BILLS OF QUANTITY
SN Item Rate Quantity Unit Rate (TZS) Total
Excavate trench on soil 700mm wide and not more than 1.2m deep for
1 m3 42.84 6,000 257040
Strip foundation
Excavate Soil pits for Isolated Pad Footing 1.4mx1.4m and not more than
2 m3 28.224 6,000 169344
1.25m deep
3 Provide a sand filling layer as bliding for the exacavated trench m3 6 25,000 150000
Provide and Fix 16mm Dia reinforcements for the Pad Foundation as per
4 Ton 0.5 1,400,000 700000
drawings details
Provide and fix Starter reinforcement bars for Columns upto plinth level
5 Ton 0.2 1,400,000 280000
as per drawings details
Provide and Pour C25 Concrete for Strip foundation as per drawings
6 m3 13.5 180,000 2430000
petails
Provide and Pour C25 Concrete for Isolated Pad foundation as per
8 m3 6.48 180,000 1166400
drawings petails
Provide and Fix Blocks For Foundation Block Walling (230mm Thick) up
9 to plinth level as per drawing's details and to the project managers Nos. 1100 1,400 1540000
satisfaction
10 Provide and Fix sown formwork for the columns upto the plinth level m2 6 32,500 195000
11 Provide and Fix C25 grade concrete for the columns up to the plinth level m3 0.8 180,000 144000
Remove to spoil Top layer of clay soil not more than 0.5m deep within
12 m3 37 6,000 222000
the structure as per Project manager's satisfaction
Provide and Fix a 200mm thick layer of sand on top of a well compacted
13 soil as bedding for hardcore of the structure to the project manager's m3 18.5 25,000 462500
satisfaction.
Provide and fix 200mm thick layer of Selected stones as hardocore for
14 m3 18.5 50,000 925000
the structure
Provide and fix sown Form Work for Groundbeam at the plinth level as
15 m2 44 32,500 1430000
per drawing's details
Provide and Lay C25 grade Concrete to the beam and 100mm thick slab
18 m3 9.25 180,000 1665000
as per drawing details.