Beruflich Dokumente
Kultur Dokumente
Risk Management
1
5/6/2016
Risk Assessment
2
5/6/2016
3
5/6/2016
4
5/6/2016
5
5/6/2016
Score Risk
1–6 Low
7 – 14 Moderate
15 – ++ High
6
5/6/2016
Time Insignificant Delivery plan Delivery plan Delivery plan Delivery plan
schedule milestone milestone milestone delay milestone delay
slippage delay within delay of one of more than outside fiscal
quarter quarter one quarter year
Cost Insignificant <5% cost 5–10% cost 10–20% cost >20% cost
Objective
7
5/6/2016
• Assess the risk of changing weather on the unit price if case the
probability of the change of the weather is as following:
Weather Probability
Dry weather 10%
Showers 20%
Rains 50%
Heavy rains 20%
Wet 50%
8
5/6/2016
Risk Response
Planning
9
5/6/2016
Risk Avoidance
• The team changes the project plan to eliminate the risk
or to protect the project objectives from its impact.
Risk Transference
Risk Mitigation
• The team seeks to reduce the probability or
consequences of a risk event to an acceptable threshold
10
5/6/2016
Risk Acceptance
• The project manager and the project team decide to
accept certain risks.
11
5/6/2016
Thank You
12