Beruflich Dokumente
Kultur Dokumente
Project: …………………………………
Contract No: …………………..
Client: …………………………………….
Date: ………………………….
Prepared by: ………………………..
Contents
1.0 Purpose and Scope .....................................................................................................2
2.0 Preparatory works.......................................................................................................2
3.0 General statement.......................................................................................................2
4.0 Work Methodology.......................................................................................................3
4.1 Cleaning of storage tanks.............................................................................................3
4.2 Setting out of new column bases and columns...............................................................3
4.3 Inserting of Re-bars.....................................................................................................3
4.4 Fixing of steel reinforcement bars.................................................................................3
4.5 Shuttering construction................................................................................................4
4.6 Checklist for a good formwork.....................................................................................4
4.6.1Formwork.................................................................................................................4
4.6.2Joint.........................................................................................................................4
4.6.3Ties and Fixings........................................................................................................4
4.6.4Finish.......................................................................................................................4
4.7 Loading, Mixing, and Discharging.................................................................................4
4.8 Concrete casting.........................................................................................................5
4.9 Striking of formwork...................................................................................................5
4.10 Cleaning of formwork................................................................................................5
4.11 Concrete Protection and Curing..................................................................................5
5.0 Construction of Roof structure and Roof covering..........................................................6
5.1 Sheet length...............................................................................................................6
5.2 Fastenings..................................................................................................................6
5.2.1 Setting of screws......................................................................................................6
5.3 Handling of Roofing sheets on site................................................................................7
5.4 Walking on roofs..........................................................................................................7
5.5 Installing of Roofing sheets..........................................................................................7.
5.6 General installation procedure of Roofing sheets............................................................7
5.6.1 Check flatness, slope and overhang........................................................................7
5.6.2 Orient sheets before lifting.....................................................................................8
5.6.3 Position first sheet.................................................................................................8
5.6.4 Position other sheets..............................................................................................8
5.6.5 Check alignment occasionally..................................................................................8
5.6.6 Side-lapping and positioning roofing sheets.............................................................9
5.7 Marking out, cutting and drilling..................................................................................9
5.7.1 Marking out...........................................................................................................9
5.7.2 Cutting..................................................................................................................9
5.7.3 Making holes.........................................................................................................9
5.7.4 Clean up..............................................................................................................10
Method Statement for roof covering storage tanks
The purpose of this Method Statement is to explain the proper intended procedures,
on how to construct new concrete columns including fixation of steel reinforcement
bars, construction of the shuttering, casting concrete and construction of roof
covering for three existing open clear water storage tanks, without exposing the
workers to injuries.
Submission of Design mix for concrete class C30 to the RE for reference only.
Submission of request for inspection of shuttering arrangement for the various
stages of work to the RE for approval as per available drawings and on the base
of Contractor’s report. Respective Drawings shall be submitted.
Submission of request for inspection of reinforcement arrangement to the RE,
before the shuttering is being closed, for approval
No concrete shall be placed, prior to the approval by the Engineer.
IF operator TUWASA will allow to shutdown all the three existing open water storage
tanks at the same, this will be good and will enable us Contractor to complete works
at the shortest possible time.
Otherwise, we will demand to work on two tanks simultaneously and let the other
remaining one to continue operating.
All new reinforced concrete columns and beams shall be made class C30 as
recommended by our Designer and noted in the drawings which approval has been
issued by Engineer’s letter dated on 23rd May 2014 and with reference.no
TUWASA/WSDP/010/HB together with an absolute water proof layer of plaster of 20
mm thickness, on all columns, which are going to be exposed to water.
When Operator TUWASA shutdown the entry of clear water from the filters to the
existing clear water storage tanks, we shall remove all sludge deposits which are
normally found in abundance at the bottom of the tanks.
Sludge deposits shall be removed through existing collecting open channel at the
middle of the storage tank towards existing sludge drain pipe up to the disposal
pond.
We will use clean water and wire brushes and blooms to make the concrete floor
and wall surfaces of the storage tanks clean and make sure that all the surfaces are
completely dried ready for marking and setting out
At this stage, we shall also remove the existing mild steel pipe handrails and discard
away to the disposal.
After the floors of the tanks are clean we shall set out on the ground for the new
column bases and new columns in accordance to the new revised contractor’s design
and when this work is completed we will request Engineers to check and when is
approved we will start fixing reinforcement steel bars
The setting out of the new column bases shall be 650x650mm and new columns
type1 and type2 shall be 250x250mm
We shall drill holes on existing ground concrete floors in order to insert re-bars of
12mm for column bases and 16mm for new columns using heavy duty drill machines
and mechanical hammers
Reinforcement steel re-bars will be cut to the required sizes, and made clean by
brushing to remove rubbish, rust and stains and finally inserted into already drilled
holes on the existing concrete floor of the storage tank
Fixing of Steel reinforcement bars for new columns and ring beams inside existing
open clear water storage tanks as per the approved drawing numbers WP08-06 and
WP00-07, which;
Method Statement for roof covering storage tanks
Reinforcement steel bars of sizes 8, 12, and 16mm diameter all these
diameters has been approved. shall be cleaned to remove dust, rust and
stains and cut and bent to the required sizes and shapes, hence fixed into
respective positions according to the structural drawings and bar bending
schedule in reference to BS4449, structural use of reinforcements.
Any loose binder or ties along the splices of reinforcement steel shall be re-
tightened and shall be bend inward, the free ends of the binding wire or ties.
Concrete spacers of at least class 30 concrete, 30 mm thickness shall be used
in sufficient numbers, on the steel bars as distance keepers to the formwork.
4.6.1 Formwork
4.6.2 Joints
Formwork joints to be flush and tight and No nails protruding into the concrete.
Formwork joints to be sealed and Construction joints strutted and supported.
4.6.4 Finish
Consider from experience: the loading period is extended from the time when the
first constituent is fed into the mixer to when all the constituents are in the mixer (Six
(6) minutes). Also add the time for discharging the content.
One set of cubes consisting of 8 [2.302.4] cubes are to be taken for testing ( 4 Nos
of cubes to be tested on 7th days, and 3 4 cubes to be tested after the 28th day.
[Test according to Specs Cl. 2.302.4 Pg VII-58 Last Para.& vii-59 2nd para].
Curing is the process of controlling the rate and extent of moisture loss from
concrete during cement hydration at least for a period of 7 days.
It provides time for the hydration of the cement to occur and ensures that the
hydration process is not hindered by lack of water.
Method Statement for roof covering storage tanks
We shall fix steel scaffolding inside the storage tanks to provide working platform for
labour and passage of materials during construction of roof structure and roof
covering.
After the roof structure is accurately completed, we shall ask the Engineer to check
before fixing IT5 roofing sheets.
All required construction materials shall be lifted by our manual labour and whenever
it becomes necessary we shall use crane which is mounted on truck.
5.2 Fastenings
Traditional slot-headed roofing screws (or nails) and washers should be used on
those parts of a roof that contribute to the building’s appearance, while modern
hexagonal nut-headed screws should only be used on less visible parts of a roof.
Fasteners with sealing washers should be tightened only until the washer is gripped
firmly enough to provide a weathertight seal. The fasteners should not be over-
tightened because this may split the sealing washer or deform the sheet, either of
which could lead to water penetration.
Method Statement for roof covering storage tanks
On this work, we shall reduce handling time by lifting bundles of corrugated sheets
with a crane direct from the delivery truck onto the roof frame. We shall use a
spreader bar for a long sheets. For small to medium size corrugated sheets, without
mechanical handling facilities, we shall unload sheets by hand and pass them up to
the roof one at a time.
We shall ensure that we walk on roofing carefully, to avoid damage to either the
roofing or we our-self.
Generally, we shall keep our weight evenly distributed over the soles of both feet to
avoid concentrating our weight on either heels or toes.
When walking across the ribs, it is better to walk over or close to the roofing
supports. (Usually over fastener locations.)
We shall be more careful when moving between supports and not to walk in the pan
immediately adjacent to flashings or translucent sheeting.
Always we will take particular care when walking on wet or newly laid sheets
particularly on steeply pitched roofs.
If there will be heavy foot traffic on a roof, we shall provide a temporary walkway or
working platform with consideration of hand rails to minimize damage.
In order to maximize water tightness, we shall always place roof screws through the
crests.
Always we shall drive the screws perpendicular to the roofing, and in the centre of
the corrugation or rib.
To Make any necessary adjustments before starting laying sheets, because they
will be difficult or impossible to rectify later.
It is much easier and safer to turn sheets on the ground than up on the roof. Before
lifting sheets on to the roof, check that they are the correct way up and the
overlapping side is towards the edge of the roof from which installation will start.
Place bundles of sheets over or near firm supports, not at mid span of roof
members.
With particular care, position the first sheet before fixing to ensure that it is correctly
located in relation to other parts of the building.
Check that the sheet:
is aligned with the end-wall (or its barge or fascia), bearing in mind the type of
flashing or capping treatment to be used; and
Aligns correctly at its ends in relation to the gutter and ridge
Fix the sheet
After fixing the first sheet in position, align the following sheets using:
The long edge of the previous sheet; and
A measurement from the end of the sheet to the fascia or purlin at the gutter.
It is important that you keep the gutter-end of all sheets in a straight line.
Occasionally check that the sheets are still parallel with the first sheet, by taking two
measurements across the width of the fixed roofing.
At about half way through the job, perform a similar check but take the
measurements from the finishing line to aim for the final sheet to be parallel with
the end of the roof. If the measurements are not close enough, lay subsequent
sheets very slightly out of parallel to gradually correct the error by:
Properly align and fix a lap, then
Fix the other edge of the sheet, placing the fasteners slightly closer or further
from where they would normally be if there was no error. (Gradually correct the
error by placing the fasteners in such a way as to slowly bring the sheets back
into correct alignment.)
Method Statement for roof covering storage tanks
To prevent moisture being drawn into laps by capillary action, the edges of sheets
are slightly modified have the edges of the sheet over-curved and all have flutes
formed into the underlapping ribs.
It is important that sheets be lapped correctly. This means there should only be one
overlap/underlap - double lapping is not recommended.
After fixing the first sheet, place the next (and subsequent) sheet with its side lap
snugly over the previous sheet . Secure the sheet firmly in place until each end of
the sheet has been fixed.
You can do this easily by:
Align the bottom edge accurately by a measurement from the end of the sheet
to the fascia or purlin at the gutter;
Clamp the lap with a pair of vice grips
At the top of the sheet: nestle the side lap snugly, check alignment, and fix the
sheet with a fastener
A pencil of any colour may be used except black or so-called lead pencils. Don’t use
black pencils to mark roofing or walling because the graphite content can create an
electric cell when wet and thus cause deterioration of the finish. You can also use a
string line with chalk dust, or a fine, felt-tipped marker.
5.7.2 Cutting
Whenever possible, we shall minimize site-work by using roofing sheets already cut
to length in the factory.
For cutting thin metal on site, we recommend to use a power saw with a metal-
cutting blade because it produces fewer damaging hot metal particles and leaves
less resultant burr than does a carborundum disc.
Cut materials over the ground and not over other materials where hot particles can
fall and cause damage to finishes especially pre-painted finishes. It is best to have
the exterior colour finish of a pre-painted sheet facing down, however it is important
to protect the paint finish of the roofing sheets
Holes are often made by drilling or cutting by hole saw or jig saw. Mask the area
around the hole to protect paint from damage by swarf.
Method Statement for roof covering storage tanks
5.7.4 Clean up
Swarf (metal scraps and/or abrasive particles resulting from cutting and drilling)
left on the surfaces of materials will cause rust stains which can lead to reduced
life of the material.
Sweep or hose all metallic swarf and other debris from roof areas and gutters at
the end of each day and at the completion of the installation.
We shall extend steel pipes scaffolding inside and outside of the storage tanks on
the gable sides to provide working platform for labour and passage of materials
during construction of gable walls.
Walls on gable sides of storage tanks shall be constructed using cement sand blocks
and cement-sand mortar laid to accommodate a thickness of 230mm.
Walls shall be plastered and painted on both sides by our qualified skilled labour.
Mortar for block laying and walls plastering shall be mixed in the concrete mixer and
not by hand.
1. All work execution shall comply with safety procedures or instructions set out
in project safety plan and municipality rules and regulations. The respective
documents to be submitted to RE for approval at least 2 weeks ahead of a
planned operation.
2. Basic personal protective equipments (PPE) to be worn by all staff and
labourers at all times, during execution of work.
3. Qualified operators will be engaged to control and/or operate the heavy
equipment, machine, vibrators and the concrete mixers.
4. Provide sufficient lighting in preparation of possible night casting. We plan to
have 10 spot lights placed at the work site, which shall be located at Concrete
mixer (2nos), at the varying pouring locations (4nos), and 2nos at the
location of material loading.
5. PPE that will be used during the work includes gum boots, rubber gloves,
leather gloves, overalls, dust masks, safety goggles, hard hats, safety boots,
work gloves of suitable material, ear plugs and face masks, whenever
necessary.
Method Statement for roof covering storage tanks
12.0 Attachments