On 22 May 2000, petitioner filed a motion for
respondent. Whereas in the first amended complaint, only reconsideration of the Decision of the Court of Appeals but
nine postdated checks were involved, in its second amended this was denied through the resolution of 06 October
complaint, respondent claimed that petitioner actually issued 2000.[28] Hence, this petition for review which basically raises
ten postdated checks. Despite the opposition by petitioner, the issues of whether or not respondent incurred delay in
the trial court admitted respondents Second Amended performing its obligation under the contract of sale and
Complaint with Preliminary Attachment.[20] whether or not said contract was validly rescinded by
petitioner.

7
That a contract of sale was entered into by the parties contract. The last stage is the consummation of the contract
is not disputed. Petitioner, however, maintains that its wherein the parties fulfill or perform the terms agreed upon
obligation to pay fully the purchase price was extinguished in the contract, culminating in the extinguishment thereof.
because the adverted contract was validly terminated due to
In the instant case, the formal quotation provided by
respondents failure to deliver the cylinder liners within the
respondent represented the negotiation phase of the
two-month period stated in the formal quotation dated 31
subject contract of sale between the parties. As of that time,
May 1989.
the parties had not yet reached an agreement as regards the
The threshold question, then, is: Was there late delivery terms and conditions of the contract of sale of the cylinder
of the subjects of the contract of sale to justify petitioner to liners. Petitioner could very well have ignored the offer or
disregard the terms of the contract considering that time tendered a counter-offer to respondent while the latter could
was of the essence thereof? have, under the pertinent provision of the Civil
Code,[38] withdrawn or modified the same. The parties were
In determining whether time is of the essence in a
at liberty to discuss the provisions of the contract of sale prior
contract, the ultimate criterion is the actual or apparent
to its perfection. In this connection, we turn to the
intention of the parties and before time may be so regarded testimonies of Pajarillo and Kanaan, Jr., that the terms of the
by a court, there must be a sufficient manifestation, either in
offer were, indeed, renegotiated prior to the issuance of
the contract itself or the surrounding circumstances of that
Purchase Order No. 13839.
intention.[29] Petitioner insists that although its purchase
orders did not specify the dates when the cylinder liners were During the hearing of the case on 28 January 1993,
supposed to be delivered, nevertheless, respondent should Pajarillo testified as follows: (I DON'T KNOW IF THIS PORTION
abide by the term of delivery appearing on the quotation it OF THE CASE IS IMPORTANT OR NOT BUT I'M LEAVING IT
submitted to petitioner.[30]Petitioner theorizes that the HERE IN CASE YOU WANT TO READ IT)
quotation embodied the offer from respondent while the
Q: You testified Mr. Witness, that you submitted a
purchase order represented its (petitioners) acceptance of
quotation with defendant Lorenzo Shipping
the proposed terms of the contract of sale.[31] Thus, petitioner
Corporation dated rather marked as Exhibit A
is of the view that these two documents cannot be taken
separately as if there were two distinct contracts.[32] We do stating the terms of payment and delivery of
the cylinder liner, did you not?
not agree.
A: Yes sir.
It is a cardinal rule in interpretation of contracts that if
the terms thereof are clear and leave no doubt as to the Q: I am showing to you the quotation which is
intention of the contracting parties, the literal meaning shall marked as Exhibit A there appears in the
control.[33]However, in order to ascertain the intention of the quotation that the delivery of the cylinder
parties, their contemporaneous and subsequent acts should liner will be made in two months time from
be considered.[34] While this Court recognizes the principle the time you received the confirmation of the
that contracts are respected as the law between the order. Is that correct?
contracting parties, this principle is tempered by the rule that
the intention of the parties is primordial[35] and once the A: Yes sir.
intention of the parties has been ascertained, that element is Q: Now, after you made the formal quotation
deemed as an integral part of the contract as though it has which is Exhibit A how long a time did the
been originally expressed in unequivocal terms.[36] defendant make a confirmation of the order?
HELD: In the present case, we cannot subscribe to the A: After six months.
position of petitioner that the documents, by themselves,
embody the terms of the sale of the cylinder liners. One can Q: And this is contained in the purchase order
easily glean the significant differences in the terms as stated given to you by Lorenzo Shipping
in the formal quotation and Purchase Order No. 13839 with Corporation?
regard to the due date of the down payment for the first
A: Yes sir.
cylinder liner and the date of its delivery as well as Purchase
Order No. 14011 with respect to the date of delivery of the Q: Now, in the purchase order dated November 2,
second cylinder liner. While the quotation provided by 1989 there appears only the date the terms
respondent evidently stated that the cylinder liners were of payment which you required of them of
supposed to be delivered within two months from receipt of 25% down payment, now, it is stated in the
the firm order of petitioner and that the 25% down payment purchase order the date of delivery, will you
was due upon the cylinder liners delivery, the purchase explain to the court why the date of delivery
orders prepared by petitioner clearly omitted these of the cylinder liner was not mentioned in the
significant items. The petitioners Purchase Order No. 13839 purchase order which is the contract between
made no mention at all of the due dates of delivery of the you and Lorenzo Shipping Corporation?
first cylinder liner and of the payment of 25% down payment.
Its Purchase Order No. 14011 likewise did not indicate the A: When Lorenzo Shipping Corporation inquired
due date of delivery of the second cylinder liner. from us for that cylinder liner, we have
inquired [with] our supplier in Japan to give
In the case of Bugatti v. Court of Appeals,[37] we us the price and delivery of that item. When
reiterated the principle that [a] contract undergoes three we received that quotation from our supplier
distinct stages preparation or negotiation, its perfection, and it is stated there that they can deliver within
finally, its consummation. Negotiation begins from the time two months but we have to get our
the prospective contracting parties manifest their interest in confirmed order within June.
the contract and ends at the moment of agreement of the
parties. The perfection or birth of the contract takes place Q: But were you able to confirm the order from
when the parties agree upon the essential elements of the your Japanese supplier on June of that year?

8
A: No sir. caused by the latter when it omitted the date of delivery of
the cylinder liners in the purchase orders and varied the term
Q: Why? Will you tell the court why you were not
with respect to the due date of the down payment,[41] said
able to confirm your order with your obscurity must be resolved against it.[42]
Japanese supplier?
Relative to the above discussion, we find the case
A: Because Lorenzo Shipping Corporation did not
of Smith, Bell & Co., Ltd. v. Matti,[43] instructive. There, we
give us the purchase order for that cylinder
held that
liner.
Q: And it was only on November 2, 1989 when When the time of delivery is not fixed or is stated in general
they gave you the purchase order? and indefinite terms, time is not of the essence of the
contract. . . .
A: Yes sir.
Q: So upon receipt of the purchase order from In such cases, the delivery must be made within a reasonable
Lorenzo Shipping Lines in 1989 did you time.
confirm the order with your Japanese
supplier after receiving the purchase order The law implies, however, that if no time is fixed, delivery
dated November 2, 1989? shall be made within a reasonable time, in the absence of
anything to show that an immediate delivery intended. . . .
A: Only when Lorenzo Shipping Corporation will
give us the down payment of 25%.[39]
We also find significant the fact that while petitioner
For his part, during the cross-examination conducted by alleges that the cylinder liners were to be used for dry dock
counsel for petitioner, Kanaan, Jr., testified in the following repair and maintenance of its M/V Dadiangas Express
manner: between the later part of December 1989 to early January
1990, the record is bereft of any indication that respondent
WITNESS: This term said 25% upon delivery.
was aware of such fact. The failure of petitioner to notify
Subsequently, in the final contract, what was
respondent of said date is fatal to its claim that time was of
agreed upon by both parties was 25% down
the essence in the subject contracts of sale.
payment.
In addition, we quote, with approval, the keen
Q: When?
observation of the Court of Appeals:
A: Upon confirmation of the order.
......................
...
Q: And when was the down payment supposed to In the instant case, the appellee should have provided for an
be paid? allowance of time and made the purchase order earlier if
indeed the said cylinder liner was necessary for the repair of
A: It was not stated when we were supposed to the vessel scheduled on the first week of January, 1990. In
receive that. Normally, we expect to receive fact, the appellee should have cancelled the first purchase
at the earliest possible time. Again, that order when the cylinder liner was not delivered on the date it
would depend on the customers. Even after now says was necessary. Instead it issued another purchase
receipt of the purchase order which was what order for the second set of cylinder liner. This fact negates
happened here, they re-negotiated the terms appellees claim that time was indeed of the essence in the
and sometimes we do accept that. consummation of the contract of sale between the
Q: Was there a re-negotiation of this term? parties.[44]

A: This offer, yes. We offered a final requirement Finally, the ten postdated checks issued in November
of 25% down payment upon delivery. 1989 by petitioner and received by the respondent as full
Q: What was the re-negotiated term? payment of the purchase price of the first cylinder liner
supposed to be delivered on 02 January 1990 fail to impress.
A: 25% down payment It is not an indication of failure to honor a commitment on
the part of the respondent. The earliest maturity date of the
Q: To be paid when?
checks was 18 January 1990. As delivery of said checks could
A: Supposed to be paid upon order.[40] produce the effect of payment only when they have been
cashed,[45] respondents obligation to deliver the first cylinder
The above declarations remain unassailed. Other than
liner could not have arisen as early as 02 January 1990 as
its bare assertion that the subject contracts of sale did not
claimed by petitioner since by that time, petitioner had yet to
undergo further renegotiation, petitioner failed to proffer
fulfill its undertaking to fully pay for the value of the first
sufficient evidence to refute the above testimonies of cylinder liner. As explained by respondent, it proceeded with
Pajarillo and Kanaan, Jr.
the placement of the order for the cylinder liners with its
Notably, petitioner was the one who caused the principal in Japan solely on the basis of its previously
preparation of Purchase Orders No. 13839 and No. 14011 yet harmonious business relationship with petitioner.
it utterly failed to adduce any justification as to why said
As an aside, let it be underscored that [e]ven where
documents contained terms which are at variance with those
time is of the essence, a breach of the contract in that
stated in the quotation provided by respondent. The only
respect by one of the parties may be waived by the other
plausible reason for such failure on the part of petitioner is
partys subsequently treating the contract as still in
that the parties had, in fact, renegotiated the proposed terms
force.[46] Petitioners receipt of the cylinder liners when they
of the contract of sale. Moreover, as the obscurity in the
were delivered to its warehouse on 20 April 1990 clearly
terms of the contract between respondent and petitioner was
9
indicates that it considered the contract of sale to be still In the first quarter of 1998, petitioner, Solar
subsisting up to that time. Indeed, had the contract of sale Harvest, Inc., entered into an agreement with
been cancelled already as claimed by petitioner, it no longer respondent, Davao Corrugated Carton Corporation, for
had any business receiving the cylinder liners even if said the purchase of corrugated carton boxes, specifically
receipt was subject to verification. By accepting the cylinder designed for petitioner's business of exporting fresh
liners when these were delivered to its warehouse, petitioner bananas, at US$1.10 each. The agreement was not
indisputably waived the claimed delay in the delivery of said reduced into writing. To get the production underway,
items. petitioner deposited, on March 31, 1998, US$40,150.00
in respondent's US Dollar Savings Account with
We, therefore, hold that in the subject contracts, time
Westmont Bank, as full payment for the ordered boxes.
was not of the essence. The delivery of the cylinder liners
on 20 April 1990 was made within a reasonable period of Despite such payment, petitioner did not
time considering that respondent had to place the order for receive any boxes from respondent. On January 3, 2001,
the cylinder liners with its principal in Japan and that the petitioner wrote a demand letter for reimbursement of
latter was, at that time, beset by heavy volume of work.[47] the amount paid. 3 On February 19, 2001, respondent
replied that the boxes had been completed as early as
There having been no failure on the part of the April 3, 1998 and that petitioner failed to pick them up
respondent to perform its obligation, the power to rescind from the former's warehouse 30 days from completion,
the contract is unavailing to the petitioner. Article 1191 of as agreed upon. Respondent mentioned that petitioner
the New Civil Code runs as follows: even placed an additional order of 24,000 boxes, out of
which, 14,000 had been manufactured without any
The power to rescind obligations is implied in reciprocal advanced payment from petitioner. Respondent then
ones, in case one of the obligors should not comply with demanded petitioner to remove the boxes from the
what is incumbent upon him. factory and to pay the balance of US$15,400.00 for the
additional boxes and P132,000.00 as storage fee.
The law explicitly gives either party the right to rescind
In reply, petitioner denied that it made a second
the contract only upon the failure of the other to perform the
order of 24,000 boxes and that respondent already
obligation assumed thereunder.[48] The right, however, is not
completed the initial order of 36,500 boxes and 14,000
an unbridled one.
boxes out of the second order. It maintained that
In other words, the party who deems the contract respondent only manufactured a sample of the ordered
violated may consider it resolved or rescinded, and act boxes and that respondent could not have produced
accordingly, without previous court action, but it proceeds at 14,000 boxes without the required pre-payments. 6
its own risk. For it is only the final judgment of the
During trial, petitioner presented Que as its sole
corresponding court that will conclusively and finally settle witness. Que testified that he ordered the boxes from
whether the action taken was or was not correct in law. But
respondent and deposited the money in respondent's
the law definitely does not require that the contracting party
account. 7 He specifically stated that, when he visited
who believes itself injured must first file suit and wait for a
respondent's factory, he saw that the boxes had no print
judgment before taking extrajudicial steps to protect its of petitioner's logo. 8 A few months later, he followed-up
interest. Otherwise, the party injured by the others breach
the order and was told that the company had full
will have to passively sit and watch its damages accumulate
production, and thus, was promised that production of
during the pendency of the suit until the final judgment of
the order would be rushed. He told respondent that it
rescission is rendered when the law itself requires that he
should indeed rush production because the need for the
should exercise due diligence to minimize its own
boxes was urgent. Thereafter, he asked his partner,
damages.[50]
Alfred Ong, to cancel the order because it was already
Here, there is no showing that petitioner notified late for them to meet their commitment to ship the
respondent of its intention to rescind the contract of sale bananas to China. 9 On cross-examination, Que further
between them. Quite the contrary, respondents act of testified that China Zero Food, the Chinese company that
proceeding with the opening of an irrevocable letter of credit ordered the bananas, was sending a ship to Davao to get
on 23 February 1990 belies petitioners claim that it notified the bananas, but since there were no cartons, the ship
respondent of the cancellation of the contract of sale. Truly, could not proceed. He said that, at that time, bananas
no prudent businessman would pursue such action knowing from Tagum Agricultural Development Corporation
that the contract of sale, for which the letter of credit was (TADECO) were already there. He denied that petitioner
opened, was already rescinded by the other party. made an additional order of 24,000 boxes. He explained
that it took three years to refer the matter to counsel
WHEREFORE, premises considered, the instant Petition because respondent promised to pay. 10
for Review on Certiorari is DENIED. The Decision of the Court
of Appeals, dated 28 April 2000, and its Resolution, dated 06 For respondent, BienvenidoEstanislao
October 2000, are hereby AFFIRMED. No costs. (Estanislao) testified that he met Que in Davao in
October 1998 to inspect the boxes and that the latter got
samples of them. In February 2000, they inspected the
[G.R. No. 176868. July 26, 2010.] boxes again and Que got more samples. Estanislao said
that petitioner did not pick up the boxes because the
SOLAR HARVEST, INC., petitioner, vs. ship did not arrive. 11 Jaime Tan (Tan), president of
DAVAO CORRUGATED CARTON respondent, also testified that his company finished
CORPORATION, respondent. production of the 36,500 boxes on April 3, 1998 and that
petitioner made a second order of 24,000 boxes. He said
that the agreement was for respondent to produce the
FACTS: boxes and for petitioner to pick them up from the
warehouse. 12 He also said that the reason why

10
petitioner did not pick up the boxes was that the ship demands from them the fulfillment of
that was to carry the bananas did not their obligation.
arrive. 13 According to him, during the last visit of Que
and Estanislao, he asked them to withdraw the boxes Evident from the records and even from the
immediately because they were occupying a big space in allegations in the complaint was the lack of demand by
his plant, but they, instead, told him to sell the cartons as petitioner upon respondent to fulfill its obligation to
rejects. He was able to sell 5,000 boxes at P20.00 each manufacture and deliver the boxes. The Complaint only
for a total of P100,000.00. They then told him to apply alleged that petitioner made a "follow-up" upon
the said amount to the unpaid balance. respondent, which, however, would not qualify as a
demand for the fulfillment of the obligation. Petitioner's
In its March 2, 2004 Decision, the Regional Trial witness also testified that they made a follow-up of the
Court (RTC) ruled that respondent did not commit any boxes, but not a demand. Note is taken of the fact that,
breach of faith that would justify rescission of the with respect to their claim for reimbursement, the
contract and the consequent reimbursement of the Complaint alleged and the witness testified that a
amount paid by petitioner. The RTC said that respondent demand letter was sent to respondent. Without a
was able to produce the ordered boxes but petitioner previous demand for the fulfillment of the obligation,
failed to obtain possession thereof because its ship did petitioner would not have a cause of action for
not arrive. It thus dismissed the complaint and rescission against respondent as the latter would not
respondent's counterclaims, disposing as follows: yet be considered in breach of its contractual obligation.
Petitioner filed a notice of appeal with the CA. As correctly observed by the CA, aside from the
On September 21, 2006, the CAdenied the pictures of the finished boxes and the production report
appeal for lack of merit. 15 The appellate court held that thereof, there is ample showing that the boxes had
petitioner failed to discharge its burden of proving what already been manufactured by respondent. There is the
it claimed to be the parties' agreement with respect to testimony of Estanislao who accompanied Que to the
the delivery of the boxes. According to the CA, it was factory, attesting that, during their first visit to the
unthinkable that, over a period of more than two years, company, they saw the pile of petitioner's boxes and Que
petitioner did not even demand for the delivery of the took samples thereof. Que, petitioner's witness, himself
boxes. The CA added that even assuming that the confirmed this incident. He testified that Tan pointed the
agreement was for respondent to deliver the boxes, boxes to him and that he got a sample and saw that it
respondent would not be liable for breach of contract as was blank. Que's absolute assertion that the boxes were
petitioner had not yet demanded from it the delivery of not manufactured is, therefore, implausible and
the boxes. 16 suspicious.

ISSUE:WON Solar Harvest, Inc. may rescind the contract. In sum, the Court finds that petitioner failed to establish a
cause of action for rescission, the evidence having shown that
HELD:NO. respondent did not commit any breach of its contractual
Petitioner's claim for reimbursement is actually obligation. As previously stated, the subject boxes are still
one for rescission (or resolution) of contract under Article within respondent's premises. To put a rest to this dispute,
1191 of the Civil Code, which reads: we therefore relieve respondent from the burden of having
to keep the boxes within its premises and, consequently, give
Art. 1191. The power to rescind it the right to dispose of them, after petitioner is given a
obligations is implied in reciprocal ones, period of time within which to remove them from the
in case one of the obligors should not premises.
comply with what is incumbent upon him.
NOTE: Yung case involves breach of contract, contract
The injured party may choose between
talagasiyabeshybakai-judge niyoakonamaliyung digest ko.
the fulfillment and the rescission of the
Walakasing topic nanakalagay kung saang topic siyamagfa-fall
obligation, with the payment of damages
so i-assume nasa Art. 1170 itong case naito – Fraud and
in either case. He may also seek
damages.
rescission, even after he has chosen
fulfillment, if the latter should become
[G.R. No. 150843. March 14, 2003]
impossible.
The court shall decree the rescission CATHAY PACIFIC AIRWAYS, LTD., petitioner, vs. SPOUSES
claimed, unless there be just cause DANIEL VAZQUEZ and MARIA LUISA MADRIGAL
authorizing the fixing of a period. VAZQUEZ, respondents.

This is understood to be without


DECISION
prejudice to the rights of third persons
who have acquired the thing, in DAVIDE, JR., C.J.:
accordance with Articles 1385 and 1388
and the Mortgage Law. FACTS:The facts in this case, as found by the Court of
The right to rescind a contract arises once the Appeals and adopted by petitioner Cathay Pacific Airways,
other party defaults in the performance of his obligation. Ltd., (hereinafter Cathay) are as follows:
In determining when default occurs, Art. 1191 should be Cathay is a common carrier engaged in the business of
taken in conjunction with Art. 1169 of the same law, transporting passengers and goods by air. Among the many
which provides: routes it services is the Manila-Hongkong-Manila course. As
Art. 1169. Those obliged to deliver or to part of its marketing strategy, Cathay accords its frequent
do something incur in delay from the time flyers membership in its Marco Polo Club. The members enjoy
the obligee judicially or extrajudicially several privileges, such as priority for upgrading of booking
11
without any extra charge whenever an opportunity to each of them the amounts of P250,000 as temperate
arises. Thus, a frequent flyer booked in the Business Class has damages; P500,000 as moral damages; P500,000 as
priority for upgrading to First Class if the Business Class exemplary or corrective damages; and P250,000 as attorneys
Section is fully booked. fees.
Respondents-spouses Dr. Daniel Earnshaw Vazquez and In their complaint, the Vazquezes alleged that when
Maria Luisa Madrigal Vazquez are frequent flyers of Cathay they informed Ms. Chiu that they preferred to stay in
and are Gold Card members of its Marco Polo Club. On 24 Business Class, Ms. Chiu obstinately, uncompromisingly and
September 1996, the Vazquezes, together with their maid in a loud, discourteous and harsh voice threatened that they
and two friends Pacita Cruz and Josefina Vergel de Dios, went could not board and leave with the flight unless they go to
to Hongkong for pleasure and business. First Class, since the Business Class was overbooked. Ms.
Chius loud and stringent shouting annoyed, embarrassed, and
For their return flight to Manila on 28 September 1996,
humiliated them because the incident was witnessed by all
they were booked on Cathays Flight CX-905, with departure
the other passengers waiting for boarding. They also claimed
time at 9:20 p.m. Two hours before their time of departure,
that they were unjustifiably delayed to board the plane, and
the Vazquezes and their companions checked in their luggage when they were finally permitted to get into the aircraft, the
at Cathays check-in counter at Kai Tak Airport and were given
forward storage compartment was already full. A flight
their respective boarding passes, to wit, Business Class
stewardess instructed Dr. Vazquez to put his roll-on luggage
boarding passes for the Vazquezes and their two friends, and
in the overhead storage compartment. Because he was not
Economy Class for their maid. They then proceeded to the assisted by any of the crew in putting up his luggage, his
Business Class passenger lounge.
bilateral carpal tunnel syndrome was aggravated, causing him
When boarding time was announced, the Vazquezes and extreme pain on his arm and wrist. The Vazquezes also
their two friends went to Departure Gate No. 28, which was averred that they belong to the uppermost and absolutely
designated for Business Class passengers. Dr. Vazquez top elite of both Philippine Society and the Philippine
presented his boarding pass to the ground stewardess, who in financial community, [and that] they were among the
turn inserted it into an electronic machine reader or wealthiest persons in the Philippine[s].
computer at the gate. The ground stewardess was assisted by In its answer, Cathay alleged that it is a practice among
a ground attendant by the name of Clara Lai Han Chiu. When
commercial airlines to upgrade passengers to the next better
Ms. Chiu glanced at the computer monitor, she saw a
class of accommodation, whenever an opportunity arises,
message that there was a seat change from Business Class to
such as when a certain section is fully booked. Priority in
First Class for the Vazquezes. upgrading is given to its frequent flyers, who are considered
Ms. Chiu approached Dr. Vazquez and told him that the favored passengers like the Vazquezes. Thus, when the
Vazquezes accommodations were upgraded to First Class. Dr. Business Class Section of Flight CX-905 was fully booked,
Vazquez refused the upgrade, reasoning that it would not Cathays computer sorted out the names of favored
look nice for them as hosts to travel in First Class and their passengers for involuntary upgrading to First Class. When Ms.
guests, in the Business Class; and moreover, they were going Chiu informed the Vazquezes that they were upgraded to
to discuss business matters during the flight. He also told Ms. First Class, Dr. Vazquez refused. He then stood at the
Chiu that she could have other passengers instead entrance of the boarding apron, blocking the queue of
transferred to the First Class Section. Taken aback by the passengers from boarding the plane, which inconvenienced
refusal for upgrading, Ms. Chiu consulted her supervisor, who other passengers. He shouted that it was impossible for him
told her to handle the situation and convince the Vazquezes and his wife to be upgraded without his two friends who
to accept the upgrading. Ms. Chiu informed the latter that the were traveling with them. Because of Dr. Vazquezs outburst,
Business Class was fully booked, and that since they were Ms. Chiu thought of upgrading the traveling companions of
Marco Polo Club members they had the priority to be the Vazquezes. But when she checked the computer, she
upgraded to the First Class. Dr. Vazquez continued to refuse, learned that the Vazquezes companions did not have priority
so Ms. Chiu told them that if they would not avail themselves for upgrading. She then tried to book the Vazquezes again to
of the privilege, they would not be allowed to take the their original seats. However, since the Business Class Section
flight. Eventually, after talking to his two friends, Dr. Vazquez was already fully booked, she politely informed Dr. Vazquez
gave in. He and Mrs. Vazquez then proceeded to the First of such fact and explained that the upgrading was in
Class Cabin. recognition of their status as Cathays valued passengers.
Finally, after talking to their guests, the Vazquezes eventually
Upon their return to Manila, the Vazquezes, in a letter decided to take the First Class accommodation.
of 2 October 1996 addressed to Cathays Country Manager,
demanded that they be indemnified in the amount Cathay also asserted that its employees at the Hong
of P1million for the humiliation and embarrassment caused Kong airport acted in good faith in dealing with the
by its employees. They also demanded a written apology Vazquezes; none of them shouted, humiliated, embarrassed,
from the management of Cathay, preferably a responsible or committed any act of disrespect against them (the
person with a rank of no less than the Country Manager, as Vazquezes). Assuming that there was indeed a breach of
well as the apology from Ms. Chiu within fifteen days from contractual obligation, Cathay acted in good faith, which
receipt of the letter. negates any basis for their claim for temperate, moral, and
exemplary damages and attorneys fees. Hence, it prayed for
In his reply of 14 October 1996, Mr. Larry Yuen, the the dismissal of the complaint and for payment of P100,000
assistant to Cathays Country Manager Argus Guy Robson, for exemplary damages and P300,000 as attorneys fees and
informed the Vazquezes that Cathay would investigate the litigation expenses.
incident and get back to them within a weeks time.
During the trial, Dr. Vazquez testified to support the
On 8 November 1996, after Cathays failure to give them allegations in the complaint. His testimony was corroborated
any feedback within its self-imposed deadline, the Vazquezes by his two friends who were with him at the time of the
instituted before the Regional Trial Court of Makati City an incident, namely, Pacita G. Cruz and Josefina Vergel de Dios.
action for damages against Cathay, praying for the payment
12
For its part, Cathay presented documentary evidence mudslinging unless convincingly substantiated by whoever is
and the testimonies of Mr. Yuen; Ms. Chiu; Norma Barrientos, alleging them.
Comptroller of its retained counsel; and Mr. Robson. Yuen
and Robson testified on Cathays policy of upgrading the seat Fraud has been defined to include an inducement
through insidious machination. Insidious machination refers
accommodation of its Marco Polo Club members when an
to a deceitful scheme or plot with an evil or devious
opportunity arises. The upgrading of the Vazquezes to First
purpose. Deceit exists where the party, with intent to
Class was done in good faith; in fact, the First Class Section is
definitely much better than the Business Class in terms of deceive, conceals or omits to state material facts and, by
reason of such omission or concealment, the other party was
comfort, quality of food, and service from the cabin
induced to give consent that would not otherwise have been
crew. They also testified that overbooking is a widely
accepted practice in the airline industry and is in accordance given.[7]
with the International Air Transport Association (IATA) Bad faith does not simply connote bad judgment or
regulations. Airlines overbook because a lot of passengers do negligence; it imports a dishonest purpose or some moral
not show up for their flight. With respect to Flight CX-905, obliquity and conscious doing of a wrong, a breach of a
there was no overall overbooking to a degree that a known duty through some motive or interest or ill will that
passenger was bumped off or downgraded. Yuen and Robson partakes of the nature of fraud.[8]
also stated that the demand letter of the Vazquezes was
immediately acted upon. Reports were gathered from their We find no persuasive proof of fraud or bad faith in this
office in Hong Kong and immediately forwarded to their case. The Vazquezes were not induced to agree to the
counsel Atty. Remollo for legal advice. However, Atty. upgrading through insidious words or deceitful machination
Remollo begged off because his services were likewise or through willful concealment of material facts. Upon
retained by the Vazquezes; nonetheless, he undertook to boarding, Ms. Chiu told the Vazquezes that their
solve the problem in behalf of Cathay. But nothing happened accommodations were upgraded to First Class in view of their
until Cathay received a copy of the complaint in this case.For being Gold Card members of Cathays Marco Polo Club. She
her part, Ms. Chiu denied that she shouted or used foul or was honest in telling them that their seats were already given
impolite language against the Vazquezes. Ms. Barrientos to other passengers and the Business Class Section was fully
testified on the amount of attorneys fees and other litigation booked. Ms. Chiu might have failed to consider the remedy of
expenses, such as those for the taking of the depositions of offering the First Class seats to other passengers. But, we find
Yuen and Chiu. no bad faith in her failure to do so, even if that amounted to
an exercise of poor judgment.
Cathay seasonably filed with us this petition in this
case. Cathay maintains that the award for moral damages has Neither was the transfer of the Vazquezeseffected for
no basis, since the Court of Appeals found that there was no some evil or devious purpose. As testified to by Mr. Robson,
wanton, fraudulent, reckless and oppressive display of the First Class Section is better than the Business Class
manners on the part of its personnel; and that the breach of Section in terms of comfort, quality of food, and service from
contract was not attended by fraud, malice, or bad faith. If the cabin crew; thus, the difference in fare between the First
any damage had been suffered by the Vazquezes, it Class and Business Class at that time was $250.[9] Needless to
was damnumabsqueinjuria, which is damage without injury, state, an upgrading is for the better condition and, definitely,
damage or injury inflicted without injustice, loss or damage for the benefit of the passenger.
without violation of a legal right, or a wrong done to a man We are not persuaded by the Vazquezes argument that
for which the law provides no remedy. Cathay also invokes the overbooking of the Business Class Section constituted bad
our decision in United Airlines, Inc. v. Court of faith on the part of Cathay. Section 3 of the Economic
Appeals[3] where we recognized that, in accordance with the Regulation No. 7 of the Civil Aeronautics Board, as amended,
Civil Aeronautics Boards Economic Regulation No. 7, as provides:
amended, an overbooking that does not exceed ten percent
cannot be considered deliberate and done in bad faith. We
Sec 3. Scope. This regulation shall apply to every Philippine
thus deleted in that case the awards for moral and exemplary
and foreign air carrier with respect to its operation of flights
damages, as well as attorneys fees, for lack of proof of
or portions of flights originating from or terminating at, or
overbooking exceeding ten percent or of bad faith on the part
serving a point within the territory of the Republic of the
of the airline carrier.
Philippines insofar as it denies boarding to a passenger on a
ISSUE: The key issues for our consideration are whether flight, or portion of a flight inside or outside the Philippines,
(1) by upgrading the seat accommodation of the Vazquezes for which he holds confirmed reserved space. Furthermore,
from Business Class to First Class Cathay breached its contract this Regulation is designed to cover only honest mistakes on
of carriage with the Vazquezes; (2) the upgrading was tainted the part of the carriers and excludes deliberate and willful
with fraud or bad faith [Ito langyungoblicon issue dito which acts of non-accommodation. Provided, however, that
should answer 1170,pero after overbooking not exceeding 10% of the seating capacity of the
neto,samakoyungsagotsadalawabakakasiitanong kayo aircraft shall not be considered as a deliberate and willful act
nabahala if babasahinniyo]; and (3) the Vazquezes are of non-accommodation.
entitled to damages.
It is clear from this section that an overbooking that does not
HELD:
exceed ten percent is not considered deliberate and
(2)No.We are not, however, convinced that the upgrading or therefore does not amount to bad faith.[10] Here, while there
the breach of contract was attended by fraud or bad faith. was admittedly an overbooking of the Business Class, there
Thus, we resolve the second issue in the negative. was no evidence of overbooking of the plane beyond ten
percent, and no passenger was ever bumped off or was
Bad faith and fraud are allegations of fact that demand refused to board the aircraft.
clear and convincing proof. They are serious accusations that
can be so conveniently and casually invoked, and that is why
they are never presumed. They amount to mere slogans or

13
(1)Yes. The upgrading Cathay breached its contract of The Court of Appeals awarded each of the Vazquezes
carriage with Vazquezes, who declined said upgrade, since moral damages in the amount of P250,000. Article 2220 of
Cathay insisted to the upgrade. the Civil Code provides:
A contract is a meeting of minds between two persons
Article 2220. Willful injury to property may be a legal ground
whereby one agrees to give something or render some
for awarding moral damages if the court should find that,
service to another for a consideration. There is no contract
under the circumstances, such damages are justly due. The
unless the following requisites concur: (1) consent of the
same rule applies to breaches of contract where the
contracting parties; (2) an object certain which is the subject
defendant acted fraudulently or in bad faith.
of the contract; and (3) the cause of the obligation which is
established.[4] Undoubtedly, a contract of carriage existed
between Cathay and the Vazquezes. They voluntarily and Moral damages include physical suffering, mental
freely gave their consent to an agreement whose object was anguish, fright, serious anxiety, besmirched reputation,
the transportation of the Vazquezes from Manila to Hong wounded feelings, moral shock, social humiliation, and similar
Kong and back to Manila, with seats in the Business Class injury. Although incapable of pecuniary computation, moral
Section of the aircraft, and whose cause or consideration was damages may be recovered if they are the proximate result
the fare paid by the Vazquezes to Cathay. of the defendants wrongful act or omission.[11] Thus, case
law establishes the following requisites for the award of
The only problem is the legal effect of the upgrading of moral damages: (1) there must be an injury clearly sustained
the seat accommodation of the Vazquezes. Did it constitute a by the claimant, whether physical, mental or psychological;
breach of contract? (2) there must be a culpable act or omission factually
established; (3) the wrongful act or omission of the defendant
Breach of contract is defined as the failure without legal
is the proximate cause of the injury sustained by the
reason to comply with the terms of a contract.[5] It is also
claimant; and (4) the award for damages is predicated on any
defined as the [f]ailure, without legal excuse, to perform any
of the cases stated in Article 2219 of the Civil Code.[12]
promise which forms the whole or part of the contract. [6]
Moral damages predicated upon a breach of contract
In previous cases, the breach of contract of carriage
of carriage may only be recoverable in instances where the
consisted in either the bumping off of a passenger with
carrier is guilty of fraud or bad faith or where the mishap
confirmed reservation or the downgrading of a passengers
resulted in the death of a passenger.[13] Where in breaching
seat accommodation from one class to a lower class. In this
the contract of carriage the airline is not shown to have acted
case, what happened was the reverse. The contract between
fraudulently or in bad faith, liability for damages is limited to
the parties was for Cathay to transport the Vazquezes to
the natural and probable consequences of the breach of the
Manila on a Business Class accommodation in Flight CX-
obligation which the parties had foreseen or could have
905. After checking-in their luggage at the Kai Tak Airport in
reasonably foreseen. In such a case the liability does not
Hong Kong, the Vazquezes were given boarding cards
include moral and exemplary damages.[14]
indicating their seat assignments in the Business Class
Section. However, during the boarding time, when the In this case, we have ruled that the breach of contract
Vazquezes presented their boarding passes, they were of carriage, which consisted in the involuntary upgrading of
informed that they had a seat change from Business Class to the Vazquezes seat accommodation, was not attended by
First Class. It turned out that the Business Class was fraud or bad faith. The Court of Appeals award of moral
overbooked in that there were more passengers than the damages has, therefore, no leg to stand on.
number of seats. Thus, the seat assignments of the Vazquezes
were given to waitlisted passengers, and the Vazquezes, The deletion of the award for exemplary damages by
being members of the Marco Polo Club, were upgraded from the Court of Appeals is correct. It is a requisite in the grant of
Business Class to First Class. exemplary damages that the act of the offender must be
accompanied by bad faith or done in wanton, fraudulent or
We note that in all their pleadings, the Vazquezes never malevolent manner.[15] Such requisite is absent in this case.
denied that they were members of Cathays Marco Polo Club. Moreover, to be entitled thereto the claimant must first
They knew that as members of the Club, they had priority for establish his right to moral, temperate, or compensatory
upgrading of their seat accommodation at no extra cost when damages.[16] Since the Vazquezes are not entitled to any of
an opportunity arises. But, just like other privileges, such these damages, the award for exemplary damages has no
priority could be waived. The Vazquezes should have been legal basis. And where the awards for moral and exemplary
consulted first whether they wanted to avail themselves of damages are eliminated, so must the award for attorneys
the privilege or would consent to a change of seat fees.[17]
accommodation before their seat assignments were given to
other passengers. Normally, one would appreciate and The most that can be adjudged in favor of the Vazquezes
accept an upgrading, for it would mean a better for Cathays breach of contract is an award for nominal
accommodation. But, whatever their reason was and damages under Article 2221 of the Civil Code, which reads as
however odd it might be, the Vazquezes had every right to follows:
decline the upgrade and insist on the Business Class
accommodation they had booked for and which was Article 2221 of the Civil Code provides:
designated in their boarding passes. They clearly waived
their priority or preference when they asked that other Article 2221. Nominal damages are adjudicated in order that
passengers be given the upgrade. It should not have been a right of the plaintiff, which has been violated or invaded by
imposed on them over their vehement objection. By the defendant, may be vindicated or recognized, and not for
insisting on the upgrade, Cathay breached its contract of the purpose of indemnifying the plaintiff for any loss suffered
carriage with the Vazquezes. by him.

Nonetheless, considering that the breach was intended to


(3)Now we come to the third issue on damages. give more benefit and advantage to the Vazquezes by

14
upgrading their Business Class accommodation to First Class commercial establishments beneath the NPC transmission
because of their valued status as Marco Polo members, we lines along Baesa, Quezon City. After deliberating on NPC's
reduce the award for nominal damages to P5,000. letter, Meralco decided to comply with NPC's requestand
thereupon issued notices of disconnection to all
Before writing finis to this decision, we find it well-worth
establishments affected including plaintiffs Leoncio Ramoy,
to quote the apt observation of the Court of Appeals
Matilde Ramoy/Matild, Rosemarie Ramoy, Ofelia Durian, Jose
regarding the awards adjudged by the trial court:
Valiza, and Cyrene S. Panado.

We are not amused but alarmed at the lower courts Plaintiff Leoncio Ramoy testified that he and his wife are the
unbelievable alacrity, bordering on the scandalous, to award registered owners of a parcel of land covered by TCT No.
excessive amounts as damages. In their complaint, appellees 326346, a portion of which was occupied by plaintiffs
asked for P1 million as moral damages but the lower court Rosemarie Ramoy, Ofelia Durian, Jose Valiza and Cyrene S.
awarded P4 million; they asked for P500,000.00 as exemplary Panado as lessees. When the Meralco employees were
damages but the lower court cavalierly awarded a disconnecting plaintiffs' power connection, plaintiffLeoncio
whooping P10 million; they asked for P250,000.00 as Ramoy objected by informing the Meralco foreman that his
attorneys fees but were awarded P2 million; they did not ask property was outside the NPC property and pointing out the
for nominal damages but were awarded P200,000.00. It is as monuments showing the boundaries of his property.
if the lower court went on a rampage, and why it acted that However, he was threatened and told not to interfere by the
way is beyond all tests of reason. In fact the excessiveness of armed men who accompanied the Meralco employees. After
the total award invites the suspicion that it was the result of the electric power in Ramoy's apartment was cut off, the
prejudice or corruption on the part of the trial court. plaintiffs-lessees left the premises.

The presiding judge of the lower court is enjoined to hearken During the ocular inspection ordered by the Court and
to the Supreme Courts admonition in Singson vs. CA (282 attended by the parties, it was found out that the residence
SCRA 149 [1997]), where it said: of plaintiffs-spouses Leoncio and Matilde Ramoy was indeed
outside the NPC property.The record also shows that at the
The well-entrenched principle is that the grant of moral request of NPC, defendant Meralco re-connected the electric
damages depends upon the discretion of the court based on service of four customers previously disconnected none of
the circumstances of each case. This discretion is limited by whom was any of the plaintiffs.
the principle that the amount awarded should not be
palpably and scandalously excessive as to indicate that it was The RTC decided in favor of MERALCO by dismissing herein
the result of prejudice or corruption on the part of the trial respondents' claim for moral damages, exemplary damages
court. and attorney's fees. However, the RTC ordered MERALCO to
restore the electric power supply of
and in Alitalia Airways vs. CA (187 SCRA 763 [1990], where it respondents.Respondents then appealed to the CA on
was held: grounds that it erred in finding MERALCO not negligent when
it disconnected power supply and in not awarding damages
Nonetheless, we agree with the injunction expressed by the to defendants.
Court of Appeals that passengers must not prey on
international airlines for damage awards, like trophies in a ISSUE: WON MERALCO is liable for damages
safari. After all neither the social standing nor prestige of the
passenger should determine the extent to which he would Ruling:
suffer because of a wrong done, since the dignity affronted in
the individual is a quality inherent in him and not conferred YES. Clearly, respondents' cause of action against MERALCO is
by these social indicators. [19] anchored on culpa contractual or breach of contract for the
latter's discontinuance of its service to respondents under
Article 1170 of the Civil Code which provides:
MERALCO V Ramoy
Article 1170. Those who in the performance of their
MANILA ELECTRIC COMPANY, Petitioner, vs.
obligations are guilty of fraud, negligence, or delay, and those
MATILDEMACABAGDAL RAMOY, BIENVENIDO RAMOY,
who in any manner contravene the tenor thereof, are liable
ROMANA RAMOY-RAMOS, ROSEMARIE RAMOY, OFELIA
for damages.
DURIAN and CYRENE PANADO, Respondents.

Facts:
In culpa contractual x x x the mere proof of the existence of
the contract and the failure of its compliance justify, prima
The evidence on record has established that in the year 1987
facie, a corresponding right of relief. The law, recognizing the
the National Power Corporation (NPC) filed with the MTC
obligatory force of contracts, will not permit a party to be set
Quezon City a case for ejectment against several persons
free from liability for any kind of misperformance of the
allegedly illegally occupying its properties in Baesa, Quezon
contractual undertaking or a contravention of the tenor
City. Among the defendants in the ejectment case was
thereof. A breach upon the contract confers upon the injured
Leoncio Ramoy, one of the plaintiffs in the case at bar.
party a valid cause for recovering that which may have been
lost or suffered. The remedy serves to preserve the interests
The MTC Branch 36, Quezon City rendered judgment for the
of the promissee that may include his "expectation interest,"
plaintiff [MERALCO] and "ordering the defendants to
which is his interest in having the benefit of his bargain by
demolish or remove the building and structures they built on
being put in asgood a position as he would have been in had
the land of the plaintiff and to vacate the premises."
the contract been performed, or his "reliance interest," which
is his interest in being reimbursed for loss caused by reliance
NPC wrote Meralco requesting for the "immediate
on the contract by being put in as good a position as he would
disconnection of electric power supply to all residential and
15
have been in had the contract not been made; or his If payment is made to our office, demand
"restitution interest," which is his interest in having restored for an OFFICIAL RECEIPT.
to him any benefit that he has conferred on the other party.
Indeed, agreements can accomplish little, either for their On December 17, 1984, respondent insurance company
makers or for society, unless they are made the basis for issued collector's provisional receipt No. 9300 to petitioner-
action. The effect of every infraction is to create a new duty, insured for the amount of P1,609.65 3 On the lower portion of
that is, to make recompense to the one who has been injured the receipt the following is written in capital letters:
by the failure of another to observe his contractual obligation
unless he can show extenuating circumstances, like proof of Note: This collector's provisional receipt will
his exercise of due diligence x x x or of the attendance of be confirmed by our official receipt. If our
fortuitous event, to excuse him from his ensuing liability. official receipt is not received by you within
7 days, please notify us. 4
Article 1173 also provides that the fault or negligence of the
obligor consists in the omission of that diligence which is
On June 29, 1985, respondent insurance company, through
required by the nature of the obligation and corresponds with
manager, Teofilo M. Malapit, sent petitioner-insured
the circumstances of the persons, of the time and of the
Endorsement No. BG-002/85 which "cancelled flat" Policy No.
place.
PA BG-20015 "for non-payment of premium effective as of
inception dated." 5 The same endorsement also credited "a
To repeat, it was not enough for MERALCO to merely rely on
return premium of P1,609.65 plus documentary stamps and
the Decision of the MTC without ascertaining whether it had
premium tax" to the account of the insured. Shocked by the
become final and executory. Moreover, if it were true that
cancellation of the policy, petitioner-insured confronted
the decision was final and executory, the most prudent thing
Carlito Ang, agent of respondent insurance company, and
for MERALCO to have done was to coordinate with the proper
demanded the issuance of an official receipt. Ang told
court officials in determining which structures are covered by
petitioner-insured that the cancellation of the policy was a
said court order. Likewise, there is no evidence on record to
mistake but he would personally see to its rectification.
show that this was done by MERALCO.
However, petitioner-insured failed to receive any official
receipt from Prudential.
The utmost care and diligence required of MERALCO
necessitates such great degree of prudence on its part, and
petitioner-insured sent respondent insurance company a
failure to exercise the diligence required means that
letter demanding that he be insured under the same terms
MERALCO was at fault and negligent in the performance of its
and conditions as those contained in Policy No. PA-BG-20015
obligation.
commencing upon its receipt of his letter, or that the current
commercial rate of increase on the payment he had made
This being so, MERALCO is liable for damages under Article
under provisional receipt No. 9300 be returned within five
1170 of the Civil Code.
days. 6 Areola also warned that should his demands be
unsatisfied, he would sue for damages.
G.R. No. 95641 September 22, 1994
On July 17, 1985, he received a letter from production
manager Malapit informing him that the "partial payment" of
SANTOS B. AREOLA and LYDIA D. AREOLA, petitioners-
P1,000.00 he had made on the policy had been "exhausted
appellants,
pursuant to the provisions of the Short Period Rate Scale".
vs.
Malapit warned Areola that should be fail to pay the balance,
COURT OF APPEALS and PRUDENTIAL GUARANTEE AND
the company's liability would cease to operate. 7
ASSURANCE, INC., respondents-appellees.
Assistant Vice President emphasized that the official receipt
FACTS:
should have been issued seven days from the issuance of the
provisional receipt but because no official receipt had been
Petitioner-insured, Santos Areola, a lawyer from Dagupan issued in Areola's name, there was reason to believe that no
City, bought from Prudential Guarantee and Assurance, Inc. payment had been made. Apologizing for the inconvenience,
(hereinafter referred to as Prudential), a personal accident Ampil expressed the company's concern by agreeing "to hold
insurance policy covering the one-year period between noon you cover (sic) under the terms of the referenced policy until
of November 28, 1984 and noon of November 28, such time that this matter is cleared." 8
1985. 1 Under the terms of the statement of account issued
by respondent insurance company, petitioner-insured was
On August 3, 1985, Ampil wrote Areola another letter
supposed to pay the total amount of P1,609.65. At the lower
confirming that the amount of P1,609.65 was in fact received
left-hand corner of the statement of account, the following is
by Prudential on December 17, 1984. Hence, Ampil informed
legibly printed:
Areola that Prudential was "amenable to extending the
insurance coverage up to December 17, 1985 or one year
This Statement of Account must not be from the date when payment was received." Apologizing
considered a receipt. Official Receipt will be again for the inconvenience caused Areola, Ampil exhorted
issued to you upon payment of this account. him to indicate his conformity to the proposal by signing on
the space provided for in the letter. 9
If payment is made to our representative,
demand for a Provisional Receipt and if our The letter was personally delivered by Carlito Ang to Areola
Official Receipts is (sic) not received by you on August 13, 1985 10 but unfortunately, Areola and his wife,
within 7 days please notify us. Lydia, as early as August 6, 1985 had filed a complaint for
breach of contract with damages before the lower court.

16
In its Answer, respondent insurance company admitted that latter. The construction will cost P60,000 which Herce agreed
the cancellation of petitioner-insured's policy was due to the upon. Pursuant to the agreement, Herce paid the down
failure of Malapit to turn over the premiums collected. payment of P30,000 and an installment payment of P15,000,
However, it argued that, by acknowledging the inconvenience leaving a balance of P15,000.
caused on petitioner-insured and after reinstating the Due to the refusal and failure of respondent to pay for
cancelled policy prior to the filing of the complaint, the balance, petitioner filed a complaint to collect the
respondent insurance company had complied with its amount.
obligation under the contract. Hence, it concluded that Respondent denied the claim saying that he had already
petitioner-insured no longer has a cause of action against it, paid the amount to the San Pedro General Merchandising Inc.
therefore cannot be held liable for damages arising from (SPGMI) which constructed the deep well to which the
breach of contract, having demonstrated fully well its windmill system was to be connected. According to him, since
fulfillment of its obligation. the deep well is part of the system, the payment should be
credited to his account by the petitioner. Moreover, the
ISSUE: WON Areola may sue Prudential for damages. balance should also be offset by the defects in the windmill
system which caused the structure to collapse after their
RULING: YES. place was hit by a strong wind.
Petitioner denied that the deep well was included in the
contract, that the P60,000 covered only the windmill
Malapit's fraudulent act of misappropriating the premiums
assembly. He also disowned any obligation to repair or
paid by petitioner-insured is beyond doubt directly imputable
reconstruct the system since it was delivered in good
to respondent insurance company. A corporation, such as
condition, and the collapse was due to a typhoon, a force
respondent insurance company, acts solely thru its
majeure, thus cannot be held liable.
employees. The latters' acts are considered as its own for
The trial court found that the deep well was not
which it can be held to account.
included in the contract. And that the petitioner has no
obligation to reconstruct the windmill since there was no
Consequently, respondent insurance company is liable by way
convincing proof that the same collapsed due to a defect.
of damages for the fraudulent acts committed by Malapit. Its
The CA, on the other hand, ruled that the contract
earlier act of reinstating the insurance policy can not
mentioned of the term deep well and thus part of the
obliterate the injury inflicted on petitioner-insured.
agreement. And it rejected the claim of force majeure,
Respondent company should be reminded that a contract of
commanding petitioner to reconstruct the windmill.
insurance creates reciprocal obligations for both insurer and
insured. Reciprocal obligations are those which arise from the
Issue: (pertinent to the topic)
same cause and in which each party is both a debtor and a
WON petitioner is obliged to rebuild or reconstruct the
creditor of the other, such that the obligation of one is
windmill system
dependent upon the obligation of the other.
Held:
Under the law governing reciprocal obligations, particularly Yes. Art 1174 of the Civil Code states that the event
the second paragraph of Article 1191, the injured party, should be the sole and proximate cause of the loss or
petitioner-insured in this case, is given a choice between destruction of the object of the contract. In Nakpil vs. CA,
fulfillment or rescission of the obligation in case one of the four(4) requisites must concur: (a) the cause of the breach of
obligors, such as respondent insurance company, fails to the obligation must be independent of the will of the debtor;
comply with what is incumbent upon him. However, said (b) the event must be either unforeseeable or unavoidable;
article entitles the injured party to payment of damages, (c) the event must be such as to render it impossible for the
regardless of whether he demands fulfillment or rescission debtor to fulfill his obligation in a normal manner; and (d) the
of the obligation. debtor must be free from any participation in or aggravation
of the injury to the creditor.
The nature of damages to be awarded, however, would be in Petitioner failed to show that the collapse of the
the form of nominal damages. Although the erroneous windmill was due solely to a fortuitous event. The evidence
cancellation of the insurance policy constituted a breach of does not even disclose that there was a typhoon on the day
contract, private respondent insurance company, within a the windmill collapsed. Petitioner merely stated the presence
reasonable time took steps to rectify the wrong committed by of a “strong wind.” But the strong wind cannot be considered
reinstating the insurance policy of petitioner. Moreover, no in this case as fortuitous nor unforeseeable nor unavoidable.
actual or substantial damage or injury was inflicted on On the contrary windmills are build in areas where there is a
petitioner Areola at the time the insurance policy was presence of strong winds, otherwise windmills will not work.
cancelled. Nominal damages are "recoverable where a legal Moreover, the windmill system is newly constructed, it is less
right is technically violated and must be vindicated against an likely to collapse unless it has an inherent defect.
invasion that has produced no actual present loss of any kind,
or where there has been a breach of contract and no
substantial injury or actual damages whatsoever have been or NAKPIL & SONS V. COURT OF APPEALS
can be shown.
FACTS

Plaintiff, Philippine Bar Association, a civic-non-profit


TANGUILIG v CA
association, incorporated under the Corporation Law, decided
G.R. No. 117190 to construct an office building on its 840 square meters lot
located at the comer of Aduana and Arzobispo Streets,
Facts:
Intramuros, Manila. The construction was undertaken by the
Petitioner Jacinto Tanguilig proposed to respondent
United Construction, Inc. on an "administration" basis, on the
Vicente Herce, Jr. To construct a windmill system for the
suggestion of Juan J. Carlos, the president and general
17
manager of said corporation. The proposal was approved by a breach of an obligation due to an "act of God," the
plaintiff's board of directors and signed by its president following must concur:
Roman Ozaeta, a third-party defendant in this case. The plans
and specifications for the building were prepared by the a) the cause of the breach of the obligation must be
other third-party defendants Juan F. Nakpil& Sons. The independent of the will of the debtor;
building was completed in June, 1966. In the early morning of b) the event must be either unforseeable or
August 2, 1968 an unusually strong earthquake [7.3 unavoidable;
magnitude] hit Manila and the building in question c) the event must be such as to render it impossible for
sustained major damage.[etoung main reason for the the debtor to fulfill his obligation in a normal
damages sustained, not the following earthquakes]The front manner; and
columns of the building buckled, causing the building to tilt d) the debtor must be free from any participation in, or
forward dangerously. The tenants vacated the building. As a aggravation of the injury to the creditor.
temporary remedial measure, the building was shored up by
United Construction, Inc. at the cost of P13,661.28.Plaintiff The principle embodied in the act of God doctrine strictly
[in his action for recovery of damages] alleges that the requires that the act must be one occasioned exclusively by
collapse of the building was accused by defects in the the violence of nature and all human agencies are to be
construction, the failure of the contractors to follow plans excluded from creating or entering into the cause of the
and specifications and violations by the defendants of the mischief. When the effect, the cause of which is to be
terms of the contract. Defendants in turn filed a third-party considered, is found to be in part the result of the
complaint against the architects who prepared the plans and participation of man, whether it be from active intervention
specifications, alleging in essence that the collapse of the or neglect, or failure to act, the whole occurrence is thereby
building was due to the defects in the said plans and humanized, as it were, and removed from the rules applicable
specifications. to the acts of God. To be exempt from liability for loss
because of an act of God, he must be free from any previous
Meanwhile, plaintiff moved twice for the demolition of the negligence or misconduct by which that loss or damage may
building on the ground that it may topple down in case of a have been occasioned.
strong earthquake. Finally, on April 30, 1979 the building was
authorized to be demolished, but 3 more earthquakes of The negligence of the defendant and the third-party
high intensity before the demolition date caused further defendants was established beyond dispute both in the lower
damage to the property. The actual demolition was court and in the Intermediate Appellate Court. Defendant
undertaken by the buyer of the damaged building. It was held United Construction Co., Inc. was found to have made
that aside from the 7.3 magnitude earthquake on Aug. 2, substantial deviations from the plans and specifications, and
1968, the damages were caused by the defects in the plans to have failed to observe the requisite workmanship in the
and specifications prepared by the third-party defendants' construction as well as to exercise the requisite degree of
architects, deviations from said plans and specifications by supervision; while the third-party defendants were found to
the defendant contractors and failure of the latter to observe have inadequacies or defects in the plans and specifications
the requisite workmanship in the construction of the building prepared by them. As correctly assessed by both courts, the
and of the contractors, architects and even the owners to defects in the construction and in the plans and
exercise the requisite degree of supervision in the specifications were the proximate causes that rendered the
construction of subject building. Lower court agreed with the PBA building unable to withstand the earthquake of August 2,
decision/findings of the Commissioner. Intermediate 1968. For this reason the defendant and third-party
Appellate Court modified. All parties appealed. Hence, these defendants cannot claim exemption from liability.
petitions.
-
ISSUE
There should be no question that the NAKPILS and UNITED
WON petitioners are liable for damages are liable for the damage resulting from the partial and
eventual collapse of the PBA building as a result of the
HELD earthquakes.

Yes. The Commissioner said that even if it can be proved that According to Justice Hugo E. Gutierrez, [gandangsinabinya as
the defects in the construction alone (and not in the plans a whole huhu, sayangkinailangankoicutkasi di
and design) caused the damage to the building, still the namanimportantelahat, magandalanghahaha]“x xxThe
deficiency in the original design and jack of specific provisions evidence reveals defects and deficiencies in design and
against torsion in the original plans and the overload on the construction. There is no mystery about these acts of
ground floor columns (found by an the experts including the negligence. The collapse of the PBA building was no wonder
original designer) certainly contributed to the damage which performed by God. It was a result of the imperfections in the
occurred. work of the architects and the people in the construction
company. The findings of the lower Court on the cause of the
The applicable law governing the rights and liabilities of the collapse are more rational and accurate. Instead of laying the
parties herein is Article 1723 of the New Civil Code. On the blame solely on the motions and forces generated by the
other hand, the general rule is that no person shall be earthquake, it also examined the ability of the PBA building,
responsible for events which could not be foreseen or which as designed and constructed, to withstand and successfully
though foreseen, were inevitable (Article 1174, New Civil weather those forces.
Code). There is no dispute that the earthquake of August 2,
1968 is a fortuitous event or an act of God. To exempt the As already discussed, the destruction was not purely an act of
obligor from liability under Article 1174 of the Civil Code, for God. Truth to tell hundreds of ancient buildings in the vicinity
were hardly affected by the earthquake. Only one thing spells

18
out the fatal difference; gross negligence and evident bad decision to either court in expectation of favorable judgment,
faith in the performance of their respective tasks, without but with intent of attacking its jurisdiction should the decision
which the damage would not have occurred. be unfavorable (Tyson Tan, et al. vs. Filipinas Compañia de
Seguros) et al., L-10096, Res. on Motion to Reconsider, March
Defendant and third-party defedants are hereby solidarily 23, 1966). Consequently, we are limited in this appeal to the
liable under Art. 1723. issues of law raised in the appellant's brief.

Taking the aforesaid rules into account, it can be seen that


the only reviewable issues in this appeal are reduced to two:
G.R. No. L-21749 September 29, 1967
ISSUE: 1) Whether or not the collision of appellant's
REPUBLIC OF THE PHILIPPINES, plaintiff-appellee, barge with the supports or piers of the Nagtahan
vs. bridge was in law caused by fortuitous event
LUZON STEVEDORING CORPORATION, defendant-appellant. or force majeure, and

FACTS: The present case comes by direct appeal from a 2) Whether or not it was error for the Court to have
decision of the Court of First Instance of Manila (Case No. permitted the plaintiff-appellee to introduce
44572) adjudging the defendant-appellant, Luzon Stevedoring additional evidence of damages after said party had
Corporation, liable in damages to the plaintiff-appellee rested its case.
Republic of the Philippines.
HELD: As to the first question, considering that the Nagtahan
In the early afternoon of August 17, 1960, barge L-1892, bridge was an immovable and stationary object and
owned by the Luzon Stevedoring Corporation was being uncontrovertedly provided with adequate openings for the
towed down the Pasig river by tugboats "Bangus" and passage of water craft, including barges like of appellant's, it
"Barbero"1 also belonging to the same corporation, when the is undeniable that the unusual event that the barge,
barge rammed against one of the wooden piles of the exclusively controlled by appellant, rammed the bridge
Nagtahan bailey bridge, smashing the posts and causing the supports raises a presumption of negligence on the part of
bridge to list. The river, at the time, was swollen and the appellant or its employees manning the barge or the tugs
current swift, on account of the heavy downpour of Manila that towed it. For in the ordinary course of events, such a
and the surrounding provinces on August 15 and 16, 1960. thing does not happen if proper care is used. In Anglo
American Jurisprudence, the inference arises by what is
known as the "res ipsa loquitur" rule (Scott vs. London Docks
Sued by the Republic of the Philippines for actual and
Co., 2 H & C 596; San Juan Light & Transit Co. vs. Requena,
consequential damage caused by its employees, amounting
224 U.S. 89, 56 L. Ed., 680; Whitwell vs. Wolf, 127 Minn. 529,
to P200,000 (Civil Case No. 44562, CFI of Manila), defendant
149 N.W. 299; Bryne vs. Great Atlantic & Pacific Tea Co., 269
Luzon Stevedoring Corporation disclaimed liability therefor,
Mass. 130; 168 N.E. 540; Gribsby vs. Smith, 146 S.W. 2d 719).
on the grounds that it had exercised due diligence in the
selection and supervision of its employees; that the damages
to the bridge were caused by force majeure; that plaintiff has The appellant strongly stresses the precautions taken by it
no capacity to sue; and that the Nagtahan bailey bridge is an on the day in question: that it assigned two of its most
obstruction to navigation. powerful tugboats to tow down river its barge L-1892; that it
assigned to the task the more competent and experienced
among its patrons, had the towlines, engines and equipment
After due trial, the court rendered judgment on June 11,
double-checked and inspected; that it instructed
1963, holding the defendant liable for the damage caused by
its patrons to take extra precautions; and concludes that it
its employees and ordering it to pay to plaintiff the actual
had done all it was called to do, and that the accident,
cost of the repair of the Nagtahan bailey bridge which
therefore, should be held due to force majeure or fortuitous
amounted to P192,561.72, with legal interest thereon from
event.
the date of the filing of the complaint.

These very precautions, however, completely destroy the


Defendant appealed directly to this Court assigning the
appellant's defense. For caso fortuito or force majeure (which
following errors allegedly committed by the court a quo, to
in law are identical in so far as they exempt an obligor from
wit:
liability)2 by definition, are extraordinary events not
foreseeable or avoidable, "events that could not be foreseen,
..........................5 ISSUES.....................
or which, though foreseen, were inevitable" (Art. 1174, Civ.
Code of the Philippines). It is, therefore, not enough that the
However, it must be recalled that the established rule in this event should not have been foreseen or anticipated, as is
jurisdiction is that when a party appeals directly to the commonly believed, but it must be one impossible to foresee
Supreme Court, and submits his case there for decision, he is or to avoid. The mere difficulty to foresee the happening is
deemed to have waived the right to dispute any finding of not impossibility to foresee the same: "un hecho no
fact made by the trial Court. The only questions that may be constituye caso fortuito por la sola circunstancia de que su
raised are those of law (Savellano vs. Diaz, L-17441, July 31, existencia haga mas dificil o mas onerosa la accion diligente
1963; Aballe vs. Santiago, L-16307, April 30, 1963; G.S.I.S. vs. del presento ofensor" (Peirano Facio, Responsibilidad Extra-
Cloribel, L-22236, June 22, 1965). A converso, a party who contractual, p. 465; Mazeaud Trait de la Responsibilite Civil,
resorts to the Court of Appeals, and submits his case for Vol. 2, sec. 1569). The very measures adopted by appellant
decision there, is barred from contending later that his claim prove that the possibility of danger was not only foreseeable,
was beyond the jurisdiction of the aforesaid Court. The but actually foreseen, and was not caso fortuito.
reason is that a contrary rule would encourage the
undesirable practice of appellants' submitting their cases for

19
Otherwise stated, the appellant, Luzon Stevedoring lost card, along with the principal card, as a "Hot Card" or
Corporation, knowing and appreciating the perils posed by "Cancelled Card" in its master file.
the swollen stream and its swift current, voluntarily entered On 06 October 1988, Luis tendered
into a situation involving obvious danger; it therefore
a despedida lunch for a close friend, a Filipino-American,
assured the risk, and can not shed responsibility merely
and another guest at the Bahia Rooftop Restaurant of the
because the precautions it adopted turned out to be
Hotel Intercontinental Manila. To pay for the lunch, Luis
insufficient. Hence, the lower Court committed no error in presented his FAREASTCARD to the attending waiter who
holding it negligent in not suspending operations and in
promptly had it verified through a telephone call to the
holding it liable for the damages caused.
bank's Credit Card Department. Since the card was not
honored, Luis was forced to pay in cash the bill
It avails the appellant naught to argue that the dolphins, like amounting to P588.13. Naturally, Luis felt embarrassed
the bridge, were improperly located. Even if true, these by this incident.
circumstances would merely emphasize the need of even
higher degree of care on appellant's part in the situation In a letter, dated 11 October 1988, private
involved in the present case. The appellant, whose barges respondent Luis Luna, through counsel, demanded from
and tugs travel up and down the river everyday, could not FEBTC the payment of damages. Adrian V. Festejo, a vice-
safely ignore the danger posed by these allegedly improper president of the bank, expressed the bank's apologies to
constructions that had been erected, and in place, for years. Luis. In his letter, dated 03 November 1988, Festejo, in
part, said:
On the second point: appellant charges the lower court with xxxxxxxxx
having abused its discretion in the admission of plaintiff's
"An investigation of your case however,
additional evidence after the latter had rested its case. There
revealed that FAREASTCARD failed to
is an insinuation that the delay was deliberate to enable the
inform you about its security policy.
manipulation of evidence to prejudice defendant-appellant.
Furthermore, an overzealous employee of
the Bank's Credit Card Department did
We find no merit in the contention. Whether or not further not consider the possibility that it may
evidence will be allowed after a party offering the evidence have been you who was presenting the
has rested his case, lies within the sound discretion of the card at that time (for which reason, the
trial Judge, and this discretion will not be reviewed except in unfortunate incident occurred)." 1
clear case of abuse.3
On 30 March 1990, the RTC of Pasig, given the
In the present case, no abuse of that discretion is shown. foregoing factual settings, rendered a decision ordering
What was allowed to be introduced, after plaintiff had rested FEBTC to pay private respondents (a) P300,000.00 moral
its evidence in chief, were vouchers and papers to support an damages; (b) P50,000.00 exemplary damages; and (c)
item of P1,558.00 allegedly spent for the reinforcement of P20,000.00 attorney's fees.
the panel of the bailey bridge, and which item already On appeal to the Court of Appeals, the appellate
appeared in Exhibit GG. Appellant, in fact, has no reason to court affirmed the decision of the trial court.
charge the trial court of being unfair, because it was also able
to secure, upon written motion, a similar order dated ISSUE:WON private respondents are entitled of moral
November 24, 1962, allowing reception of additional damages.
evidence for the said defendant-appellant.4 HELD:NO.
Concededly, the bank was remiss in indeed
WHEREFORE, finding no error in the decision of the lower neglecting to personally inform Luis of his own card’s
Court appealed from, the same is hereby affirmed. Costs cancellation. Nothing in the findings of the trial court and
against the defendant-appellant. the appellate court, however, can sufficiently indicate
any deliberate intent on the part of FEBTC to cause harm
to private respondents. Neither could FEBTC's negligence
[G.R. No. 108164. February 23, 1995.] in failing to give personal notice to Luis be considered so
gross as to amount to malice or bad faith.
FAR EAST BANK AND TRUST "xxxxxxxxx.
COMPANY, petitioner, vs. THE
"The distinction between fraud, bad faith
HONORABLE COURT OF APPEALS, LUIS A.
or malice in the sense of deliberate or
LUNA and CLARITA S. LUNA, respondents.
wanton wrong doing and negligence (as
mere carelessness) is too fundamental in
FACTS: our law to be ignored (Arts. 1170-1172);
their consequences being clearly
Some time in October 1986, private respondent differentiated by the Code.
Luis A. Lunaapplied for, and was accorded, a
FAREASTCARD issued by petitioner Far East Bank and "'ART. 2201. In contracts and
Trust Company ("FEBTC") at its Pasig Branch. Upon his quasi-contracts, the damages for
request, the bank also issued a supplemental card to which the obligor who acted in
private respondent Clarita S. Luna. good faith is liable shall be those
that are the natural and
In August 1988, Clarita lost her credit card.
probable consequences of the
FEBTC was forthwith informed. In order to replace the
breach of the obligation, and
lost card, Clarita submitted an affidavit of loss. In cases of
which the parties have foreseen
this nature, the bank’s internal security procedures and
or could have reasonably
policy would appear to be to meanwhile so record the

20
foreseen at the time the continued even after plaintiff was discharged from
obligation was constituted. the hospital when not even a word of consolation
was heard from them. Plaintiff waited for more
'In case of fraud, bad faith, than one (1) year for the defendants to perform
malice or wanton attitude, the their moral obligation but the wait was fruitless.
obligor shall be responsible for This indifference and total lack of concern of
all damages which may be defendants served to exacerbate plaintiff's miserable
reasonably attributed to the condition.
non-performance of the
obligation."
xxxx
The Court finds, therefore, the award of moral
damages made by the court a quo, affirmed by the 11.0. Defendants are responsible for ensuring the
appellate court, to be inordinate and substantially devoid safety of its students while the latter are within the
of legal basis. University premises. And that should anything
WHEREFORE, the petition for review is given untoward happens to any of its students while they
due course. The appealed decision is MODIFIED by are within the University's premises shall be the
deleting the award of moral and exemplary damages to responsibility of the defendants. In this case,
private respondents; in its stead, petitioner is ordered to defendants, despite being legally and morally bound,
pay private respondent Luis A. Luna an amount of miserably failed to protect plaintiff from injury and
P5,000.00 by way of nominal damages. In all other thereafter, to mitigate and compensate plaintiff for
respects, the appealed decision is AFFIRMED. No costs. said injury;

G.R. No. 179337 April 30, 2008 12.0. When plaintiff enrolled with defendant FEU, a
contract was entered into between them. Under
this contract, defendants are supposed to ensure
JOSEPH SALUDAGA, petitioner,
that adequate steps are taken to provide an
vs.
atmosphere conducive to study and ensure the
FAR EASTERN UNIVERSITY and EDILBERTO C. DE JESUS in his
safety of the plaintiff while inside defendant FEU's
capacity as President of FEU, respondents.
premises. In the instant case, the latter breached
this contract when defendant allowed harm to befall
DECISION upon the plaintiff when he was shot at by, of all
people, their security guard who was tasked to
YNARES-SANTIAGO, J.: maintain peace inside the campus.12

FACTS:Petitioner Joseph Saludaga was a sophomore law In Philippine School of Business Administration v. Court of
student of respondent Far Eastern University (FEU) when he Appeals,13 we held that:
was shot by Alejandro Rosete (Rosete), one of the security
guards on duty at the school premises on August 18, 1996. When an academic institution accepts students for
Petitioner was rushed to FEU-Dr. Nicanor Reyes Medical enrollment, there is established a contract between
Foundation (FEU-NRMF) due to the wound he them, resulting in bilateral obligations which both
sustained.6Meanwhile, Rosete was brought to the police parties are bound to comply with. For its part, the
station where he explained that the shooting was accidental. school undertakes to provide the student with an
He was eventually released considering that no formal education that would presumably suffice to equip
complaint was filed against him. him with the necessary tools and skills to pursue
higher education or a profession. On the other hand,
Petitioner thereafter filed a complaint for damages against the student covenants to abide by the school's
respondents on the ground that they breached their academic requirements and observe its rules and
obligation to provide students with a safe and secure regulations.
environment and an atmosphere conducive to learning.
Respondents, in turn, filed a Third-Party Complaint7 against Institutions of learning must also meet the implicit or
Galaxy Development and Management Corporation (Galaxy), "built-in" obligation of providing their students with
the agency contracted by respondent FEU to provide security an atmosphere that promotes or assists in attaining
services within its premises and Mariano D. Imperial its primary undertaking of imparting knowledge.
(Imperial), Galaxy's President, to indemnify them for Certainly, no student can absorb the intricacies of
whatever would be adjudged in favor of petitioner, if any; physics or higher mathematics or explore the realm
and to pay attorney's fees and cost of the suit. On the other of the arts and other sciences when bullets are flying
hand, Galaxy and Imperial filed a Fourth-Party Complaint or grenades exploding in the air or where there
against AFP General Insurance.8 looms around the school premises a constant threat
to life and limb. Necessarily, the school must ensure
Petitioner is suing respondents for damages based on the that adequate steps are taken to maintain peace and
alleged breach of student-school contract for a safe learning order within the campus premises and to prevent
environment. The pertinent portions of petitioner's the breakdown thereof.14
Complaint read:
It is undisputed that petitioner was enrolled as a sophomore
6.0. At the time of plaintiff's confinement, the law student in respondent FEU. As such, there was created a
defendants or any of their representative did not contractual obligation between the two parties. On
bother to visit and inquire about his condition. This petitioner's part, he was obliged to comply with the rules and
abject indifference on the part of the defendants regulations of the school. On the other hand, respondent

21
FEU, as a learning institution is mandated to impart Article 1170 of the Civil Code provides that those who are
knowledge and equip its students with the necessary skills to negligent in the performance of their obligations are liable for
pursue higher education or a profession. At the same time, it damages. Accordingly, for breach of contract due to
is obliged to ensure and take adequate steps to maintain negligence in providing a safe learning environment,
peace and order within the campus. respondent FEU is liable to petitioner for damages. It is
essential in the award of damages that the claimant must
It is settled that in culpa contractual, the mere proof of the have satisfactorily proven during the trial the existence of the
existence of the contract and the failure of its compliance factual basis of the damages and its causal connection to
justify, prima facie, a corresponding right of relief. 15 In the defendant's acts.18
instant case, we find that, when petitioner was shot inside
the campus by no less the security guard who was hired to In the instant case, it was established that petitioner spent
maintain peace and secure the premises, there is a prima P35,298.25 for his hospitalization and other medical
facie showing that respondents failed to comply with its expenses.19 While the trial court correctly imposed interest
obligation to provide a safe and secure environment to its on said amount, however, the case at bar involves an
students. obligation arising from a contract and not a loan or
forbearance of money. As such, the proper rate of legal
In order to avoid liability, however, respondents aver that the interest is six percent (6%) per annum of the amount
shooting incident was a fortuitous event because they could demanded. Such interest shall continue to run from the filing
not have reasonably foreseen nor avoided the accident of the complaint until the finality of this Decision.20 After this
caused by Rosete as he was not their employee; 16and that Decision becomes final and executory, the applicable rate
they complied with their obligation to ensure a safe learning shall be twelve percent (12%) per annum until its satisfaction.
environment for their students by having exercised due
diligence in selecting the security services of Galaxy. The other expenses being claimed by petitioner, such as
transportation expenses and those incurred in hiring a
ISSUE: WON FEU is liable for damages for breach of its personal assistant while recuperating were however not duly
obligation to provide students with a safe and secure learning supported by receipts.21 In the absence thereof, no actual
atmosphere. damages may be awarded. Nonetheless, temperate damages
under Art. 2224 of the Civil Code may be recovered where it
HELD: YES. After a thorough review of the records, we find has been shown that the claimant suffered some pecuniary
that respondents failed to discharge the burden of proving loss but the amount thereof cannot be proved with certainty.
that they exercised due diligence in providing a safe learning Hence, the amount of P20,000.00 as temperate damages is
environment for their students. They failed to prove that they awarded to petitioner.
ensured that the guards assigned in the campus met the
requirements stipulated in the Security Service Agreement. As regards the award of moral damages, there is no hard and
Indeed, certain documents about Galaxy were presented fast rule in the determination of what would be a fair amount
during trial; however, no evidence as to the qualifications of of moral damages since each case must be governed by its
Rosete as a security guard for the university was offered. own peculiar circumstances.22 The testimony of petitioner
about his physical suffering, mental anguish, fright, serious
Respondents also failed to show that they undertook steps to anxiety, and moral shock resulting from the shooting
ascertain and confirm that the security guards assigned to incident23 justify the award of moral damages. However,
them actually possess the qualifications required in the moral damages are in the category of an award designed to
Security Service Agreement. It was not proven that they compensate the claimant for actual injury suffered and not to
examined the clearances, psychiatric test results, 201 files, impose a penalty on the wrongdoer. The award is not meant
and other vital documents enumerated in its contract with to enrich the complainant at the expense of the defendant,
Galaxy. Total reliance on the security agency about these but to enable the injured party to obtain means, diversion, or
matters or failure to check the papers stating the amusements that will serve to obviate the moral suffering he
qualifications of the guards is negligence on the part of has undergone. It is aimed at the restoration, within the limits
respondents. A learning institution should not be allowed to of the possible, of the spiritual status quo ante, and should be
completely relinquish or abdicate security matters in its proportionate to the suffering inflicted. Trial courts must then
premises to the security agency it hired. To do so would result guard against the award of exorbitant damages; they should
to contracting away its inherent obligation to ensure a safe exercise balanced restrained and measured objectivity to
learning environment for its students. avoid suspicion that it was due to passion, prejudice, or
corruption on the part of the trial court.24 We deem it just
and reasonable under the circumstances to award petitioner
Consequently, respondents' defense of force majeure must
moral damages in the amount of P100,000.00.
fail. In order for force majeure to be considered,
respondents must show that no negligence or misconduct
was committed that may have occasioned the loss. An act of Likewise, attorney's fees and litigation expenses in the
God cannot be invoked to protect a person who has failed to amount of P50,000.00 as part of damages is reasonable in
take steps to forestall the possible adverse consequences of view of Article 2208 of the Civil Code.25 However, the award
such a loss. One's negligence may have concurred with an act of exemplary damages is deleted considering the absence of
of God in producing damage and injury to another; proof that respondents acted in a wanton, fraudulent,
nonetheless, showing that the immediate or proximate cause reckless, oppressive, or malevolent manner.
of the damage or injury was a fortuitous event would not
exempt one from liability. When the effect is found to be None of the foregoing exceptions was established in the
partly the result of a person's participation - whether by instant case; hence, respondent De Jesus should not be held
active intervention, neglect or failure to act - the whole solidarily liable with respondent FEU.
occurrence is humanized and removed from the rules
applicable to acts of God.17

22
Incidentally, although the main cause of action in the instant does not, by itself, render the client responsible as
case is the breach of the school-student contract, petitioner, an employer of the security guards concerned and
in the alternative, also holds respondents vicariously liable liable for their wrongful acts or omissions.31
under Article 2180 of the Civil Code, which provides:
Respondents and Galaxy were able to litigate their respective
Art. 2180. The obligation imposed by Article 2176 is claims and defenses in the course of the trial of petitioner's
demandable not only for one's own acts or complaint. Evidence duly supports the findings of the trial
omissions, but also for those of persons for whom court that Galaxy is negligent not only in the selection of its
one is responsible. employees but also in their supervision. Indeed, no
administrative sanction was imposed against Rosete despite
xxxx the shooting incident; moreover, he was even allowed to go
on leave of absence which led eventually to his
Employers shall be liable for the damages caused by disappearance.34 Galaxy also failed to monitor petitioner's
their employees and household helpers acting within condition or extend the necessary assistance, other than the
the scope of their assigned tasks, even though the P5,000.00 initially given to petitioner. Galaxy and Imperial
former are not engaged in any business or industry. failed to make good their pledge to reimburse petitioner's
medical expenses.
xxxx
For these acts of negligence and for having supplied
respondent FEU with an unqualified security guard, which
The responsibility treated of in this article shall cease
resulted to the latter's breach of obligation to petitioner, it is
when the persons herein mentioned prove that they
proper to hold Galaxy liable to respondent FEU for such
observed all the diligence of a good father of a family
damages equivalent to the above-mentioned amounts
to prevent damage.
awarded to petitioner.
We agree with the findings of the Court of Appeals that
Unlike respondent De Jesus, we deem Imperial to be solidarily
respondents cannot be held liable for damages under Art.
liable with Galaxy for being grossly negligent in directing the
2180 of the Civil Code because respondents are not the
affairs of the security agency. It was Imperial who assured
employers of Rosete. The latter was employed by Galaxy. The
petitioner that his medical expenses will be shouldered by
instructions issued by respondents' Security Consultant to
Galaxy but said representations were not fulfilled because
Galaxy and its security guards are ordinarily no more than
they presumed that petitioner and his family were no longer
requests commonly envisaged in the contract for services
interested in filing a formal complaint against them. 35
entered into by a principal and a security agency. They cannot
be construed as the element of control as to treat
respondents as the employers of Rosete.28 WHEREFORE, the petition is GRANTED. The June 29, 2007
Decision of the Court of Appeals in CA-G.R. CV No. 87050
nullifying the Decision of the trial court and dismissing the
As held in Mercury Drug Corporation v. Libunao:29
complaint as well as the August 23, 2007 Resolution denying
the Motion for Reconsideration are REVERSED and SET
In Soliman, Jr. v. Tuazon,30 we held that where the
ASIDE. The Decision of the Regional Trial Court of Manila,
security agency recruits, hires and assigns the works
Branch 2, in Civil Case No. 98-89483 finding respondent FEU
of its watchmen or security guards to a client, the
liable for damages for breach of its obligation to provide
employer of such guards or watchmen is such
students with a safe and secure learning atmosphere,
agency, and not the client, since the latter has no is AFFIRMED with the following MODIFICATIONS:
hand in selecting the security guards. Thus, the duty
to observe the diligence of a good father of a family
a. respondent Far Eastern University (FEU) is ORDERED to pay
cannot be demanded from the said client:
petitioner actual damages in the amount of P35,298.25, plus
6% interest per annum from the filing of the complaint until
… [I]t is settled in our jurisdiction that
the finality of this Decision. After this decision becomes final
where the security agency, as here, recruits,
and executory, the applicable rate shall be twelve percent
hires and assigns the work of its watchmen (12%) per annum until its satisfaction;
or security guards, the agency is the
employer of such guards or watchmen.
b. respondent FEU is also ORDERED to pay petitioner
Liability for illegal or harmful acts
temperate damages in the amount of P20,000.00; moral
committed by the security guards attaches
damages in the amount of P100,000.00; and attorney's fees
to the employer agency, and not to the
and litigation expenses in the amount of P50,000.00;
clients or customers of such agency. As a
general rule, a client or customer of a
security agency has no hand in selecting c. the award of exemplary damages is DELETED.
who among the pool of security guards or
watchmen employed by the agency shall be The Complaint against respondent Edilberto C. De Jesus
assigned to it; the duty to observe the is DISMISSED. The counterclaims of respondents are
diligence of a good father of a family in the likewise DISMISSED.
selection of the guards cannot, in the
ordinary course of events, be demanded Galaxy Development and Management Corporation (Galaxy)
from the client whose premises or property and its president, Mariano D. Imperial are ORDERED to jointly
are protected by the security guards. and severally pay respondent FEU damages equivalent to the
above-mentioned amounts awarded to petitioner.
The fact that a client company may give instructions
or directions to the security guards assigned to it, SO ORDERED.
23
G.R. No. 185798 January 13, 2014 demand for refund on October 08, 1998 until fully
paid,
FIL-ESTATE PROPERTIES, INC. AND FIL-ESTATE NETWORK
INC., Petitioners, b) ONE HUNDRED THOUSAND PESOS (P100,000.00)
vs. as moral damages,
SPOUSES CONRADO AND MARIA VICTORIA
RONQUILLO, Respondents. c) FIFTY THOUSAND PESOS (P50,000.00) as
attorney’s fees,
DECISION
d) The costs of suit, and
PEREZ, J.:
e) An administrative fine of TEN THOUSAND PESOS
Before the Court is a petition for review on certiorari under (P10,000.00) payable to this Office fifteen (15) days
Rule 45 of the 1997 Rules .of Civil Procedure assailing the upon receipt of this decision, for violation of Section
Decision1 of the Court of Appeals in CA-G.R. SP No. 100450 20 in relation to Section 38 of PD 957.3
which affirmed the Decision of the Office of the President in
O.P. Case No. 06-F-216. The Arbiter considered petitioners’ failure to develop the
condominium project as a substantial breach of their
As culled from the records, the facts are as follow: obligation which entitles respondents to seek for rescission
with payment of damages. The Arbiter also stated that mere
Petitioner Fil-Estate Properties, Inc. is the owner and economic hardship is not an excuse for contractual and legal
developer of the Central Park Place Tower while co-petitioner delay.
Fil-Estate Network, Inc. is its authorized marketing agent.
Respondent Spouses Conrado and Maria Victoria Ronquillo Petitioners appealed the Arbiter’s Decision through a petition
purchased from petitioners an 82-square meter condominium for review pursuant to Rule XII of the 1996 Rules of Procedure
unit at Central Park Place Tower in Mandaluyong City for a of HLURB. On 17 February 2005, the Board of Commissioners
pre-selling contract price of FIVE MILLION ONE HUNDRED of the HLURB denied4 the petition and affirmed the Arbiter’s
SEVENTY-FOUR THOUSAND ONLY (P5,174,000.00). On 29 Decision. The HLURB reiterated that the depreciation of the
August 1997, respondents executed and signed a Reservation peso as a result of the Asian financial crisis is not a fortuitous
Application Agreement wherein they deposited P200,000.00 event which will exempt petitioners from the performance of
as reservation fee. As agreed upon, respondents paid the full their contractual obligation.
downpayment of P1,552,200.00 and had been paying
the P63,363.33 monthly amortizations until September 1998. Petitioners filed a motion for reconsideration but it was
denied5 on 8 May 2006. Thereafter, petitioners filed a Notice
Upon learning that construction works had stopped, of Appeal with the Office of the President. On 18 April 2007,
respondents likewise stopped paying their monthly petitioners’ appeal was dismissed6 by the Office of the
amortization. Claiming to have paid a total of P2,198,949.96 President for lack of merit. Petitioners moved for a
to petitioners, respondents through two (2) successive reconsideration but their motion was denied 7 on 26 July
letters, demanded a full refund of their payment with 2007.
interest. When their demands went unheeded, respondents
were constrained to file a Complaint for Refund and Damages Petitioners sought relief from the Court of Appeals through a
before the Housing and Land Use Regulatory Board (HLURB). petition for review under Rule 43 containing the same
Respondents prayed for reimbursement/refund arguments they raised before the HLURB and the Office of
of P2,198,949.96 representing the total amortization the President:
payments, P200,000.00 as and by way of moral damages,
attorney’s fees and other litigation expenses. I.

On 21 October 2000, the HLURB issued an Order of Default THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN
against petitioners for failing to file their Answer within the AFFIRMING THE DECISION OF THE HONORABLE HOUSING
reglementary period despite service of summons.2 AND LAND USE REGULATORY BOARD AND ORDERING
PETITIONERS-APPELLANTS TO REFUND RESPONDENTS-
Petitioners filed a motion to lift order of default and attached APPELLEES THE SUM OF P2,198,949.96 WITH 12% INTEREST
their position paper attributing the delay in construction to FROM 8 OCTOBER 1998 UNTIL FULLY PAID, CONSIDERING
the 1997 Asian financial crisis. Petitioners denied committing THAT THE COMPLAINT STATES NO CAUSE OF ACTION
fraud or misrepresentation which could entitle respondents AGAINST PETITIONERS-APPELLANTS.
to an award of moral damages.
II.
On 13 June 2002, the HLURB, through Arbiter Atty. Joselito F.
Melchor, rendered judgment ordering petitioners to jointly THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN
and severally pay respondents the following amount: AFFIRMING THE DECISION OF THE OFFICE BELOW ORDERING
PETITIONERS-APPELLANTS TO PAY RESPONDENTS-APPELLEES
a) The amount of TWO MILLION ONE HUNDRED THE SUM OF P100,000.00 AS MORAL DAMAGES
NINETY-EIGHT THOUSAND NINE HUNDRED FORTY AND P50,000.00 AS ATTORNEY’S FEES CONSIDERING THE
NINE PESOS & 96/100 (P2,198,949.96) with interest ABSENCE OF ANY FACTUAL OR LEGAL BASIS THEREFOR.
thereon at twelve percent (12%) per annum to be
computed from the time of the complainants’ III.

24
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN only resorted to "suspension and reformatting as a testament
AFFIRMING THE DECISION OF THE HOUSING AND LAND USE to their commitment to their buyers." Petitioners attribute
REGULATORY BOARD ORDERING PETITIONERS-APPELLANTS the delay to the 1997 Asian financial crisis that befell the real
TO PAY P10,000.00 AS ADMINISTRATIVE FINE IN THE estate industry. Invoking Article 1174 of the New Civil Code,
ABSENCE OF ANY FACTUAL OR LEGAL BASIS TO SUPPORT petitioners maintain that they cannot be held liable for a
SUCH FINDING.8 fortuitous event.

On 30 July 2008, the Court of Appeals denied the petition for Petitioners contest the payment of a huge amount of interest
review for lack of merit. The appellate court echoed the on account of suspension of development on a project. They
HLURB Arbiter’s ruling that "a buyer for a liken their situation to a bank which this Court, in Overseas
condominium/subdivision unit/lot unit which has not been Bank v. Court of Appeals,12 adjudged as not liable to pay
developed in accordance with the approved interest on deposits during the period that its operations are
condominium/subdivision plan within the time limit for ordered suspended by the Monetary Board of the Central
complying with said developmental requirement may opt for Bank.
reimbursement under Section 20 in relation to Section 23 of
Presidential Decree (P.D.) 957 x x x."9 The appellate court Lastly, petitioners aver that they should not be ordered to
supported the HLURB Arbiter’s conclusion, which was pay moral damages because they never intended to cause
affirmed by the HLURB Board of Commission and the Office of delay, and again blamed the Asian economic crisis as the
the President, that petitioners’ failure to develop the direct, proximate and only cause of their failure to complete
condominium project is tantamount to a substantial breach the project. Petitioners submit that moral damages should
which warrants a refund of the total amount paid, including not be awarded unless so stipulated except under the
interest. The appellate court pointed out that petitioners instances enumerated in Article 2208 of the New Civil Code.
failed to prove that the Asian financial crisis constitutes a Lastly, petitioners refuse to pay the administrative fine
fortuitous event which could excuse them from the because the delay in the project was caused not by their own
performance of their contractual and statutory obligations. deceptive intent to defraud their buyers, but due to
The appellate court also affirmed the award of moral unforeseen circumstances beyond their control.
damages in light of petitioners’ unjustified refusal to satisfy
respondents’ claim and the legality of the administrative fine, Three issues are presented for our resolution: 1) whether or
as provided in Section 20 of Presidential Decree No. 957. not the Asian financial crisis constitute a fortuitous event
which would justify delay by petitioners in the performance
Petitioners sought reconsideration but it was denied in a of their contractual obligation; 2) assuming that petitioners
Resolution10 dated 11 December 2008 by the Court of are liable, whether or not 12% interest was correctly imposed
Appeals. on the judgment award, and 3) whether the award of moral
damages, attorney’s fees and administrative fine was proper.
Aggrieved, petitioners filed the instant petition advancing
substantially the same grounds for review: It is apparent that these issues were repeatedly raised by
petitioners in all the legal fora. The rulings were consistent
A. that first, the Asian financial crisis is not a fortuitous event
that would excuse petitioners from performing their
THE HONORABLE COURT OF APPEALS ERRED WHEN IT contractual obligation; second, as a result of the breach
AFFIRMED IN TOTO THE DECISION OF THE OFFICE OF THE committed by petitioners, respondents are entitled to rescind
PRESIDENT WHICH SUSTAINED RESCISSION AND REFUND IN the contract and to be refunded the amount of amortizations
FAVOR OF THE RESPONDENTS DESPITE LACK OF CAUSE OF paid including interest and damages; and third, petitioners
ACTION. are likewise obligated to pay attorney’s fees and the
administrative fine.
B.
This petition did not present any justification for us to deviate
GRANTING FOR THE SAKE OF ARGUMENT THAT THE from the rulings of the HLURB, the Office of the President and
PETITIONERS ARE LIABLE UNDER THE PREMISES, THE the Court of Appeals.
HONORABLE COURT OF APPEALS ERRED WHEN IT AFFIRMED
THE HUGE AMOUNT OF INTEREST OF TWELVE PERCENT Indeed, the non-performance of petitioners’ obligation
(12%). entitles respondents to rescission under Article 1191 of the
New Civil Code which states:
C.
Article 1191. The power to rescind obligations is implied in
THE HONORABLE COURT OF APPEALS LIKEWISE ERRED WHEN reciprocal ones, in case one of the obligors should not comply
IT AFFIRMED IN TOTO THE DECISION OF THE OFFICE OF THE with what is incumbent upon him.
PRESIDENT INCLUDING THE PAYMENT OF P100,000.00 AS
MORAL DAMAGES, P50,000.00 AS ATTORNEY’S FEES The injured party may choose between the fulfillment and
AND P10,000.00 AS ADMINISTRATIVE FINE IN THE ABSENCE the rescission of the obligation, with payment of damages in
OF ANY FACTUAL OR LEGAL BASIS TO SUPPORT SUCH either case. He may also seek rescission, even after he has
CONCLUSIONS.11 chosen fulfillment, if the latter should become impossible.

Petitioners insist that the complaint states no cause of action More in point is Section 23 of Presidential Decree No. 957,
because they allegedly have not committed any act of the rule governing the sale of condominiums, which provides:
misrepresentation amounting to bad faith which could entitle
respondents to a refund. Petitioners claim that there was a Section 23. Non-Forfeiture of Payments.1âwphi1 No
mere delay in the completion of the project and that they installment payment made by a buyer in a subdivision or
25
condominium project for the lot or unit he contracted to buy We likewise affirm the award of attorney’s fees because
shall be forfeited in favor of the owner or developer when the respondents were forced to litigate for 14 years and incur
buyer, after due notice to the owner or developer, desists expenses to protect their rights and interest by reason of the
from further payment due to the failure of the owner or unjustified act on the part of petitioners. 18 The imposition
developer to develop the subdivision or condominium project of P10,000.00 administrative fine is correct pursuant to
according to the approved plans and within the time limit for Section 38 of Presidential Decree No. 957 which reads:
complying with the same. Such buyer may, at his option, be
reimbursed the total amount paid including amortization Section 38. Administrative Fines. The Authority may prescribe
interests but excluding delinquency interests, with interest and impose fines not exceeding ten thousand pesos for
thereon at the legal rate. (Emphasis supplied). violations of the provisions of this Decree or of any rule or
regulation thereunder. Fines shall be payable to the Authority
Conformably with these provisions of law, respondents are and enforceable through writs of execution in accordance
entitled to rescind the contract and demand reimbursement with the provisions of the Rules of Court.
for the payments they had made to petitioners.
Finally, we sustain the award of moral damages. In order that
Notably, the issues had already been settled by the Court in moral damages may be awarded in breach of contract cases,
the case of Fil-Estate Properties, Inc. v. Spouses the defendant must have acted in bad faith, must be found
Go13 promulgated on 17 August 2007, where the Court stated guilty of gross negligence amounting to bad faith, or must
that the Asian financial crisis is not an instance of caso have acted in wanton disregard of contractual
fortuito. Bearing the same factual milieu as the instant case, obligations.19 The Arbiter found petitioners to have acted in
G.R. No. 165164 involves the same company, Fil-Estate, albeit bad faith when they breached their contract, when they
about a different condominium property. The company failed to address respondents’ grievances and when they
likewise reneged on its obligation to respondents therein by adamantly refused to refund respondents' payment.
failing to develop the condominium project despite
substantial payment of the contract price. Fil-Estate advanced In fine, we find no reversible error on the merits in the
the same argument that the 1997 Asian financial crisis is a impugned Court of Appeals' Decision and Resolution.
fortuitous event which justifies the delay of the construction
project. First off, the Court classified the issue as a question WHEREFORE, the petition is PARTLY GRANTED. The appealed
of fact which may not be raised in a petition for review Decision is AFFIRMED with the MODIFICATION that the legal
considering that there was no variance in the factual findings interest to be paid is SIX PERCENT (6%) on the amount due
of the HLURB, the Office of the President and the Court of computed from the time of respondents' demand for refund
Appeals. Second, the Court cited the previous rulings of Asian on 8 October 1998.
Construction and Development Corporation v. Philippine
Commercial International Bank14 and Mondragon Leisure and
SO ORDERED.
Resorts Corporation v. Court of Appeals15 holding that the
1997 Asian financial crisis did not constitute a valid
justification to renege on obligations. The Court expounded:

G.R. No. 177921 December 4, 2013


Also, we cannot generalize that the Asian financial crisis in
1997 was unforeseeable and beyond the control of a business
corporation. It is unfortunate that petitioner apparently met METRO CONCAST STEEL CORPORATION, SPOUSES JOSE S.
with considerable difficulty e.g. increase cost of materials and DYCHIAO AND TIUOH YAN, SPOUSES GUILLERMO AND
labor, even before the scheduled commencement of its real MERCEDES DYCHIAO, AND SPOUSES VICENTE AND
estate project as early as 1995. However, a real estate FILOMENA DYCHIAO, Petitioners,
enterprise engaged in the pre-selling of condominium units is vs.
concededly a master in projections on commodities and ALLIED BANK CORPORATION, Respondent.
currency movements and business risks. The fluctuating
movement of the Philippine peso in the foreign exchange The Facts
market is an everyday occurrence, and fluctuations in
currency exchange rates happen everyday, thus, not an On various dates and for different amounts, Metro Concast, a
instance of caso fortuito.16 corporation duly organized and existing under and by virtue
of Philippine laws and engaged in the business of
The aforementioned decision becomes a precedent to future manufacturing steel,5 through its officers, herein individual
cases in which the facts are substantially the same, as in this petitioners, obtained several loans from Allied Bank. These
case. The principle of stare decisis, which means adherence loan transactions were covered by a promissory note and
to judicial precedents, applies. separate letters of credit/trust receipts.

In said case, the Court ordered the refund of the total By way of security, the individual petitioners executed several
amortizations paid by respondents plus 6% legal interest Continuing Guaranty/Comprehensive Surety Agreements19 in
computed from the date of demand. The Court also awarded favor of Allied Bank. Petitioners failed to settle their
attorney’s fees. We follow that ruling in the case before us. obligations under the aforementioned promissory note and
trust receipts, hence, Allied Bank, through counsel, sent them
The resulting modification of the award of legal interest is, demand letters, seeking payment of the total amount
also, in line with our recent ruling in Nacar v. Gallery of P51,064,093.62, but to no avail. Thus, Allied Bank was
Frames,17 embodying the amendment introduced by the prompted to file a complaint for collection of sum of
Bangko Sentral ng Pilipinas Monetary Board in BSP-MB money21 (subject complaint) against Metro Concast.
Circular No. 799 which pegged the interest rate at 6% Petitioners admitted their indebtedness to Allied Bank but
regardless of the source of obligation. denied liability for the interests and penalties charged,

26
claiming to have paid the total sum of P65,073,055.73 by way the outset, the Court must dispel the notion that the MoA
of interest charges for the period covering 1992 to 1997.24 would have any relevance to the performance of petitioners’
obligations to Allied Bank. The MoA is a sale of assets
They also alleged that the economic reverses suffered by the contract, while petitioners’ obligations to Allied Bank arose
Philippine economy in 1998 as well as the devaluation of the from various loan transactions. Absent any showing that the
peso against the US dollar contributed greatly to the downfall terms and conditions of the latter transactions have been, in
of the steel industry, directly affecting the business of Metro any way, modified or novated by the terms and conditions in
Concast and eventually leading to its cessation. Hence, in the MoA, said contracts should be treated separately and
order to settle their debts with Allied Bank, petitioners distinctly from each other, such that the existence,
offered the sale of Metro Concast’s remaining assets, performance or breach of one would not depend on the
consisting of machineries and equipment, to Allied Bank, existence, performance or breach of the other.
which the latter, however, refused. Instead, Allied Bank
advised them to sell the equipment and apply the proceeds of Fortuitous events by definition are extraordinary events not
the sale to their outstanding obligations. Accordingly, foreseeable or avoidable. It is therefore, not enough that the
petitioners offered the equipment for sale, but since there event should not have been foreseen or anticipated, as is
were no takers, the equipment was reduced into ferro scrap commonly believed but it must be one impossible to foresee
or scrap metal over the years. In 2002, Peakstar Oil or to avoid. The mere difficulty to foresee the happening is
Corporation (Peakstar), represented by one Crisanta Camiling not impossibility to foresee the same. To constitute a
(Camiling), expressed interest in buying the scrap metal. fortuitous event, the following elements must concur: (a) the
During the negotiations with Peakstar, petitioners claimed cause of the unforeseen and unexpected occurrence or of the
that Atty. Peter Saw (Atty. Saw), a member of Allied Bank’s failure of the debtor to comply with obligations must be
legal department, acted as the latter’s agent. Eventually, with independent of human will; (b) it must be impossible to
the alleged conformity of Allied Bank, through Atty. Saw, a foresee the event that constitutes the caso fortuito or, if it
Memorandum of Agreement25 was drawn between Metro can be foreseen, it must be impossible to avoid; (c) the
Concast, represented by petitioner Jose Dychiao, and occurrence must be such as to render it impossible for the
Peakstar, through Camiling, under which Peakstar obligated debtor to fulfill obligations in a normal manner; and (d) the
itself to purchase the scrap metal for a total consideration obligor must be free from any participation in the aggravation
of P34,000,000.00. of the injury or loss.40 (Emphases supplied)

Unfortunately, Peakstar reneged on all its obligations under While it may be argued that Peakstar’s breach of the MoA
the MoA. In this regard, petitioners asseverated that: was unforseen by petitioners, the same us clearly not
"impossible"to foresee or even an event which is
(a) their failure to pay their outstanding loan obligations to independent of human will." Neither has it been shown that
Allied Bank must be considered as force majeure ; and said occurrence rendered it impossible for petitioners to pay
their loan obligations to Allied Bank and thus, negates the
(b) since Allied Bank was the party that accepted the terms former’s force majeure theory altogether. In this regard,
and conditions of payment proposed by Peakstar, petitioners petitioners’ liability must perforce stand. Considering,
must therefore be deemed to have settled their obligations to however, that Allied Bank’s extra-judicial demand on
Allied Bank. petitioners appears to have been made only on December 10,
1998, the computation of the applicable interests and penalty
charges should be reckoned only from such date.
Claiming that the subject complaint was falsely and
maliciously filed, petitioners prayed for the award of moral
damages and exemplary damages, attorney’s fees, and G.R. No. L-7859 February 12, 1913
payment for other litigation expenses, including costs of suit.
VICTORIA SEOANE, administratrix of The Intestate Estate of
The Issue Eduardo Fargas,Plaintiff-Appellee, vs. CATALINA FRANCO,
administratrix of The Intestate Estate of Manuel
Franco, Defendant-Appellant.
whether or not the loan obligations incurred by the
petitioners under the subject promissory note and various
trust receipts have already been extinguished.. Ramon Salinas, for appellant.
Gibbs, McDonough and Blanco, for appellee.
The Court’s Ruling: NO.
MORELAND, J. :chanrobles virtual law library
Article 1231 of the Civil Code states that obligations are
extinguished either by payment or performance, the loss of This is an appeal from a judgment of the Court of First
the thing due, the condonation or remission of the debt, the Instance of Zamboanga in favor of the plaintiff, holding that
confusion or merger of the rights of creditor and debtor, the right of action upon the mortgage debt which was the
compensation or novation. basis of the claim presented against the plaintiff's estate had
prescribed.chanroblesvirtualawlibrary chanrobles virtual law
library
Petitioners classify Peakstar’s default as a form of force
majeure in the sense that they have, beyond their control,
lost the funds they expected to have received from the The mortgage in question was executed on the 13th of
Peakstar (due to the MoA) which they would, in turn, use to October, 1884, to secure the payment of the sum of
pay their own loan obligations to Allied Bank. They further P4,876.01, the mortgagor agreeing to pay the sum "little by
state that Allied Bank was equally bound by Metro Concast’s little." The claim appears to have been presented to the
MoA with Peakstar since its agent, Atty. Saw, actively plaintiff's intestate on the 8th of August, 1911. Nothing has
represented it during the negotiations and execution of the been paid either of principal or of
said agreement. Petitioners’ arguments are untenable. At
27
interest.chanroblesvirtualawlibrary chanrobles virtual law which must be fixed by the
library courts.chanroblesvirtualawlibrary chanrobles virtual law
library
We are of the opinion that this case falls within the provisions
of article 1128 of the Civil Code, which reads as follows: The only action which can be maintained under the terms of
the contract is that bywhich it is sought to be obtain from the
1128. When the obligation does not fix a term, but it can be judge the determination of this period, and not the unlawful
inferred from its nature and circumstance that there was an detainer action which has been brought - an action which
intention of granting it to the debtor, the courts shall fix the presupposes the expiration of the term and makes it the duty
duration of such a of the judge to simply the decree the eviction. To maintain
term.chanroblesvirtualawlibrary chanrobles virtual law library the latter action it is sufficient to show the expiration of the
term of the contract, whether conventional or legal; in order
The courts shall also fix the duration of a term when it may to decree the relief to be granted in the former action it is
have been left at the will of the debtor. necessary for the judge to look into the character and
conditions of the mutual undertakings with a view to
supplying the lacking element of a time at which the lease is
The obligation in question seems to leave the duration of the
to expire.
period for the payment thereof to the will of the debtor. It
appears also that it was the intention of the instrument to
give the debtor time within which to pay the obligation. In The case of Barreto vs. The City of Manila (7 Phil. Rep., 416)
such cases this court has held, on several occasions, that the dealt with a case where the terms of a donation did not fix
obligation is not due and payable until an action has been the time of the performance of the condition placed upon the
commenced by the mortgagee against the mortgagor for the donation, and the court held that the period must be
purpose of having the court fix the date on and after which determined by the court in a proper action in accordance
the instrument shall be payable and the date of maturity is with article 1128 of the Civil Code, saying (p. 420):
fixed in pursuance thereof. The case of Eleizegui vs. The
Manila Lawn Tennis Club (2 Phil. Rep., 309), in which the The contract having fixed no period in which the condition
opinion was written by the Chief Justice of the court, is the should be fulfilled, the provisions of article 1128 of the Civil
leading case upon the subject. In that case the question was Code are applicable and it is the duty of the court to fix a
over the duration of a lease concerning "a piece of land for a suitable time for its fulfillment. Eleizegui vs. The Manila Lawn
fixed consideration and to endure at the will of the lessee." In Tennis Club, 2 Phil. Rep., 309. (11 Phil. Rep., 624. 1 )
discussing the question the court said (p. 310):
In the case of Levy Hermanos vs. Paterno (18 Phil. Rep., 353)
With respect to the term of the lease the present question the court said (p. 355):
has arisen. In its discussion three theories have been
presented: One which makes the duration depend upon the The defendant having bound himself to pay his debt to the
will of the lessor, who, upon one month's notice given to the plaintiffs in partial payments, as set forth in the note in
lessee, may terminate the lease so stipulated; another which, question, it is seen that the obligation is one of payment by
on the contrary, makes it dependent upon the will of the installments, since its fulfillment cannot be required
lessee, as stipulated; and the third, in accordance with which immediately nor does its existence depend upon the
the right is reserved to the court to fix the duration of the happening of any particular event. But, thought the obligation
term. is one of payment by installments, nevertheless no fixed day
was specified for its fulfillment, so that the period for
The clause on which the case turns is as follows (p. 312): payment is undetermined or was not fixed by the parties
when they executed the contract. Besides, it is evident that
Mr. Williamson, or whoever may succeed him as secretary of the term for payment was granted for the exclusive benefit of
the club, may terminate this lease whenever desired without the defendant and for his own convenience, as by the
other formality than that of giving a month's notice. The language of the document, the plaintiffs gained nothing by
owners of the land undertake to maintain the club as tenant the fact that the debt was not immediately demandable. Nor
as long as the latter shall see fit. was any interest stipulated on the debt during the time that it
should remain unpaid by the defendant. For the foregoing
reasons, and in whatever manner this case be considered, it is
Considering the case the court said (314):
unquestionable that it falls within the provisions of article
1128 of the Civil Code. . .
The Civil Code has made provision for such a case in all kinds
.chanroblesvirtualawlibrary chanrobles virtual law library
of obligations. In speaking in general of obligations with a
term it has supplied the deficiency of the former law with
The obligation being manifestly defective with regard to the
respect to the "duration of the term when it has been left to
duration of the period granted to the debtor, that is, to the
the will of the debtor," and provides that in this case the term
defendant, that defect must be cured by the courts through
shall be fixed by the courts. (Art. 1128, sec. 2.) In every
judicial decision which shall determine the said duration,
contract, as laid down by the authorities, there is always a
under the power expressly granted them for such purpose by
creditor who is entitled to demand the performance, and a
the legal provisions just above
debtor upon whom rests the obligation to perform the
transcribed.chanroblesvirtualawlibrary chanrobles virtual law
undertaking. In bilateral contracts the contracting parties are
library
mutually creditors and debtors. Thus, in this contract of lease,
the lessee is the creditor with respect to the rights
enumerated in article 1554, and is the debtor with respect to The trial court, therefore, acted in accordance with the law in
the obligations imposed by articles 1555 and 1561. The term exercising the said power in the present case, by fixing the
within which performance of the latter obligation is due is duration of the period on the basis that the payment of the
what has been left to the will of the debtor. This term it is debt should be made at the rate of P200 a month; and we see

28
no abuse of judicial discretion of fixing such a rate, as they appeared and expressed our opinion of what the
considering the importance of the obligation and the absence result of the case would be upon the merits if it subsequently
of any stipulation of interest in favor of the creditors. came before us upon the same facts. In that case we said (p.
17):
From these decisions it is clear that the instrument sued upon
in the case at bar is one which leaves the period of payment We believe, however, that, for the information of the parties
at the will of the mortgagor. Such being the case, an action interested in the subject matter of this action and to the end
should have been brought for the purpose of having the court that unnecessary litigation may be avoided, the opinion of
set a date on which the instrument should become due and the court should be given upon the facts presented in this
payable. Until such action was prosecuted no suit could be case. Knowing what our opinion is upon these facts it is
brought for the recovery of the amount named in the probable that the heirs will not care to pursue the litigation
instrument. It is, therefore, clear that this action is further unless, which is somewhat unlikely, they are able to
premature. The instrument has been sued upon before it is present new facts. We, therefore, proceed to a consideration
due. The action must accordingly be of the case upon the merits as presented by the record.
dismissed.chanroblesvirtualawlibrary chanrobles virtual law
library The judgment is affirmed, with the costs against the
appellant. So ordered.chanroblesvirtualawlibrary
Ordinarily when an action of this sort is dismissed the plaintiff
may at once begin his action for the purpose of fixing a date
upon which the instrument shall become due. From the
undisputed facts in this case and from the facts and
conditions that very probably cannot be charged hereafter, it
is our present opinion that such action is itself prescribed.
Section 38 of the Code of Civil Procedure reads as follows:

SEC. 38. To what this chapter does not apply. - This chapter
shall not apply to actions already commenced, or to cases
wherein the right of action has already accrued; but the
statutes in force when the action or right of action accrued
shall be applicable to such cases according to the subject of
the action and without regard to the form; nor shall this
chapter apply in the case of a continuing and subsisting trust,
nor to an action by the vendee of real property in possession
thereof to obtain the conveyance of it: Provided,
nevertheless, That all rights of action which have already
accrued, except those named in the last preceding paragraph,
must be vindicated by the commencement of an action or
proceeding to enforce the same within ten years after this Act
comes into effect.

This section evidently covers all rights of action of whatever


kind or nature, except those which have special limitations
and are referred to in subsequent sections. A right of action
to fix a day for the determination of the time of payment is
included within the terms of this section. The mortgage in
question having left the period of payment to the will of the
mortgagor, an action could have been maintained by the
mortgagee at any time after its execution for the naming of a
date on which the instrument must be paid in full. The right
of action accrued as soon as the instrument was executed.
Such action, therefore, falls within the provisions of section
38, and not having been commenced within the ten years
next following the 1st day of October, 1901, such action
cannot, under the facts as they now appear, be
maintained.chanroblesvirtualawlibrary chanrobles virtual law
library

While the expression of an opinion as to the prescription of


the action to fix a date for the maturity of the obligation in
question is unnecessary for a complete resolution of the case
before us, still we do not hesitate to express that opinion for
the reasons which we have heretofore given in one or two
cases, particularly that of Lichauco vs. Limjuco (19 Phil. Rep.,
12). That case went off upon the finding of the court that the
action could not be maintained by the plaintiff, Lichauco, on
behalf of his brothers and sisters and upon that finding the
complaint was dismissed. While the merits in that case were
not necessarily before us, we nevertheless took up the facts

29

Das könnte Ihnen auch gefallen