Beruflich Dokumente
Kultur Dokumente
delivered bays
3000
development and manufacturing
of SF6 Gas Insulated Switchgear 550 kV GIS
(GIS) since the sixties. The first 3 Gorges Project (CN)
First 500 kV GIS
170 kV GIS was installed in 1969 at Jiang Men (CN)
550 kV GIS
Itaipu
54 bays
2
Active parts under high-voltage
GIS-Type ELK-3
Enclosure
SF6-gas
Insulation material
Low-voltage parts
Encapsulation single-phase
Rated voltage kV 420 550
Rated power-frequency withstand voltage kV 650 740
Rated lightning impulse withstand voltage kV 1425 1550
Rated current A 4000 4000
Rated breaking current kA 63 63
3
Flexibility by modular design
The background
Based on the unique experience
on development of GIS products
and realisation of GIS substation
projects, ABB developed the most
flexible modular design for GIS
equipment.
Front view of a double busbar GIS substation with four line bays, a bus coupler bay and a
Application transfer busbar.
The proven modular design pro- • Switching stations with rigorous • The extension of conventional
vides a high versatility to meet safety requirements. outdoor installations where
the most challenging present and • Indoor substations to occupy a space is constraint.
future user requirements. The fol- minimum of space in densely • Replacing existing substations
lowing examples exhibit the vari- populated urban areas. and upgrading the voltage level
ety of applications that have been without taking up extra space.
• Protected installations exposed
put into practice by ABB.
to unusually dirty, polluted or
corrosive environments.
Main design features
• Underground substations for
pumped storage and other • Lightweight enclosures of alu-
hydro-electric power stations. minium with good conductivity,
no eddy-current losses and a
• Generating plants where the
high resistance to corrosion.
switchgear can be very close to
the power transformers to give • Single-phase encapsulated
an ideal overall layout. design, assuring minimal dielec-
tric and dynamic stresses.
Legend
1 Circuit-breaker
Sectional view of type ELK-3 feeder bay 2 Operating mechanism (circuit-breaker)
4 with double busbars and outdoor bushing 3 Current transformer 8
4 Disconnector
5 Maintenance earting switch
6 Fast-acting earthing switch
7 Voltage transformer
8 Bushing
7
6
5
4
4
3
2 1
lar system. The view on page 4
shows the sectional elevation of a
typical switchgear bay of the
ELK-3 size. All live parts are pro-
tected aluminium enlosure. Pressu-
KUPPELFELD GOESGEN EICHHARD SUED
SS1
Modular design with standardised components for complying with user’s requirements. 5
Circuit-breaker
Circuit-breaker of gravity are the most famous In case of an overhaul, the inter-
features of the circuit-breakers. rupter column can easily be
• Reliable making and breaking
Extensive operating experiences removed from the enclosure.
capacity for heavy load and
up to voltage range 800 kV and
short-circuit currents The circuit-breaker is of the single-
80 kA as well as continuous
• Easy access to active parts for pressure type and works on the
research and development
inspection and overhaul well proven puffer principle. Dur-
activities have lead to a breaker
ing an interruption, a compression
• Low noise level design which fulfils newest
piston in each chamber generates
• Maintenance-free design standards in IEC and ANSI.
the SF6-gas pressure required to
• Separate contact system for extinguish the arc between the
continuous current and current Breaker design contacts.
interruption Each circuit-breaker comprises
• High dielectric withstand in three single-phase metal enclosed
open and closed position breaker poles. Each pole consists
• Single-phase auto-reclosing of the operating mechanism, the
• Compact hydraulic spring oper- interrupter column with 2 inter-
ating mechanism rupting chambers in series and the
enclosure with the basic support
• Continuous self-supervision of
structure. To guarantee simultani-
hydraulic system
ous interruption, the chambers are
• No external hydraulic piping mechanically connected in series.
• Type tested according latest IEC One grading capcitor for each
& ANSI standards chamber guarantees an equalised
voltage distribution across the
The simple, robust design and a
interrupting chambers.
horizontal layout with low center
ELK-3 Substation
6
Operating mechanism Working principle Now, both sides of the output
piston are connected to the high
Each pole of the circuit-breaker A hydraulic pump moves oil from
pressure and the circuit-breaker is
is equipped with the hydraulic the low pressure reservoir to the
moving to it’s closed position due
spring operating mechanism. It high pressure side of the energy
to the differential pressure prin-
combines the advantages of the storage piston, connected to the
ciple.
hydraulic operating mechanism disc springs. The output piston,
with those of the spring energy which is connected to the oper-
storage type. It’s compact, modular ating rod of the circuit-breaker
design, consisting of column, is controlled by a change-
over valve. For opening, it
• the housing with position indi-
switches hydraulically to the open
cator
position after the trip coil is actu-
• power-pack for energy storage ated for opening the breaker and
without any kind of external connects the bottom side of the
hydraulic pipe output piston with the low pres-
• monitoring module for control sure reservoir. The circuit-breaker
moves than to open position
It guarantees easy access to all
where it will be retained due to
components inside the drive for
the hydraulic pressure. For closing
overhaul and repair. Sealing of the
the circuit-breaker, the change-
pressure operated hydraulic circuit
over valve connects the bottom
against the atmosphere is achieved
side of the output piston to the
entirely by highly reliable static
high-pressure reservoir after actua-
seals. Hydraulic spring operating mechanism
tion of the closing coil.
7
0 1
M M
High pressure
Low pressure
Disconnector and earthing switch
Various applications:
In-line disconnectors
8 Angular disconnectors
Manual operation is possible. In Earthing switches are mounted ing operation the spring is auto-
this case electrical control connec- directly on the enclosure (see fig- matically released and the switch
tions are automatically disconnect- ure below). Slow-motion mainte- closed. The opening process is
ed. The mechanism is padlockable nance earthing switches are used slow, similar to that of the mainte-
in both, open or close position. for earthing isolated sections of nance earthing switch.
switchgear to protect personnel
In certain cases, an interposed
during maintenance and overhauls
insulation is fitted between the
Earthing switch or erection. The operating mecha-
earthing switch and the enclo-
nism is the same as used for the
• Safe earthing of sections of the sure. This provides access to the
disconnector switches. It is mount-
main circuit active parts for measuring pur-
ed on one phase. The two other
poses through the closed contacts,
• Designed for full short-circuit phases are operated by intermedi-
without opening the enclosure.
current in closed position ate gear.
During normal operation the insu-
• Insulated version available The fast-acting earthing switch is lation is by-passed. All the earth-
(optional) mainly used to discharge static ing switches have a mechanically
• Motor-operated mechanism, charges on overhead lines, HV coupled position indicator. The
slow closing or high-speed cables or long buses. It is designed gap between contacts can also be
spring-loaded to close on and carry full short- verified through a viewport by
• Full short-circuit making and circuit currents and to safely break means of an endoscope. To check
induced currents switching capacitive and inductive induced whether a point to be earthed
capability currents from long energised par- really is dead, the earthing switch
allel lines. Each phase is provided can be equipped with a capacitive
with its own operating mecha- tap for connecting a voltage test
nism. For the closing operation a unit. This additional safety device
spring in the drive is loaded by reduces the risk of closing onto a
the motor. At the end of the charg- live conductor.
0
0
0
Instrument transformer and surge arrester
Surge arrester
Length section of the principal arrange-
ment and cross-section of the MO resistor
stack 11
Connecting elements, terminations
Cable termination
High-voltage cables of various
types are connected to the SF6
switchgear via cable connection
assembly. It consists of the cable
sealing with connecting flange, the
main circuit end terminal and the
surrounding enclosure.
SF6-air bushings with porcelain (1) or composite insulator (2) Cable
termination (3) and transformer termination (4)
1 2 3 4
13
Local Control
The local control cubicle is based Safe station operation is ensured • Supervision of pole discrepancy
on the Bay Control Solution con- through following base functions. for circuit-breaker
cept BCS as a comprehensive scal-
able solution for control cubicles. The Bay Control Mimic BCM is the
Functions
The BCS is suitable for all types main component of the control
of switchgear used in transmission • Feeder and station interlocking, cubicle.
and subtransmission systems and depending on the position of all
every possible busbar configura- high-voltage apparatusses with
Features
tion. The BCS includes all required their blocking functionality
• Blocking of commands when • Representation of the single-line
functions for control and supervi-
crank handle of disconnectors or diagramme/gas schematic dia-
sion of a complete GIS as well as
earthing switches is introduced. gramme including position
the marshalling of all connections
indication of all primary appa-
to and from the GIS bays. • Extensive circuit-breaker super-
ratusses such as circuit-breaker,
vision through “Anti-pumping”,
disconnectors and earthing
pump and hydraulic system
switches with reliable LED’s
supervision, operation counter
for circuit-breaker and pumps. • Up to 8 high-voltage switching
devices can be monitored and
• Gas density and position super-
controlled with an easy-to-use
vision of circuit-breaker.
two hand push-button system
based on the ”select before
operate”principle
• Optional light guided operation
to support the operator
• Digital display of measuring
values as current, voltage, active
and reactive power
• Integrated local/remote key
switch
• Alarm unit for 16 feeder alarms
e.g. gas alarm, DC and AC
supervision
14
The local control cubicle is fit- On customer’s request additional
ted with prewired interface ter- functions (optional) can be pro-
minal blocks for the connection vided.
to feeder and station protection.
Standardised plug connections
This interface includes all needed
instead of terminal connections
measuring values of the feeder as
are available.
well as protection trip 1, trip 2 and
signals from the auto-reclose sys-
tem. Additional prewired terminal
groups are provided for the con-
nection to remote control systems
and remote alarm systems.
15
Space saving arrangements
Typical ELK-3 double busbar arrangement with two line bays (one with aerial, one with cable
connection), a transformer bay and bus coupler bay.
16 Double busbar bay: overhead line, transformer, cable feeder and bus coupler bay
Four diameters of a typical ELK-3 one-and-a-half breaker arrangement
Individual, fully equipped gas Safe gas sealing system Gas density monitor
compartments
A prerequisite for safe and reli- Reliability of SF6 gas-insulated The dielectric strength of the GIS
able operation is the segregation switchgear depends to a large depends on the gas density, which
of the sections and phases of the extent on the low rate of gas leak- is therefore directly monitored.
equipment into individual and age. Thus special attention is given The proven density monitor is
independent gas compartment. to the sealing system. The proven directly mounted on the enclosure.
This is also required to keep parts static sealing system at the flange The gas pressure acts on metal
of the system in operation while joints is effected by single sealing bellows, with a reference volume
other parts are out of service. The rings (“O-rings”). High-quality fin- for compensation of the tem-
segregation is achieved by barrier ish limits the gas losses to much perature. In case of gas leakage a
insulators. To avoid any impact less than 0.5 % per annum. micro-switch is actuated. Thresh-
from each other, all gas compart- olds for refilling (first stage) or
ments are fitted with their indi- lock-out alarm (second stage) can
vidual non-return filling valve and be mechanically set. The response
density monitor. Any pipe connec- characteristic is shown in the Mol-
tions to common sampling points lier diagramme. Density monitors
are therefore strictly avoided. Each can be easily removed for testing
compartment is also fitted with its with a separate calibration device.
own moisture absorber and pres-
sure relief.
18 Single-line and gas schematic diagramme Flange connections Gas density monitor
M
M M
Main technical data ELK-3
(g/dm ) (g/dm )
3 3
Pabs (kPa) Pabs (kPa)
60 56 52 60 56 52
1000 48 1000 48
46 46
a) a)
900 44 900 44
42 42
b) b)
40 40
800 c) 800 c)
38 38
36 36
700 34 700 34
32 32
30 30
a)
600 600
28 28
a)
26 26 b)
c)
500 24 500 24
b)
22 c) 22
20 20
400 400
18 18
16 16
300 14 300 14
t °C t °C
200 200
-50 -40 -20 0 20 40 60 80 100 -50 -40 -20 0 20 40 60 80 100