Sie sind auf Seite 1von 12

5/6/2016

Risk Assessment & Analysis


Dr. Hossam Mohamed Toma

Risk Management

1
5/6/2016

Risk Assessment

• Risk assessment is the overall process of risk analysis


and risk evaluation.

• Its purpose is to develop agreed priorities for the identified


risks.

Qualitative Risk Analysis

• Qualitative Risk Analysis assesses the impact and


likelihood of the identified risks and develops prioritized
lists of these risks for further analysis or direct mitigation.

• The project team assesses each identified risk for its


probability of occurrence and its impact on project
objectives.

2
5/6/2016

Qualitative Risk Analysis

Qualitative Risk Analysis can be used by project teams:

• As an initial screening or review of project risks

• When a quick assessment is desired

• As the preferred approach for some simpler and smaller


projects where robust and/or lengthy quantitative analysis is
not necessary.

Qualitative Risk Analysis


• Risk identification results in the generation of a risk register.

• The risk register can be sizeable

• It is necessary to evaluate and prioritize the risk events


identified in the risk register.

• Prioritizing risks that present the highest potential for


significantly affecting project objectives gives Project
Managers the information necessary to focus project
resources.

How to Perform Qualitative Risk


Analysis
• Once a risk is identified, including a thorough description of
the risk and risk triggers, it can be characterized in terms of
probability of occurrence and the consequence if it does
occur.

1. Gather the project team and appropriate persons to discuss


project risk. Establish which of the qualitative risk matrices
you intend to use, and define the terms you plan to use
(Very High, High, Medium, Low, etc.).

2. Review the risk information from the risk identification


step.

3
5/6/2016

Defining Terms of the Matrix

How to Perform Qualitative Risk


Analysis

3. Discuss the risk with the group.

4. Evaluate the likelihood of the risk occurring by asking


the group, “How likely is it that this risk will occur?”
Record the result that the group agrees on.

How to Perform Qualitative Risk


Analysis

5. Evaluate the consequences if the risk does occur by


asking the group, “What will be the impacts if this risk
does occur?” Record the result that the group agrees on.

6. Prioritize the risks based on the results of the


qualitative analysis. If it is desirable, the risks can also be
grouped by category (e.g., Environmental, Structures/
Geotech) and ranked within each category.

4
5/6/2016

Determination of the Probability &


Impact of Risks

Defining Risks on the Qualitative Risk


Matrix

Example 2 (Probability Scale)

Risk Probability Ranking


Ranking Probability of Risk Event
5 80–99%
4 60–79%
3 40–59%
2 20–39%
1 1–19%

5
5/6/2016

Example 2 (Impact Scale)

Risk Impact Ranking


Ranking Impact of Risk Event
5 16
4 8
3 4
2 2
1 1

Determination of the Risk Matrix Scale

Translate Score to Risk Rank

Score Risk
1–6 Low
7 – 14 Moderate

15 – ++ High

Qualitative Risk Matrix


Time, Cost, and Scope Objectives
Large Aversion to High & Very High Impacts
Probability
5 5 10 20 40 80
4 4 8 16 32 64
3 3 6 12 24 48
2 2 4 8 16 32
1 1 2 4 8 16
1 2 4 8 16
Impact

6
5/6/2016

Evaluating Impact of a Risk on Major Project Objectives


Qualitative
Impact 1 Risk
2 Matrix
4 8 16

Time Insignificant Delivery plan Delivery plan Delivery plan Delivery plan
schedule milestone milestone milestone delay milestone delay
slippage delay within delay of one of more than outside fiscal
quarter quarter one quarter year
Cost Insignificant <5% cost 5–10% cost 10–20% cost >20% cost
Objective

cost increase increase increase increase increase


Scope Scope decrease Changes in Changes in Sponsor does Scope does not
is barely project limits project limits not agree that meet purpose
noticeable or features or features scope meets the and need
with <5% cost with 5–10% purpose and
increase cost increase need

Quantitative Risk Analysis


• Quantitative Risk Analysis numerically estimates the probability
that a project will meet its cost and time objectives. Quantitative
analysis is based on a simultaneous evaluation of the impacts of
all identified and quantified risks.

• Quantitative techniques, such as Monte Carlo simulation, can be


a powerful tool for analysis of project risk and uncertainty. This
technique provides project forecasts with an overall outcome
variance for estimated project cost and schedule. Probability
theory allows us to look into the future and predict possible
outcomes.

Quantitative Risk Analysis (Example)

• In a construction project the unit price and estimated for


excavation is depending on the type of the excavated soil as
shown in the following table.

Soil Type Unit Price (L.E.) Time (minutes)


Very dry soil 2.6 12
Fairly dry 3.0 15
Wet 6.0 25
Very wet 8.0 35

7
5/6/2016

Quantitative Risk Analysis (Example)

• Assess the risk of changing weather on the unit price if case the
probability of the change of the weather is as following:

Weather Probability
Dry weather 10%
Showers 20%
Rains 50%
Heavy rains 20%

Quantitative Risk Analysis (Example)

• Probability of the excavated soil will be as following:

Excavated soil Probability

Very dry soil 10%

Fairly dry 20%

Wet 50%

Very wet 20%

Quantitative Risk Analysis (Example)


• Probability of the cost and time will be as following:

Excavated soil Probable cost Probable time

Very dry soil 0.1 * 2.6 = 0.26 0.1 * 12 = 1.2

Fairly dry 0.2 * 3.0 = 0.60 0.2 * 15 = 3.0

Wet 0.5 * 6.0 = 3.00 0.5 * 25 = 12.5

Very wet 0.2 * 8.0 = 1.60 0.2 * 35 = 7.0

Total probable cost/time 5.46 23.7

8
5/6/2016

Risk Response
Planning

Risk Response Planning


• Risk response planning focuses on the high-risk items
evaluated in the qualitative and/or quantitative risk
analysis

• It identifies and assigns parties to take responsibility for


each risk response

• This process ensures that each risk requiring a response


has an owner

Risk Response Planning


• The project manager and risk team identify which
strategy is best for each risk

• These strategies and actions include:


Avoidance
Transference
Mitigation
Acceptance

9
5/6/2016

Risk Avoidance
• The team changes the project plan to eliminate the risk
or to protect the project objectives from its impact.

• The team might achieve this by changing scope, adding


time, or adding resources

Risk Transference

• The team transfers the financial impact of risk by


contracting out some aspect of the work.

Risk Mitigation
• The team seeks to reduce the probability or
consequences of a risk event to an acceptable threshold

• They accomplish this via many different means that are


specific to the project and the risk

• Mitigation steps, although costly and time-consuming,


may still be preferable to going forward with the
unmitigated risk

10
5/6/2016

Risk Acceptance
• The project manager and the project team decide to
accept certain risks.

• They do not change the project plan to deal with a risk,


or identify any response strategy other than agreeing to
address the risk if and when it occurs.

Risk Monitoring &


Control

Risk Monitoring & Control


• Risk monitoring and control keeps track of the identified
risks, residual risks, and new risks.

• It also ensures the execution of risk response plans, and


evaluates their effectiveness.

• Risk monitoring and control continues for the life of the


project. The list of project risks changes as the project
matures, new risks develop, or anticipated risks
disappear.

11
5/6/2016

Thank You

12

Das könnte Ihnen auch gefallen