MS FOR FIXING PIPES ALONG THE EXISTING BRIDGE

Project: ………………………………

Contract No: …………………………

Client: ………………………….

Date: …………………

Execute by: …………………..

Title: Method Statement for fixing the part of the new DN


400mm rising main to the existing access bridge on the
southern side
Contents

1.0 General statement...............................................................................................2

2.0 Purpose and scope..............................................................................................2

3.0 Method statement................................................................................................2

4.0 Staff to be used..................................................................................................4

5.0 Equipments and tools........................................................................................4

6.0 Materials to be used..........................................................................................5

7.0 Safety................................................................................................................5

8.0 Personal protective Gears.................................................................................5

9.0 Workprogram.......................................................................................................5

1/5
MS FOR FIXING PIPES ALONG THE EXISTING BRIDGE

1.0 General Statement

About 10 m DN400 pipes will be fixed along the existing access bridge.

2.0 Purpose and scope

The purpose of this Method Statement is to explain the proper procedure on how to
fix the part of the new DN 400mm raw water main to the existing access bridge on
the southern side according to BoQ item no:2.1.3.6

3.0 Method statement

The new DN400 pipes will be fixed to the bridge, By using U bar. As below drawing.

2/5
MS FOR FIXING PIPES ALONG THE EXISTING BRIDGE

3/5
MS FOR FIXING PIPES ALONG THE EXISTING BRIDGE

4.0 Staff for this task - Supervisors and labours

S.no Description Quantity Remarks


1 Engineer 1
2 Foreman 1
3 Plumber 2
4 Surveyor 1
5 Unskilled labour 10
6 Welder 1

5.0 Equipment and Tools

S.no Description Quantity Remarks


1 Welding machine 1
2 Drilling machine 1
3 Levelling staff 1
4 Levelling machine 1
5 Grinder 1
6 Measuring tape 1

4/5
MS FOR FIXING PIPES ALONG THE EXISTING BRIDGE

50m
6.0 Materials to be used

S.no Description Quantity Remarks


1 Steel pipes DN400 1pcs @10m long
2 DN400 flow meter 1pc
3 DN400 dismantle joint 1pc
4 DN400 BFV 2pcs
5 DN400/200 F-F tee 1pc
6 U bar 4*10*5 20m
7 ∅12 bolts 20pcs
8 Angle bar 40*4 20m

7.0 Safety

 All works shall comply with safety procedure or instruction setout in project
safety plan and municipality rules and regulations

 Basic PPE to be worn by all staff and labours

 Trained operator and banksman would be engaged to control or operate heavy


equipment machine

 To inspect equipments so as to be satisfied that it is working properly

8.0 Personal Protective Gears

PPE that will be used during the work includes gum boots,rubber gloves,leather
gloves,overalls,dust musks,hard hats,safety boots,etc

9.0 Work program

10/11/2014-15/11/2014: installation of U bar to the existing bridge

16/11/2014-21/11/2014: Installation of pipe pieces along the bridge

5/5