SCHEDULE OF PRICES

Amount
Item Description Qty Unit U.Rate
(RM)

B. TNB SUB-STATION

B1 Supply and install 30A 415V Distribution Board ( DB - SS ) 1 Lot 500.00

B2 From TNB LV panel to DB - SS using 2 x 10 sq. mm 1C PVC 150.00


1 Lot
cable in conduit to be laid to the TNB LV Panel.

B3 Wiring for lighting points using 2 x 1.5 sq.mm. PVC Cu 800.00


conductors in concealed G.I conduit complete with earth wire 1 Lot
and 5A switches.

B4 Wiring for emergency lighting (EL) points using 2 x 1.5 sq.mm. 400.00
PVC Cu conductors in concealed conduit earth wire on 1 Lot
switchless circuit.

B5 Wiring for Exhaust Fan points using 2 x 2.5 sq.mm. PVC Cu 100.00
conductors in concealed G.I conduit complete with earth wire 1 Lot
and 5A switches.

B6 Wiring for 13Amps outlet using 2 x 2.5sqmm. PVC Cu 450.00


conductors in concealed G.I conduit complete with wire and 1 Lot
13Amps metal-clad Socket Outlet.

B7 Supply and install the following fittings :


a. 1 X 100W bulkhead light fitting. 1 LS 500.00
b. 1 X 100W weather bulkhead 1 LS 50.00
c. TNB
18W Connection Charges (Provision)
emergency light. 1 LS 200.00
d. 13Amps metal clad S/S/O 1 LS included
e. Exhaust Fan c/w thermostat control 1 LS 1,350.00

B8 Earthing system of 16mm diameter copper rod and drive into 6,500.00
ground connection clamps, precast concrete pit and cover to 1 LS
achieve of less than three (3) ohm.

B9 Supply and install 1800mm x 1800mm x 1200mm heavy duty 5,000.00


manhole c/w excavation, encased concrete and making good in 1 Lot
reinstate to original condition as per TNB requirement.

B10 Supply and install 1800mm x 1200mm x 1200mm heavy duty 10,000.00
manhole c/w excavation, encased concrete and making good in 2 Lot
reinstate to original condition as per TNB requirement.

B11 Supply and install 3 Nos of 2 Layer (6 Nos) 150mm dia. G.I pipe 1,000.00
for drain crossing c/w accessories as specified in drawings and 1 Lot
specification.

B12 Supply and install 3 Nos of 2 Layer (6 Nos) 150mm dia. HDPE 8,000.00
pipe double wall laid underground from TNB sub-station to
Manholes and external road c/w accessories as specified in 1 Lot
drawings and specification.

B13 Any other items not mentioned in the above but indicated in the
drawings or deemed to be necessary for the satisfactory
completion of the works. If NONE is stated then it is deemed
that the contractor ha priced for ALL works essential for the
complete functioning of the system, please specify.

a. _____________________________________________
b. _____________________________________________
c. _____________________________________________
d. _____________________________________________

Section A - 18 TNB Substation


SCHEDULE OF PRICES

SUB-TOTAL FOR TNB SUB-STATION TO BE CARRIED 35,000.00


FORWARD TO THE SUMMARY OF PRICES

Section A - 19 TNB Substation

Das könnte Ihnen auch gefallen