Sie sind auf Seite 1von 140

Project Integration Project Plan

Management Development

Why is historical
Integrated Change information useful
Control? in developing the
project plan?

Project Planning
Constraints
Methodology?

Work Authorization
Project Plan
System?

How is the project


plan used to in
Work Results?
integrated change
control?
Taking results of other The processes
planning processes required to ensure
and putting them into that various elements
a coherent, consistent of the project are
document. properly coordinated.

Because it helps
verify assumptions Coordinating
and assess changes across the
identified entire project.
alternatives.
Any structured
Factors that limit
approach to guide
the project
the project team in
management team's
the development of a
options.
project plan.
A formal procedure to A formal, approved
sanction project work
document used to
so that it is done at
the proper time and in manage and control
the proper sequence. project execution.

The project plan


Outcomes of
provides the
activities performed
baseline against
to accomplish the
which all changes
project.
are controlled.
What is required in
the decision Llife-Cycle Costing
making process?

Matrix
Line Manager
Organization?

Organization
Network Logic?
Planning

Parametric
Pareto Diagram
Estimating

Work Breakdown
Work Package
Structure
The concept of Analyzing the
including acquisition, problem to identify
operating, and disposal viable solutions and
costs when evaluating then making a choice
various alternatives. from among them.
Any organization structure in The manager of any
which the project manager group that actually
shares responsibility with the
makes a product or
functional managers for
assigning priorities and for performs a service.
directing the work of individuals Also called a functional
assigned to the project. manager.

Identifying, Any continuous


documenting, and
series of connected
assigning project roles,
responsibilities, and activities in a project
reporting relationships. network diagram.

A histogram, ordered by An estimating technique


frequency of that uses a statistical
occurrence, that shows relationship between
how many results were historical data and other
generate by each variables to calculate an
identified cause. estimate.

A task oriented structure that


organizes and defines total A deliverable at the
work to be accomplished in a lowest level of the Work
project. Each level represents Breakdown Structure. A
an increasingly detailed work package may be
definition of a project
component. divided into activities.
Critical Path
Float / Slack
Method(CPM)

Backward Pass Corrective Action

Budgeted Cost of
Work Scheduled Baseline
(BCWS)

Arrow Diagramming Administrative


Method (ADM) Closure

Backward Pass Activity


A network analysis technique The amount of time that an activity
used to predict project may be delayed from its early start
duration by analyzing which date without delaying the project
finish date. Float is a arithmetic
sequence of tasks has the calculation and can change as the
least amount of scheduling project progresses and changes
flexibility (i.e. the least amount are made to the project plan. Also
of float). called slack.

Changes made to The calculation of late finish


dates and late start dates for
bring expected future the uncompleted portions of all
performance of the network activities. Determined
by working backwards through
project into line with the network logic from the
the project plan. project's end date.

"The original plan (for a project, The sum of the approved cost
a work package, or an activity), estimates (including any
plus or minus approved overhead allocation) for
changes. Usually used with a activities (or portions of
modifier (e.g., cost baseline, activities) scheduled to be
schedule baseline, performance performed during a given period
measurement baseline)." (usually project-to-date).

A network diagramming technique in


which activities are represented by
"Generating, gathering, arrows. The tail of the arrow
and disseminating represents the start and the head
represents the finish of the activity.
information to formalize Activities are connected at points
called nodes to illustrate the sequence
project completion." in which the activities are expected to
be performed.

"An element of work performed The calculation of late finish dates and
during the course of a project. late start dates for the uncompleted
An activity normally has an portions of all network activities.
Determined by working backwards
expected duration, an expected through the network logic from the
cost, and expected resource project’s end date. The end date may
requirements. Activities are be calculated in a forward pass or set
often subdivided into tasks." by the customer or sponsor.
Activity Definition Activity Description

Activity Duration Cost of Work


Estimating Performed (ACWP)

Actual Finish Date Actual Start Date

Administractive
Application Area
Closure

Bar Chart Baseline


A short phrase or label Identifying the specific
used in a project network activities that must be
diagram. The activity
performed in order to
description normally
describes the scope of produce the various
work of the activity. project deliverables.

Estimating the
Total costs incurred
number of work
in accomplishing
periods which will be
work during a given
needed to complete
time period. individual activities.

The point in time The point in time


that work actually that work actually
started on an ended on an
activity. activity.

A category of projects that have


common elements not present "Generating, gathering,
in all projects. Application areas
and disseminating
are usually defined in terms of
either the product of the information to formalize
project. Application areas often project completion."
overlap.

"The original plan (for a project, "A graphic display of schedule-related


a work package, or an activity), information. In the typical bar chart,
plus or minus approved activities or other project elements are
listed down the left side of the chart,
changes. Usually used with a dates are shown across the top, and
modifier (e.g., cost baseline, activity durations are shown as
schedule baseline, performance date-placed horizontal bars. Also
measurement baseline)." called a Gantt chart."
Word Breakdown
Work Package
Structure

Total Quality
Workaround
Management (TQM)

Target Start Date Target Finish Date


(TS) (TF)

Time-Scaled
Team Development
Network Diagram

Target Completion
Successor Activity
Date (TC)
A deliverable-oriented
A deliverable at the
grouping of project
lowest level of the work
elements which
breakdown structure. A
organizes and defines
work package may be
the total scope of the
divided into activities.
project.

A common approach A response to a negative risk


to implementing a event. Distinguished from
contingency plan in that a
quality improvement workaround is not planned in
program within an advance of the occurrence of
organization. the risk event.

The date work is The date work is


planned (targeted) planned (targeted)
to finish on an to start on an
activity. activity.

Any project network diagram


Developing drawn in such a way that the
individual and group positioning and length of the
activity represents its
skills to enhance duration. Essentially, it is a
project performance. bar chart that includes
network logic.

(1) In the arrow An imposed date


diagramming method, the which constrains or
activity which departs a
node. (2) In the
otherwise modifies
precedence diagramming the network
method, the “to” activity. analysis.
Statement of Work
Subnet
(SOW)

Start Date Stakeholder

Staff Acquisition Source Selection

Solicitation What is Project


Planning Risk Management?

How is Monte Carlo What is the


analysis used in difference between
schedule a risk and a
simulations? problem?
A narrative A subdivision of a
description of project network
products or services diagram usually
to be supplied under representing some
contract. form of subproject.
Individuals and A point in time associated with
an activity’s start, usually
organizations who qualified by one of the
are involved in or following: actual, planned,
estimated, scheduled, early,
may be affected by late, target, baseline, or
project activities. current.

Getting the human


Choosing from resources needed
among potential assigned to and
contractors. working on the
project.
The process concerned with Documenting
identifying, analyzing, and
responding to project risk. It product
also includes maximizing the
results of positive events as well requirements and
as minimizing the consequences
of adverse events to project
identifying potential
objectives. sources.
A risk is a future To perform the project
event; it has not yet many times in order to
occurred. A problem, provide a statistical
on the other hand, distribution of the
currently exists. calculated results.
Should-Cost
Solicitation
Estimates

Scope Verification Scope Planning

Scope Change
Scope Definition
Control

Scope Change Scope

Scheduled Start Scheduled Finish


Date (SS) Date (SF)
An estimate of the cost of
a product or service used Obtaining
to provide an assessment quotations, bids,
of the reasonableness of a offers, or proposals
prospective contractor’s
proposed cost.
as appropriate.

Developing a written Ensuring that all


scope statement that identified project
includes the project
justification, the major deliverables have
deliverables, and the been completed
project objectives. satisfactorily.
Decomposing the major
Controlling deliverables into
smaller, more
changes to project manageable
scope. components to provide
better control.

The sum of the Any change to the


products and project scope. A scope
change almost always
services to be requires an adjustment
provided as a to the project cost or
project. schedule.

The point in time work was The point in time work was
scheduled to finish on an scheduled to start on an
activity. The scheduled finish activity. The scheduled start
date is normally within the date is normally within the
range of dates delimited by range of dates delimited by
the early finish date and the the early start date and the
late finish date. late start date.
Schedule
Schedule Variance
Performance Index
(SV)
(SPI)

Schedule
Schedule Control
Development

Risk Response
S-Curve
Development

What type of change


Risk Response constitutes one of
Control the major areas of
cost growth?

What are the


What is privity of
characteristics of a
contract?
well-written SOW?
(1) Any difference between
The ratio of work the scheduled completion
performed to work of an activity and the
scheduled actual completion of that
activity. (2) In earned
(BCWP/BCWS). value, BCWP less BCWS.

Analyzing activity
Controlling sequences, activity
changes to the durations, and resource
project schedule. requirements to create
the project schedule.

Defining Graphic display of cumulative costs,


labor hours, or other quantities,
enhancement steps plotted against time. The name derives
from the S-like shape of the curve
for opportunities and (flatter at the beginning and end,
steeper in the middle) produced on a
mitigation steps for project that starts slowly, accelerates,
and then tails off.
threats.

Responding to
Change to project changes in risk
scope. over the course of
the project.

The SOW shoulbe be A doctrine of law that


clear, complete, and recognizes the
concise and include a contractual relationship
description of any existing between a
collateral services buyer and its prime
required. contractor.
Risk Quantification Risk Identification

Risk Event Retainage

Responsibility
Assignment Matrix Resource Planning
(RAM)

Resource-Limited
Resource Leveling
Schedule

Request for
Reserve
Quotation (RFQ)
Determining which Evaluating the
risk events are probability of risk
likely to affect the event occurrence
project. and effect.

A portion of a contract
payment that is held A discrete
until contract occurrence that may
completion in order to affect the project for
ensure full performance better or worse.
of the contract terms.

Determining what A structure which relates the


resources (people, project organization structure
to the work breakdown
equipment, materials) structure to help ensure that
are needed in what each element of the project’s
quantities to perform scope of work is assigned to a
project activities. responsible individual.

Any form of network analysis in A project schedule whose


which scheduling decisions start and finish dates
(start and finish dates) are driven
reflect expected resource
by resource management
concerns (e.g., limited resource availability. The final
availability or difficult-to-manage project schedule should
changes in resource levels). always be resource-limited.

Generally, this term is A provision in the project plan to


mitigate cost and/or schedule risk.
equivalent to request for Often used with a modifier (e.g.,
proposal. However, in management reserve, contingency
reserve) to provide further detail on
some application areas it what types of risk are meant to be
mitigated. The specific meaning of the
may have a narrower or modified term varies by application
more specific meaning. area.
Request for Remaining Duration
Proposal (RFP) (RDU)

Quality Control
Quality Planning
(QC)

Quality Assurance Projectized


(QA) Organization

As a PMP, what laws,


regulations, and
Project Time
ethical standards
Management govern your
professional practice?

What is meant What are the two


when someone is ways project
said to be resources are
ethnocentric? obtained?
A type of bid document used
to solicit proposals from
The time needed to prospective sellers of
complete an products or services. In some
application areas it may have
activity. a narrower or more specific
meaning.

(1) The process of monitoring specific Identifying which


project results to determine if they
comply with relevant quality standards quality standards are
and identifying ways to eliminate
causes of unsatisfactory performance. relevant to the project
(2) The organizational unit that is
assigned responsibility for quality
and determining how
control. to satisfy them.
(1) The process of evaluating
Any organizational structure overall project performance on a
in which the project manager regular basis to provide
has full authority to assign confidence that the project will
priorities and to direct the satisfy the relevant quality
standards. (2) The organizational
work of individuals assigned
unit that is assigned responsibility
to the project. for quality assurance.

Those of the state or A subset of project management that


includes the processes required to
province and/or ensure timely completion of the
country where you project. It consists of activity
definition, activity sequencing, activity
provide project duration estimating, schedule
development, and schedule control.
management services.

A belief in the
Staff acquisition inherent superiority
and procurement. of one's own
culture.
What are the two
ways project Project Team
resources are Members
obtained?

Project Risk
Project Schedule
Management

Project
Project Quality
Procurement
Management
Management

Project Plan
Project Planning
Execution

Project Plan
Project Plan
Development
A subset of project management that
includes the processes required to
ensure that the project includes all of
the work required, and only the work
required, to complete the project
Staff acquisition
successfully. It consists of initiation,
scope planning, scope definition,
and procurement.
scope verification, and scope change
control.

A subset of project management The planned dates


that includes the processes
concerned with identifying, for performing
analyzing, and responding to
project risk. It consists of risk activities and the
identification, risk quantification,
risk response development, and
planned dates for
risk response control. meeting milestones.
A subset of project management that
A subset of project management
includes the processes required to that includes the processes
acquire goods and services from required to ensure that the
outside the performing organization. It project will satisfy the needs for
consists of procurement planning, which it was undertaken. It
solicitation planning, solicitation, consists of quality planning,
source selection, contract
quality assurance, and quality
administration, and contract close-out.
control.

Carrying out the


project plan by The development
performing the and maintenance of
activities included the project plan.
therein.
A formal, approved document used to
guide both project execution and Taking the results of
project control. The primary uses of the
project plan are to document planning
other planning
assumptions and decisions, to facilitate processes and putting
communication among stakeholders,
and to document approved scope, cost, them into a consistent,
and schedule baselines. A project plan
may be summary or detailed. coherent document.
Project Network
Project Phase
Diagram

Project Manager Project


(PM) Management Team

Project Project
Management Management
Software Professional (PMP)

Project
Management Body Project
of Knowledge Management (PM)
(PMBOK)

Project Integration
Project Life Cycle
Management
Any schematic display of the A collection of logically
logical relationships of project related project activities,
activities. Always drawn from
left to right to reflect project
usually culminating in
chronology. Often incorrectly the completion of a
referred to as a “PERT chart.” major deliverable.

The members of the project team


who are directly involved in
project management activities.
The individual
On some smaller projects, the responsible for
project management team may
include virtually all of the project managing a project.
team members.

An individual A class of computer


certified as such by applications specifically
designed to aid with
the Project planning and controlling
Management project costs and
Institute. schedules.
An inclusive term that describes the sum of
The application of knowledge, knowledge within the profession of project
management. As with other professions
skills, tools, and techniques such as law, medicine, and accounting, the
toproject activities in order to body of knowledge rests with the
meet or exceed stakeholder practitioners and academics who apply and
advance it. The PMBOK includes proven,
needs and expectations from traditional practices which are widely
a project. applied as well as innovative and advanced
ones which have seen more limited use.

A collection of generally
A subset of project management that
includes the processesrequired to
sequential project phases
ensure that the various elements of whose name and number are
the project are properly coordinated. determined by the control
It consists of project plan needs of the organization or
development, project plan execution,
and overall change control. organizations involved in the
project.
Project Human
Project Cost
Resource
Management
Management

Project
Communications Project Charter
Management

Program Evaluation
Project and Review
Technique (PERT)

Procurement
Program
Planning

Predecessor Precedence
Activity Relationship
A subset of project management A subset of project management
that includes the processes that includes the processes
required to ensure that the required to make the most
project is completed within the effective use of the people
approved budget. It consists of involved with the project. It
resource planning, cost consists of organizational
estimating, cost budgeting, and planning, staff acquisition, and
cost control. team development.

A document issued by senior A subset of project management that


management that provides includes the processes required to
the project manager with the ensure proper collection and
dissemination of project information. It
authority to apply consists of communications planning,
organizational resources to information distribution, performance
reporting, and administrative closure.
project activities.

An event-oriented network analysis


technique used to estimate project
A temporary
duration when there is a high degree
of uncertainty with the individual
endeavor
activity duration estimates. PERT
applies the critical path method to a
undertaken to create
weighted average duration estimate.
Also given as Program Evaluation and
a unique product or
Review Technique. service.
A group of related
Determining what projects managed in a
coordinated way.
to procure and Programs usually
when. include an element of
ongoing activity.
The term used in the precedence
diagramming method for a
(1) In the arrow
logical relationship. In current diagramming method, the
usage, however, precedence activity which enters a
relationship, logical relationship, node. (2) In the precedence
and dependency are widely used diagramming method, the
interchangeably regardless of
the diagramming method in use. “from” activity.
Precedence
Diagramming PERT Chart
Method (PDM)

Performing Performance
Organization Reporting

Percent Complete
Path Convergence
(PC)

Path Pareto Diagram

Parametric Overall Change


Estimating Control
A network diagramming
technique in which activities are
A specific type of represented by boxes (or
project network nodes). Activities are linked by
precedence relationships to
diagram. show the sequence in which the
activities are to be performed.

Collecting and The enterprise


disseminating whose employees
information about
project performance to are most directly
help ensure project involved in doing the
progress. work of the project.
In mathematical analysis, An estimate, expressed
the tendency of parallel as a percent, of the
paths of approximately amount of work which
equal duration to delay the has been completed on
completion of the an activity or group of
milestone where they meet. activities.

A histogram, ordered by
frequency of A set of sequentially
occurrence, that shows connected activities
how many results were in a project network
generated by each diagram.
identified cause.

An estimating technique that


uses a statistical relationship
Coordinating between historical data and
changes across the other variables (e.g., square
footage in construction, lines of
entire project. code in software development)
to calculate an estimate.
Organizational
Organizational
Breakdown
Planning
Structure (OBS)

Node Network Path

Network Logic Network Analysis

Near-Critical Monte Carlo


Activity Analysis

Modern Project
Monitoring
Management (MPM)
A depiction of the Identifying,
project organization documenting, and
arranged so as to assigning project roles,
relate work packages responsibilities,and
to organizational units. reporting relationships.

One of the defining points of a


Any continuous network; a junction point
series of connected joined to some or all of the
other dependency lines. See
activities in a project also arrow diagramming
network diagram. method and precedence
diagramming method.

The process of The collection of


identifying early and activity
late start and finish
dates for the dependencies that
uncompleted portions of make up a project
project activities. network diagram.

A schedule risk assessment


technique that performs a
project simulation many times
An activity that has
in order to calculate a low total float.
distribution of likely results.

A term used to distinguish the The capture,


current broad range of project analysis, and
management (scope, cost,
time, quality, risk, etc.) from reporting of project
narrower, traditional use that performance, usually
focused on cost and time. as compared to plan.
Mitigation Milestone Schedule

Milestone Matrix Organization

Management
Master Schedule
Reserve

Loop Start-to-finish

Start-to-start Finish-to-finish
A summary-level Taking steps to lessen
schedule which risk by lowering the
probability of a risk
identifies the major event’s occurrence or
milestones. See also reducing its effect
master schedule. should it occur.

Any organizational structure in


which the project manager A significant event in
shares responsibility with the
functional managers for
the project, usually
assigning priorities and for completion of a
directing the work of individuals
assigned to the project.
major deliverable.

A separately planned quantity used to


allow for future situations which are
A summary-level
impossible to predict. Management
reserves may involve cost or schedule.
schedule which
Management reserves are intended to
reduce the risk of missing cost or
identifies the major
schedule objectives. Use of
management reserve requires a
activities and key
change to the project’s cost baseline. milestones.
A network path that passes
the “from” activity the same node twice. Loops
must start before cannot be analyzed using
traditional network analysis
the “to” activity can techniques such as CPM and
PERT. Loops are allowed in
finish GERT.

the “from” activity the “from” activity


must finish before must start before
the “to” activity can the “to” activity can
finish start
The four possible
Finish-to-start types of logical
relationships

Logical
Line Manager
Relationship

Why is the type of


organizational When is the project
structure important team directory
in project developed?
management?

Which type of Which type of


power should a power should a
project manager project manager
avoid? use?

What is the highest


What are the five
level of need's in
methods of dealing
Maslow's hierarchy
with conflict?
of needs?
Finish-to-start, the “from” activity
Finish-to-finish, must finish before
Start-to-start, the “to” activity can
Start-to-finish start

(1) The manager of any A dependency


group that actually between two project
makes a product or activities, or between
performs a service. (2) a project activity and
A functional manager. a milestone.
The structure of the
As part of the staff organization often
constrains the
acquisition phase availability under which
of the project. resources become
available to the project.

Should try to use


Avoid using
reward and expert
coercive power.
powers.

Self-fulfillment through Smoothing,


the development of Withdrawl,
powers and skills, and Compromise,
a chance to use Forcing and Problem
creativity. Solving
What use does a
Smoothing Gantt Chart
provide?

What is life-cycle What is a variable


costing? cost?

How is the cost


Define what a
performance index
payback period is?
(CPI) figured?

What is internal What is BCWS or


rate of return (IRR)? PV?

How is schedule
What are direct
variance (SV)
costs?
figured?
To identify when a Deemphasizing the
particular resource opponents' differences
is (or will be) and emphasizing their
working on a commonalities over
particular task. the issues in question.

The concept of
Costs that rise including acquisition,
directly with the operating, and disposal
size of the project. costs when evaluating
various alternatives.

The number of times periods


up to the point at which
cumulative revenues exceed CPI = BCWP /ACWP
cumulative costs and, or EV / AC
therefore, the project has
turned a profit.

The percentage rate


Budgeted cost of that makes the present
work scheduled or value of costs equal to
planned value. the present value of
benefits.

Costs incurred
SV = BCWP - BCWS
directly by a
or EV - PV
specific project.
Level of Effort
Lead
(LOE)

Late Finish Date


Late Start Date (LS)
(LF)

Invitation for Bid


Lag
(IFB)

Information
Initiation
Distribution

Hanger Hammer
A modification of a logical Support-type activity (e.g.,
relationship which allows an vendor or customer liaison) that
acceleration of the successor does not readily lend itself to
task. For example, in a measurement of discrete
finish-to-start dependency with a accomplishment. It is generally
10-day lead, the successor characterized by a uniform rate
activity can start 10 days before of activity over a specific period
the predecessor has finished. of time.

In the critical path method, the In the critical path method, the
latest possible point in time latest possible point in time
that an activity may be that an activity may begin
completed without delaying a without delaying a specified
specified milestone (usually milestone (usually the project
the project finish date). finish date).

Generally, this term is A modification of a logical


relationship which directs a
equivalent to request for delay in the successor task. For
proposal. However, in example, in a finish-to-start
some application areas it dependency with a 10-day lag,
the successor activity cannot
may have a narrower or start until 10 days after the
more specific meaning. predecessor has finished.

Making needed
Committing the
information available
organization to
to project
begin a project
stakeholders in a
phase.
timely manner.

An aggregate or summary An unintended break in


activity (a group of related a network path. Hangers
activities is shown as one and are usually caused by
reported at a summary level). missing activities or
A hammock may or may not missing logical
have an internal sequence. relationships.
Graphical
Evaluation and
Grade
Review Technique
(GERT)

Functional
Functional Manager
Organization

Free Float (FF) Forward Pass

Fixed Price
Float Incentive Fee (FPIF)
Contract

Firm Fixed Price


Finish Date
(FFP) Contract
A category or rank used to
distinguish items that have the A network analysis technique
same functional use (e.g., that allows for conditional and
“hammer”) but do not share the probabilistic treatment of
same requirements for quality logical relationships (i.e.,
(e.g., different hammers may some activities may not be
need to withstand different
performed).
amounts of force).

A manager responsible for An organization structure in


which staff are grouped
activities in a specialized hierarchically by specialty (e.g.,
department or function production, marketing,
(e.g., engineering, engineering, and accounting at
the top level; with engineering,
manufacturing, further divided into mechanical,
marketing). electrical, and others).

The amount of time an


The calculation of the
activity can be delayed
early start and early
without delaying the
finish dates for the
early start of any
uncompleted portions of
immediately following
all network activities.
activities.

A type of contract where the The amount of time that an activity


buyer pays the seller a set may be delayed from its early start
amount (as defined by the without delaying the project finish
date. Float is a mathematical
contract), and the seller can calculation and can change as the
earn an additional amount if it project progresses and changes are
meets defined performance made to the project plan. Also called
criteria. slack, total float, and path float.

A point in time associated with A type of contract where


an activity’s completion. the buyer pays the seller
Usually qualified by one of the
a set amount (as defined
following: actual, planned,
estimated, scheduled, early, by the contract)
late, baseline, target or regardless of the seller’s
current. costs.
Expected Monetary
Fast Tracking
Value

Exception Report Event-on-Node

Estimate To Estimate At
Complete (ETC) Completion (EAC)

Estimate Effort

Early Start Date


Earned Value (EV)
(ES)
The product of an event’s Compressing the project
probability of occurrence and the schedule by overlapping
gain or loss that will result. For activities that would normally
example, if there is a 50 percent
probability that it will rain, and rain
be done in sequence, such as
will result in a $100 loss, the design and construction.
expected monetary value of the Sometimes confused with
rain event is $50 (.5 x $100). concurrent engineering.

A network diagramming Document that


technique in which events are
represented by boxes (or nodes) includes only major
connected by arrows to show
the sequence in which the variations from plan
events are to occur. Used in the
original Program Evaluation and
(rather than all
Review Technique. variations).
The expected total cost of an activity, a
The expected additional cost
group of activities, or of the project when
the defined scope of work has been needed to complete an activity, a
completed. Most techniques for group of activities, or the project.
forecasting EAC include some adjustment Most techniques for forecasting
of the original cost estimate based on ETC include some adjustment to
project performance to date. Also shown as
“estimated at completion.” Often shown as
the original estimate based on
EAC = Actuals-to-date + ETC. project performance to date.

An assessment of the likely quantitative


The number of labor units result. Usually applied to project costs and
required to complete an durations and should always include some
indication of accuracy (e.g., ± x percent).
activity or other project Usually used with a modifier (e.g.,
element. Usually expressed as preliminary, conceptual, feasibility). Some
application areas have specific modifiers
staffhours, staffdays, or that imply particular accuracy ranges (e.g.,
staffweeks. Should not be order-of-magnitude estimate, budget
estimate, and definitive estimate in
confused with duration. engineering and construction projects).

(1) A method for measuring project


In the critical path method, the earliest performance. It compares the amount of work
possible point in time on which the that was planned with what was actually
uncompleted portions of an activity (or accomplished to determine if cost and schedule
performance is as planned. See also actual cost
the project) can start, based on the
of work performed, budgeted cost of work
network logic and any schedule scheduled, budgeted cost of work performed,
constraints. Early start dates can cost variance, cost performance index, schedule
change as the project progresses and variance, and schedule performance index. (2)
changes are made to the project plan. The budgeted cost of work performed for an
activity or group of activities.
Early Finish Date Duration
(EF) Compression

Duration Dummy Activity

Deliverable Data Date

Current Start Date Current Finish Date

Critical Path
Critical Path
Method (CPM)
Shortening the project In the critical path method, the earliest
possible point in time on which the
schedule without reducing uncompleted portions of an activity (or
the project scope. Duration the project) can finish based on the
compression is not always network logic and any schedule
constraints. Early finish dates can
possible and often requires change as the project progresses and
an increase in project cost. changes are made to the project plan.

An activity of zero duration used to


show a logical relationship in the The number of work periods (not
arrow diagramming method. Dummy including holidays or other
activities are used when logical non-working periods) required to
relationships cannot be completely or complete an activity or other project
correctly described with regular element. Usually expressed as
activity arrows. Dummies are shown workdays or workweeks. Sometimes
graphically as a dashed line headed by incorrectly equated with elapsed time.
an arrow.

Any measurable, tangible, verifiable


The point in time that outcome, result, or item that must be
separates actual produced to complete a project or part
of a project. Often used more narrowly
(historical) data from in reference to an external deliverable,
future (scheduled) data. which is a deliverable that is subject to
approval by the project sponsor or
Also called as-of date. customer.

The current estimate The current estimate


of the point in time of the point in time
when an activity will when an activity will
be completed. begin.

A network analysis technique used to


In a project network diagram, the series of
predict project duration by analyzing which
activities which determines the earliest
sequence of activities (which path) has the
completion of the project. The critical path will
least amount of scheduling flexibility (the
generally change from time to time as activities
least amount of float). Early dates are
are completed ahead of or behind schedule.
calculated by means of a forward pass
Although normally calculated for the entire
using a specified start date. Late dates are
project, the critical path can also be determined
calculated by means of a backward pass
for a milestone or subproject. The critical path is
starting from a specified completion date
usually defined as those activities with float less
(usually the forward pass’s calculated
than or equal to a specified value, often zero.
project early finish date).
Critical Activity Crashing

Cost Plus Incentive


Cost Variance (CV)
Fee (CPIF) Contract

Cost Plus Fixed Fee Cost Performance


(CPFF) Contract Index (CPI)

Cost of Quality Cost Estimating

Cost Control Cost Budgeting


Taking action to decrease the Any activity on a critical path.
total project duration after Most commonly determined by
analyzing a number of using the critical path method.
Although some activities are
alternatives to determine how
“critical” in the dictionary sense
to get the maximum duration without being on the critical path,
compression for the least this meaning is seldom used in
cost. the project context.

A type of contract where the (1) Any difference


buyer reimburses the seller between the estimated
for the seller’s allowable costs
cost of an activity and the
(allowable costs are defined
by the contract), and the seller actual cost of that
earns its profit if it meets activity. (2) In earned
defined performance criteria. value, BCWP less ACWP.
The ratio of budgeted costs to
actual costs (BCWP/ACWP). CPI A type of contract where the
is often used to predict the buyer reimburses the seller
magnitude of a possible cost for the seller’s allowable
overrun using the following costs (allowable costs are
formula: original cost defined by the contract) plus a
estimate/CPI = projected cost at
fixed amount of profit (fee).
completion.

The costs incurred to


Estimating the cost ensure quality. The cost
of the resources of quality includes
needed to complete quality planning, quality
control, quality
project activities.
assurance, and rework.

Allocating the cost


Controlling
estimates to
changes to the
individual project
project budget.
components.
Corrective Action Control Charts

Control Contract Close-out

What are the 3


Contract general types of
contracts?

Fixed price or lump Cost reimbursable


sum contracts contracts

Contingency
Unit price contracts
Reserve
Control charts are a graphic Changes made to
display of the results, over
time and against established bring expected
control limits, of a process. future performance
They are used to determine if
the process is “in control” or of the project into
in need of adjustment. line with the plan.
Completion and The process of comparing
actual performance with
settlement of the planned performance, analyzing
contract, including variances, evaluating possible
alternatives, and taking
resolution of all appropriate corrective action as
outstanding items. needed.

Fixed price or lump A contract is a mutually


sum contracts, Cost binding agreement which
obligates the seller to
reimbursable provide the specified
contracts, Unit price product and obligates the
contracts buyer to pay for it.
This type of contract involves payment
(reimbursement) to the contractor for its actual costs. This type of contract involves a
Costs are usually classified as direct costs (costs
incurred directly by the project, such as wages for fixed total price for a well-defined
members of the project team) and indirect costs product. Fixed price contracts
(costs allocated to the project by the performing
organization as a cost of doing business, such as may also include incentives for
salaries for corporate executives). Indirect costs are meeting or exceeding selected
usually calculated as a percentage of direct costs.
Cost reimbursable contracts often include incentives project objectives such as
for meeting or exceeding selected project objectives schedule targets.
such as schedule targets or total cost.

A separately planned With this type of contract the


quantity used to allow for contractor is paid a preset amount per
unit of service (e.g., $70 per hour for
future situations which professional services or $1.08 per
cubic yard of earth removed) and the
may be planned for only total value of the contract is a function
in part (sometimes called of the quantities needed to complete
the work.
“known unknowns”).
Do you include
Why would you use
contingency
contingency
reservers in the
reserves?
schedule baseline?

Are contingency
reservers only used Contingency
when dealing with Planning
costs?

Concurrent Communications
Engineering Planning

Code of Accounts Chart of Accounts

Change Control
Calendar Unit
Board (CCB)
Contingency reserves Yes, contingency
are intended to reserves are normally
reduce the impact of included in the
missing cost or project’s cost and
schedule objectives. schedule baselines.

The development of a
management plan that
No, contingency
identifies alternative reserves may
strategies to be used to involve cost,
ensure project success if
specified risk events occur. schedule, or both.

Determining the An approach to project


staffing that, in its most
information and general form, calls for
communications implementors to be involved
in the design phase.
needs of the project Sometimes confused with fast
stakeholders. tracking.

Any numbering system used to


monitor project costs by
Any numbering
category (e.g., labor, supplies, system used to
materials). The project chart of
accounts is usually based upon uniquely identify each
the corporate chart of accounts element of the work
of the primary performing
organization. breakdown structure.

The smallest unit of time used in A formally constituted


scheduling the project. Calendar group of stakeholders
units are generally in hours, responsible for
days, or weeks, but can also be
in shifts or even in minutes. Used approving or rejecting
primarily in relation to project changes to the project
management software.
baselines.
Budgeted Cost of Budgeted Cost of
Work Scheduled Work Performed
(BCWS) (BCWP)

Budget At
Baseline
Completion (BAC)

Bar Chart Gantt chart

Arrow Diagramming
Backward Pass
Method (ADM)

Arrow Application Area


The sum of the approved cost The sum of the approved cost
estimates (including any estimates (including any
overhead allocation) for overhead allocation) for
activities (or portions of activities (or portions of
activities) completed during a activities) scheduled to be
given period (usually performed during a given period
project-to-date). (usually project-to-date).

The original plan (for a project,


a work package, or an activity),
plus or minus approved The estimated total
changes. Usually used with a cost of the project
modifier (e.g., cost baseline,
schedule baseline, performance when done.
measurement baseline).

A graphic display of schedule-related A graphic display of schedule-related


information. In the typical bar chart, information. In the typical bar chart,
activities or other project elements are activities or other project elements are
listed down the left side of the chart, listed down the left side of the chart,
dates are shown across the top, and dates are shown across the top, and
activity durations are shown as activity durations are shown as
date-placed horizontal bars. Also date-placed horizontal bars. Also
called a Bar chart. called a Gantt chart.

A diagramming technique in which


The calculation of late finish dates and
activities are represented by arrows.
late start dates for the uncompleted
The tail of the arrow represents the
portions of all network activities.
start and the head represents the
Determined by working backwards
finish of the activity. Activities are
through the network logic from the
connected at points called nodes to
project’s end date. The end date may
illustrate the sequence in which the
be calculated in a forward pass or set
activities are expected to be
by the customer or sponsor.
performed.

A category of projects that


have common elements not
present in all projects. The graphic
Application areas are usually presentation of an
defined in terms of either the
product of the project or the activity.
type of customer.
Is stakeholder What is the triple
managerment a constraint and what
proactive task? is it used for?

What is
What is meant by
Social-Econominc
the word
Environmental
internationalization?
Sustainability?

Should you
incorporate What does the
stakeholders' initiating process
requirements into a do?
project?

What is the meant


What is down in the
by the planning
executing process?
process?

What is done in the


What is done in the
controlling
closing process?
process?
The triple constraint is
time, cost, quality. It is Yes, stakeholder
used to identify the three
most important factors that management is a
a project manager needs to proactive task.
consider in a project.

Being accountable Consideration of


for impacts resulting time-zone differences,
national and regional
from a project both holidays. travel
social and requirements, and other
economic. logistical issues.

Yes, always
incorporate the
It authorizes the
stakeholder's
project of phase.
requirements into
the project.

During this phase This process is used


people are coordinating for defining and
with other resources to refining objectives
carry out the project and selecting the best
phase or plan. of the alternatives.

This process is when This process is for ensuring


formailizing acceptance that project objectives are met
by monitoring and measuring
of the project or phase progress in order to indetify
is completed in the variances from the plan so
hopes of bringing it to that corrective action can be
an orderly end. taken if and when necessary.
In a strong matrix
what type of
What is a tight
power/authority
matrix?
does the project
manager have?

In a weak matrix
does the project
Project Coordinator
manager have much
authority?

What are some


advantages/benefits
Project Expeditor
of a functional
organization?

What are some Is scope verification


disadvantages of a necessary when a
functional project is
organization? terminated?

Will management
by objectives work
Dephi Technique
if management
doesn't support it.
This refers to
In this type of
locating the offices
matrix the power
for the project team
rests with the
in the same
project manager. room/location.
An individual who reports to a
higher-level manager in the No, the
organization, has the authority to
assign work to individuals in power/authority
various functional organizations,
and shares authoity and
rests with the
resources with the functional functional manager.
manager.

1) Easier management o An individual who is a staff


specialist's, 2) Team assistant to an executive who
memebers only report to 1 has the ultimate responsibility
for the project. Has authority
boss, 3) Clearly defined only in his managers department
careeer paths, 4) but not over resources from
resources are centralized. other departments.

Yes, scope verifcation is 1) The project manager


necessary when a project has NO authority, 2)
is terminated, it People place more
althoughs the emphasis on their
organization to determine speciality than to the
the level of completion. project.

A mthod to obtain opinions on


issues. Information sent to No, in orer to work
experts, responses are compiled
and the results are sent back for
properly, it must be
further review. Using the delphi supported by
technique helps reduce bias and
undue influence. management.
What type of What are the three
diagram uses uses for dummy
dummy activities? activites?

What is the What is problem


expectancy theory? solving/confrontation?

Give three examples


of hygiene factors in
What is McGregor's
Herzberg's theory of
motivation. How do Theory X?
they affect motivation.

What is an
What is McGregor's organizational
theory Y? breakdown
structure (OBS)?

Does the matrix form


What is the purpose of project
of a resource Gantt organization facilitate
chart? or complicate project
team development?
1) logic, 2) time
delay and, 3) Activity-On-Arrow
uniqueness. Network.

Addressing conflict directly by It holds that people tend to be


getting the parties to work highly productive and
together to define the
motivated if they believe their
problem, collect information,
develop and analyze efforts will lead to successful
alternatives, and select the results and they will be
most appropriate alternative. rewarded for their success.

Pay, attitude of supervisor, and


Traditional approach: workers working conditions.
stroy motivation,
are self-centered, lazy, lacking
but improving hygiene factors in not
ambition. Managers organize likely to increase motivation.
the elements of the Motivators are an opportunity to
productive enterprise in the achieve and experience
interest of economic ends. self-actualization.

A specific type of Workers are not by nature


resistant to organizational
organizational chart needs; they are willing and
that shows which eager to accept
responsibilities and are
units are responsible concerned with self-growth
for which work items and fulfillment.

It complicates team
development because It identifies when a
team members are particular resource
accountable to both a is or will be working
functional manager and on a particular task.
a project manager.
Name three major
What is a
forms of project
projectized
organizational
organization?
structure.

Describe the
What is a project
difference between
"war room" and
a weak matrix and a
what is its benefit?
strong matrix.

What is variance What is active


analysis? listening?

What is major
What is most
cause of conflict
difficult conflict to
with functional
deal with?
managers?

What is earned value


What is the tool for
analysis and how is
used for
it used in
communication
performance
planning?
reporting?
One in which a separate,
functional organization
is established for each Functional, Matrix,
project. Personnel are and Projectized
assigned on a full-time
basis.

A single location for the team to Weak matrices are similar to


get together for any purpose. It functional organizations.
provides a repository for project
Strong matrices are similar to
artifacts, records, and
up-to-date schedules and status projectized organizations
reports. It gives an identity to (with balance of power tipped
the project team. toward the project manager)

Listening in which the Comparing actual


recipient is attentive project results to
planned or expected
and asks for results in terms of cost,
clarification of schedule, scope, quality,
ambiguous messages and risk.

Personality
Schedules
conflicts

An analysis that
integrates cost and
Stakeholder schedule measures. It is
analysis used to help the project
management team assess
project performance.
5 Phases of Project
Initiation Phase Activities
Management

Planning Phase Core Planning Phase


Processes Facilitating Processes

Activity Activity aspects

Activity definition Activity description

Activity Duration
Activity-On-Arrow
Estimating
Initiation - Planning -
Initiation Execution - Control -
Closure

Quality Planning - Scope Planning - Scope


Communicaiton Planning - Risk Definition - Activity Definition -
Activity Sequencing - Activity
ID - Risk Quantification - Risk
Duration Estimating - Resource
Response Devlp -
Planning - Cost Estimating -
Organizational Planning - Staff Schedule Development - Cost
Acquisition - Procurement Budgeting - Project Plan
Planning - Solicitation Planning Development

Duration - Expected cost


Element of work on a
- Expected resources
project
required

Identifying specific
The scope of work of the activities that must be
activity. - Used in project performed in order to
diagrams. produce a project's
deliverables.

Estimating the number of


Part of the Arrow work periods that will be
Diagramming Method needed to complete
individual activities.
Actual Cost of Work
Activity-On-Node
Performed

Actual Finish Date Actual Start Date

Administrative Closure Application Area

Arrow Diagramming
Arrow
Method

As-Of Date Backward Pass


Total costs incurred
Part of the Precedence
(direct and indirect) for a
Diagramming Method
project.

When work starts. When work ends.

Type of: product, project


or customer. - There is Formalized project end.
often overlap

Graphical representation
of a project where Graphic presentation of
activities are represented an activity.
by arrows.

Calculating a project
Same as Data Date
length based on end-date
Bar Chart Baseline

Baseline Finish Date Baseline Start Date

Budget at Completion Budget Estimate

Budget Cost of Work Budgeted Cost of Work


Performed Scheduled

Calendar Unit Change Control Board


Left side = Project
elements Bottom = Date
The original plan
range (Also called =
GANTT Chart)

Scheduled Start Date Scheduled Finish Date

The estimated total cost


Estimate
of the project when done.

Sum of approved cost


Sum of approved cost
estimates not yet
estimates completed.
completed. Part of
Part of Earned Value
Earned Value

Group of stakeholders
responsible for Smaller unit (Hours -
approving or rejecting Days - Weeks - Shifts -
changes in the project Minutes)
baseline.
Change in Scope Chart of Accounts

Charter Code of Accounts

Communications
Concurrent Engineering
Planning

Contingency Planning Contingency Reserve

Contract - 3 Categories Contract Definition


Numbering system used
to monitor project costs Scope Change
by category.

Numbering system used


to identify each element
Same as project charter
of the work breakdown
structure.

Not Fast Tracking - Calls


Determining the
for project
communication needs
implementations to be
and procedures for each
involved in the Design
stakeholder.
Phase.

Known Unknowns. They


are buffers (cost,
schedules, resources) Risk mitigation plan
built into the project
baseline.

1 - Fixed price or lump


Mutually binding sum. 2 - Cost
agreement. reimbursable. 3 - Unit
price
Contract - Fixed
Contract - 2 Parts
price/Lump Sum

Contract - Cost
Contract - Unit Price
reimbursable

Contract Administration Contract Close-out

Control Control Chart

Corrective Action Cost Budgeting


Seller - delivers product
Fixed price for a
or service. Buyer -
well-defined product or
obliged to pay for
service.
product or service.

Seller is paid a pre-set


price for unit of product
Time and materials.
or service (i.e. $70 per
hour)

Managing the
Completion of the
relationship with the
contract.
seller.

Graphical display of Comparing planned vs.


results. actual performance.

Allocating cost estimates Used to get a project


to the actual project. back on track.
Cost control. Cost Estimating

Cost Performance Index


Cost of Quality
= Formula

Project Cost at
Cost Performance Index
Compellation

Cost Plus Fixed Fee Cost Plus Inventive Fee


Contract Contract

Cost Variance Crashing


Controlling changes in
Estimating project costs
the project budget.

Cost incurred to ensure


CPI = BCWP / ACWP
quality.

Used to predict the


PCC = Original Cost Est. /
magnitude of a project
CPI
cost overrun.

Time and Materials +


Time and Materials + a
fixed profit level if all
fixed profit level.
goals are met.

BCWP < ACWP


Taking action to
Difference between
decrease a project
estimated and actual
timeline.
cost.
Critical Activity Critical Path Method

Current Finish Date Current Start Date

Data Date Deliverable

Dependency Dummy Activity

Duration Duration Compressing


The path with the least
Critical Path Method
amount of flexibility.

Current estimate of Current estimate of


project initiation. project completion

As-Of-Date. Point of time


Tangible and verifiable
that is between historical
outcome.
and future date.

Zero length. Place holder


Requires another step to
activities in a project
be accomplished.
schedule.

Shorten duration without


Length of time to
decreasing project
complete an activity.
scope.
Early Finish Date Early Start Date

Earned Value Effort

Estimate Estimate at Completion

Estimate to Complete Event-on-Node

Exception Report Expected Monetary Value


Used in the Critical Path
Used in the Critical Path
Method. Earliest date the
Method. Earliest date the
project can be completed
project can be started by.
by.

1 - Method for measuring


Not Duration. Resource project performance. 2 -
units needed to complete Budgeted cost. 3 -
an activity. Compares work planned
vs. actually performed.

Prediction of costs,
EAC = Actuals-to-date +
resources needed and
ETC
duration.

Project diagramming Expected additional cost


method that uses needed to complete an
connected boxes. activity.

Document which show


Monetary gain or lose
only major variations to
due to an event.
the project plan.
Fast Tracking Finish Date

Fixed Price Incentive Fee


Firm Fixed Price Contract
Contract

Float Forecast Final Cost

Forward Pass Fragnet

Free Float Functional Manager


Compressing a project
Project activities schedule by overlapping
completed date. activities. Not =
Concurrent Engineering

Fixed price, regardless of


Fixed price with a bonus
changes in Time and
for performance.
Material costs.

Amount of time an
activity can be delayed
EST
without affecting the
project schedule.

Calculating a project
Subnet time-line based on a
start-date.

Amount of time an
Specialized department
activity can be delayed
manager (i.e. Marketing
without affecting an early
Mgr.)
start of a project.
Functional Organization Gantt Chart

Graphical Evaluation and


Grade
Review Technique

Hammock Hanger

Information Distribution Initiation

Integrated Cost/Schedule
Invitation for Bid
Reporting
Department (i.e.
Bar chart Marketing Dept) grouped
staff.

Cartoon representation Items in the same


of a Conditional category but require
evaluation of a problem. different quality controls.

Break in the project path


- missed activities in the Summary/roll-up activity
plan.

Committing the Distributing necessary


organization to begin a information to project
project phase. stakeholders

Request for Proposal Earned Value


Key Event Schedule Lag

Late Finish Date Late Start Date

Lead Level of Effort

Life-Cycle Costing Line Manager

Link Logic Diagram


A step in the project path
must wait X days after its
Master Schedule
predecessor is
completed.

Latest possible date a


Latest possible date a
task can be completed
task can begin without
without delaying the
delaying the schedule.
schedule.

A step in the project path


Estimate of resources
which can start X days
needed to complete the
before its predecessor is
task.
completed.

Acquisition - Operating -
A manager who is also
Disposal costs.
working directly on the
Considered when
project.
evaluating alternatives.

Project Network Diagram Connection of steps


Logical Relationships (4
Finish-to-Start Activity
Types)

Finish-to-Finish Activity Finish-to-Start Activity

Finish-to-Start Activity Loop

Management Reserve Master Schedule

Matrix Organization Milestone


Finish-to-start /
The FROM activity must
Finish-to-finish /
FINISH before the TO
Start-to-start /
activity can START.
Start-to-finish

The FROM activity must The FROM activity must


START before the TO FINISH before the TO
activity can FINISH. activity can FINISH.

The FROM activity must


Cannot be in CPM or
START before the TO
PERT. Can be in GERT
activity can FINSH.

Cost and schedule


Summary-level schedule buffers planned by
that identifies key management for unseen
milestones. events that would impact
the project.

Project and Functional


Significant event. managers share
responsibilities.
Modern Project
Mitigation
Management

Monitoring Monte Carlo Analysis

Near-Critical Activity Network Analysis

Network Logic Network Path

Organizational
Node
Breakdown Structure
Broad / Not focused on
cost and time / Focused Steps to lessen risk by
on: scope, cost, time lowering probability.
quality, risk, etc.

Simulation of Risk that Tracking and reporting


occurs throughout the project performance and
project. status.

The process of
identifying early and late
An activity that has low
finish dates for the
total float.
uncompleted portions of
project activities.

A collection of
Connected activities in
dependencies that make
the project network
up the project network
diagram.
diagram.

A depiction of the project


A junction point in a
into work breakdown
project network diagram.
"packages".
Organizational Planning Overall Change Control

Parametric Estimating Pareto Diagram

Path Path Convergence

Percent Complete Performance Reporting

Precedence
Performing Organization
Diagramming Method
Identifying, documenting
and assigning project
Coordinating changes
roles, responsibilities
across the entire project.
and reporting
relationships.

Histogram ordered by
frequency of occurrence
Estimates based on
that shows multiple
statistics and history.
results relating to one
cause.

Parallel paths that lead to


one milestone, but may
Sequential activities.
singularly delay a
project.

Collecting and
disseminating
Percent of work already
information about project
performed.
performance to help
ensure project progress.

Activities are The enterprise whose


represented by boxes employees are most
and linked sequentially. directly involved in doing
A diagramming method. the work of the project.
Precedence Relationship Predecessor Activity

Procurement Planning Program

Program Evaluation and


Project
Review Technique

Project Communications
Project Charter
Management

Project Cost Project Human Resource


Management Management
1 - Arrow Diagramming
Method - Activity which
enters a NODE. / 2 -
Refers to the
Precedence Diagramming
Method - Activity which diagramming methods.
goes "away from" the
NODE.

A group of related
Determining what to
projects. Usually
procure and when.
on-going.

Event-oriented. Used to
A temporary endeavor
estimate project
undertaken to create a
duration. Used for
unique product or
projects with uncertainly
service.
in duration.

Sr. Management's written


Subset project for
authority given to the PM
collecting and dispersing
for organization
project info.
resources.

Subset project for Subset project for


effectively using ensuring a project is
personnel in the project. completed within budget.
Project Integration
Project Life Cycle
Management

Project Management
Project Management
Body of Knowledge

Project Management Project Management


Software Professional

Project Management
Project Manager
Team

Project Network Diagram Project Phase


Subset project for
A collection of sequential
integrating subset
project phases.
projects into the whole.

The knowledge, skills,


tools and techniques to
Book of proven project meet and exceed a
management practices. stakeholders
expectations with a
project.

Computer application
Certified PM from PMI designed to plan and
control a project.

Individual responsible for Members of the project


managing the project. team.

PERT or GANTT
A subset collection of
Schematic display of
project activities.
project activities.
Project Plan Project Plan - Elements

Is a Project Plan Project Plan


Summary or Detailed? Development

Project Plan Execution Project Planning

Project Procurement Project Quality


Management Management

Project Risk Management Project Schedule


Plan / Cost Assumptions
Formal document used
/ Schedule / Decisions /
to guide the project.
Scope

Taking the results of


other planning processes
Can be both
and putting them into a
new document.

Development and
Carrying out the project
maintenance of the
plan details.
project plan.

Subset of the project Acquiring goods and


used to ensure the services outside of the
project is up to project team for use in
requirements at delivery. the project.

Outlines dates for each Subset of the project for


activity in sequential identifying and mitigating
order. risks.
Project Scope
Project Team Members
Management

Project Time
Projectized Organization
Management

Quality Assurance Quality Control

Quality Planning Remaining Duration

Request for Proposal Request for Quotation


Subset of the project
used to ensure only the
They work for the Project
pre-defined work
Manager
required is done and no
more.

Subset of the project that


Where PM has 100% over
monitors and ensures a
project team. No shared
team meeting all
authority.
milestone dates.

Process of evaluating Evaluating process to


specific project steps to ensure the project will
verify they meet with the satisfy its quality
project quality standards. standards.

Identifying which quality


Time needed to complete
standards are relevant to
an activity.
the project.

Bid document from a


Bid document from
company to a vendor for
company to vendor.
pricing information.
Reserve Resource Leveling

Resource-Limited
Resource Planning
Schedule

Responsibility
Retainage
Assignment Matrix

Risk Event Risk Identification

Risk Quantification Risk Response Control


Where scheduling
Provision in the project
concerns are addressed
plan to mitigate cost
by resource management
and/or schedule risks.
concerns.

Project where start and


Resource identification
end date are based on
process.
resource availability.

Relates project
Down payment on a
organization structure to
contracted product or
work breakdown
service.
structure.

An occurrence that
Identifying which risks
affects the projects
will affect the project.
outcome.

Responding to changes
Identifying probability of
in risk over the course of
the risk.
the project.
Risk Response
S-Curve
Development

Schedule Control Schedule Development

Schedule Performance
Schedule Variance
Index

Scheduled Finished Date Scheduled Start Date

Scope Scope Change


Graph showing
cumulative cost and Risk mitigation plan
labor over time.

Analyzing activity
sequences, durations
Controlling changes to
and resource
the project schedule
requirements to create a
project schedule.

Difference between Work performed / Work


scheduled and actual Schedule (BCWP /
timeframes. BCWS)

Planned activity start


Planned activity end date
date

The sum of the products


Any change to the scope. and services to be
provided as a project.
Scope Change Control Scope Definition

Scope Planning Scope Verification

Should-Cost Estimate Slack

Solicitation Solicitation Planning

Source Selection Staff Acquisition


Decomposing the major
Controlling changes in
deliverables into small
the scope.
parts.

Auditing each scope


Written scope
element at the end of a
statements.
project for completion.

Used to judge the


Used in PERT for FLOAT reasonableness of a
vendors quote.

Document stating
requirements and Obtaining quotes, bids
potential sources to meet and offers.
those requirements.

Getting human resources Choosing a vendor or


to work on the project. product.
Stakeholder Start Date

Statement of Work Subnet

Successor Activity Target Completion Date

Time-Scaled Network
Team Development
Diagram

Target Finish Date Target Start Date


People directly or
Qualified starting date indirectly involved in the
project.

A narrative description of
products or services to
Subproject
be supplied under
contract.

A constraining date in Activity while "leaves"


the project diagram. the node.

Diagram where the


physical shape of each Developing team
activity object is members to enhance the
proportional to the project.
duration of that activity.

The date the work for the The date the work for the
activity is planned to be activity is planned to be
started by. completed by.
How is performance
How is contract closeout
reporting used as a tool
similar to administrative
for contract
closeout?
administration?

When are payment Describe the


requests an output of characteristics of a
contract administration? unilateral contract?

Under what two conditions


must PMI members refrain
What is a unilateral from offering or accepting
contract? monetary payments or other
forms of compensation or
tangible benefits?

What is the most critical


culture for the success of Who can initiate an
a project manager ethics complaint?
working internationally?

When is a PMP What are the two


responsible for reporting conditions under which
to PMI possible PMI member's do not have
violations of the PMP to honor and maintain the
Code of Professional privacy and confidentiality
Conduct? of client information?
Both contract closeout and
it provides management administrative closure
with information about involve product verification.
how effectively the seller However, the contract terms
is achieving the and conditions may prescribe
contractual objectives. specific procedures for
contract closeout.

It usually takes the form


of a purchase order -- a When the project is using
standard form listing an external payment
routine items at standard system.
prices.

When payments do not


conform with applicable
A contract that has only
laws and when they may
one signature (the
provide an unfair
advantage for themselves issuer).
or their business.

Any person, group, or


organization, including Leadership
PMI.

1) if granted permission by
the customer, client, or
When reasonable and
employer, and 2) If
clear facts exist to verify
maintaining the
confidentiality is otherwise the violation.
unethical or unlawful.
What is the best way to
demonstrate a
What is the purpose of
professional and
the procurement
cooperative manner with
management plan?
team members or other
stakeholders?

What are two outputs What is a procurement


from contract closeout? audit? How is it used?

During which process are


the impact and likelihood of
identified risks assessed so How is expected
that they may be prioritized monetary value
according to their potential computed?
effect on project
objectives?

What action should the


project manager take to
What is a SWOT analysis ensure that each risk
and how is it used? response plan is
implemented and
monitored?

What type of contract


What are five success
documentation should be
factors for doing
reviewed in contract
business internationally?
closeout?
To describe how solicitation
planning, solicitation, By respecting cultural,
source selection, contract ethnic and personal
administration, and contract differences.
closeout will be managed.

A comprehensive analysis and


review of the process from
procurement planning through The contract file, and
contract administration. It is formal acceptance and
used to identify successes and closure.
failures, which can be applied as
lessons learned to other projects.

Expected monetary value is


the product of two numbers:
risk event probability
(probability risk will occur) Qualitative risk analysis
and risk event value (estimate
if it does happen, the loss
that will be incurred).

Identify and assign an A strengths, weakness,


individual to own each risk opportunities, and threats
who will take personal analysis. Used in risk
responsibility for protecting identification, it tends to
the project objectives from increase the number of
the risk's impact. project risks considered.

1) Cultural The contract itself and all


associated schedules, requested
understanding, 2) and approved contract changes,
Cross-cultural journeys, seller developed technical
3) Good communication, documentation, seller
performance reports, financial
4) Negotiation, and 5) documents, and contract-related
Global management inspection reports
What is the difference
In which project phase is
between attribute
quality control
sampling and variable
performed?
sampling?

What is the difference What are the three (3) key


between a tolerance and outputs from
a control limit? administrative closure?

Name three
Name five barriers to
communications
effective project
channels in an
communications.
organization?

Why is communications
planning so tightly linked
What is active listening?
to project organizational
planning?

What is earned value


analysis and how is it List the four parts of the
used in performance communication model.
reporting?
Attribute sampling determines
whether the result does or does
Quality control is not conform to the specifications.
performed throughout all In variable sampling, the result is
phases of the project life rated on a continuous scale that
measures the degree of
cycle. conformance within a
pre-established acceptable range.

A tolerance establishes
1) Project archives, 2) the range of acceptable
Project closure, 3) results. A control limit is
Lessons learned. computed based on the
results themselves.

1) Lack of clear communication


channels. 2) Physical distance
between communicator and
Personal, Organization, receiver, 3) Difficulties with
Grapevine technical language, 4)
Distracting environmental
factors, 5) Detrimental attitudes.

Because the project's


Listening in which the
organizational structure
recipient is attentive and
will have a major effect
asks for clarification of
on project
ambiguous messages.
communications.

An analysis that integrates


cost and schedule
Communicator, Message, measures. It is used t help
Medium, Recipient the project management
team assess project
performance.
What is the difference When should EAC be
between a risk and a calculated by AC + BAC -
problem? EV?

When should EAC be What does the


calculated by AC + (BAC benefit-cost ratio not tell
- EV) / CPI? you?

if a project is experiencing
quality problems, should What are the seven (7)
the project manager main quality control
devote more resources to tools, often called the
inspection of to "basic seven" tools?
prevention?

does the matrix form of


project organization Project Human Resource
facilitate or complicate Management comprises
project team which three processes?
development? Why?

How is simulation used At which phase(s) in the


in activity duration project life cycle is
estimating and what is significant risk thought
the most common type of to have the greatest
simulation? impact?
When current variances
are seen as atypical, and A risk is a future event; it
the project management has not yet occurred. A
team's expectation is that problem, on the other
similar variances will not hand, currently exists.
occur in the future.

When the current


The absolute value of the variances are seen as
benefit or cost. typical of future
variances.

1) Flowcharts, 2)
Diagrams, 3) Pareto Prevention, because
Diagram, 4) preventing a problem is
Cause-and-Effect Diagram, far less costly, than
5) Graphs, 6) Control fixing a problem.
Charts, 7) Checklists

It complicates project
1) Organizational team development.
planning, 2) Staff Because team members
acquisition, 3) Team are accountable to both a
development functional manager and
the project manager.

To calculate multiple durations with


different sets of assumptions.
Project execution and Monte Carlo Analysis, in which a
distribution of probable results is
closeout. defined for each activity and used to
calculate a distribution of probable
results for the total project.
Project Plan Execution Project Plan
- Inputs Development - Tools

Project Plan Execution Integrated Change


- Tools Control - Inputs

Integrated Change
Initiation - Inputs
Control - Tools

Initiation - Tools Scope Planning - Tools

Scope Planning - Scope Definition -


Inputs Tools
Project planning Project plan,
methodology, stakeholder supporting details,
skills & knowledge, project
management information
organizational policies,
system (PMIS), earned preventive action,
value management (EVM) corrective action

General management skills,


Project plan, product skills & knowledge,
work authorization system,
performance reports, project management
change requests information system (PMIS),
and organization procedures

Change control system,


Product description, configuration management,
strategic plan, project performance measurements,
selection criteria, and additional planning, and
historical information project management
information system (PMIS)

Product analysis,
benefit/cost analysis. Project selection
alternative methods, expert
identification and judgement
expert judgement

Product description,
WBS templates and project charter,
decomposition constraints, and
assumptions
Scope Definition - Scope Verification -
Inputs Tools

Scope Verification - Scope Change Control


Input - Tools

Scope Change Control Activity Definition -


- Inputs Tools

Activity Definition - Activity Sequencing -


Inputs Inputs

Activity Sequencing - Project Plan


Tools Development - Input
Scope statement,
constraints,
Inspection assumptions, other
planning outputs, and
historical information

Scope change control Work results, product


system, performance documentation, WBS,
measurement, and scope statement and
additional planning project plan

WBS, performance
Decomposition and reports, change
templates requests, and scope
management plan

Activity list, product WBS, scope statement,


description, mandatory historical information,
dependencies, discretionary constraints,
dependencies, external assumptions, and
dependencies and milestones
expert judgement

Precedence Diagram
Other planning outputs,
Method (PDM), Arrow
historical information,
Diagram Method (ADM),
organizational policies,
conditional diagram
constraints,
techniques and network
assumptions
templates
Schedule Development
Cost Control - Input
- Inputs

Activity Duration Schedule Development


Estimating - Inputs - Tools

Schedule Control - Schedule Control -


Tools Inputs

Resource Planning - Resource Planning -


Tools Inputs

Cost Estimating - Cost Estimating -


Tools Inputs
Project network diagrams,
Cost baseline, activity duration estimates,
performance reports, resource requirements, resource
pool descriptions, calendars,
change requests, and constraints, assumptions, leads
cost management plan and lags, risk management plan,
and activity attributes

Mathematical analysis, Activity list, constraints,


duration compression, assumptions, resource
simulation, resource requirements, resource
leveling heuristics, project capabilities, historical
management software, information and
and coding structure identified risks

Project schedule, Schedule change control


software, performance
performance reports,
measurements, additional
change requests, and
planning, project
schedule management management software,
plan and variance analysis

WBS, historical Expert judgment,


information, scope alternatives
statement, resource pool
description, organizational
identification, and
policies, and activity project management
duration estimates software

WBS, resource requirements, Analogous estimating,


resource rates, activity parametric modeling,
duration estimates, estimating bottom-up estimating,
publications, historical computerized tools, and
information, chart of other cost estimating
accounts, and risks methods
Cost Budgeting - Tools Cost Budgeting - Tools

Activity Duration
Cost Control - Tools
Estimating - Inputs

Quality Planning - Quality Assurance -


Tools Tools

Quality Assurance -
Quality Control - Tools
Inputs

Quality Control - Quality Planning -


Inputs Input
Cost estimates, WBS,
Cost estimating tools
project schedule, and
& techniques
risk management plan

Expert judgment, Cost change control


system, performance
analogous estimating,
measurements, earned
quantitative based
value management,
durations, and reserve additional planning, and
time (contingency) computerized tools

Benefit/cost analysis,
Quality planning tools benchmarking, flow
and techniques, and charting, design of
quality audits experiments, cost of
quality

Inspection, control Quality management


charts, Pareto diagrams,
plan, quality control
statistical sampling,
measurements, and
flow charting, and trend
analysis operational definitions

Quality policy, scope


Work results, quality
statement, product
management plan,
description, standards
operational definitions,
and regulations, and
and checklists
other process inputs
Organization Planning Staff Acquisition -
- Inputs Tools

Staff Acquisition - Team Development -


Inputs Tools

Team Development - Communication


Inputs Planning - Tools

Communications Information
Planning - Inputs Distribution - Tools

Information Performance
Distribution - Inputs Reporting - Tools
Negotiations, Project interfaces,
pre-assignment, and staffing requirements,
procurement and constraints

Team building activities, Staffing management


general management
plan, staffing pool
skills, reward and
descriptions, and
recognition systems,
collocation, and training recruitment practices

Project staff, project


plan, staffing
Stakeholder analysis management plan,
performance reports,
and external feedback

Communication skills, Communications


information retrieval requirements,
systems, and communications
information technology, constraints,
distribution systems and assumptions

Performance reviews,
variance analysis, trend Work results,
analysis, earned value communications
analysis, and management plan, and
information distribution project plan
tools
Administrative Closure Administrative Closure
- Inputs - Tools

Performance Risk Management


Reporting - Inputs Planning - Inputs

Risk Management Risk Identification -


Planning - Tools Tools

Risk Identification - Qualitative Risk


Inputs Analysis - Tools

Qualitative Risk Organizational


Analysis - Input Planning - Tools
Performance
Performance reporting
measurement
tools, project reports,
documents, product
and project
documentation, and
presentations
other project records

Project charter, organizational


risk management policies,
defined roles and Project plan, work
responsibilities, stakeholder results, and other
risk tolerance, organization's project records
risk management templates,
and the WBS

Documentation review,
information gathering
techniques, checklists,
Planning Meetings
assumptions analysis,
and diagramming
techniques

Risk probability and Risk management


impact, probability/impact plan, project planning
risk rating matrix, project outputs, risk
assumptions testing, and categories, and
data precision ranking historical information

Templates, human Risk management plan,


identified risks, project
resource practices,
status, project type, data
organizational theory,
precision, scales of
and stakeholder probability and impact,
analysis and assumptions
Risk Monitoring & Quantitative Risk
Control Tools Analysis - Inputs

Procurement Planning Risk Monitoring and


- Tools Control - Inputs

Solicitation Planning -
Solicitation - Tools
Inputs

Solicitation Planning - Procurement Planning


Tools - Inputs

Source Selection -
Solicitation - Inputs
Inputs
Risk management plan, Project risk response audits,
identified risks, list of periodic project risk reviews,
prioritized risks, list of risks
earned value analysis,
for additional analysis,
historical information, expert technical performance
judgment, and other planning measurements, and additional
outputs risk response planning

Risk management plan,


risk response plan, project Make of buy analysis,
communication, additional
expert judgment, and
risk identification and
analysis, and scope contract type selection
changes

Procurement
management plan, Bidders conferences,
statement of work, and and advertising
other planning outputs

Procurement Planning Standard forms and


- Inputs expert judgment

Proposals, evaluation Procurement


criteria, and documents, and
organizational policies qualified seller lists
Source Selection - Quality Control -
Tools Outputs

Contract Close-out - Contract Close-out -


Inputs Tools

Contract Contract
Administration - Inputs Administration - Tools

Project Plan Execution Organizational


- Outputs Planning - Outputs

Project Plan Quantitative Risk


Development - Outputs Analysis - Tools
Quality improvement,
Contract negotiation,
acceptance decisions,
weighting system,
rework, completed
screening system, and
checklists, and
independent estimates
process adjustments

Contract
Procurement Audits
Documentation

Contract change
Contract, work results,
control systems,
change requests, and
performance reporting,
seller invoices
and payment systems

Role and responsibility


assignments, staffing
Work results, and
management plan,
change requests
oganization charts,
and supporting details

Interviewing,
sensitivity analysis, Project plan, and
decision tree analysis, supporting details
and simulation
Schedule Development Quantitative Risk
- Outputs Analysis - Outputs

Activity Duration Qualitative Risk


Estimating - Outputs Analysis - Outputs

Activity Sequencing - Risk Identification -


Outputs Outputs

Activity Definition - Risk Management


Outputs Planning - Output

Scope Change Control Administrative Closure


- Outputs - Outputs
Prioritized list of quantified Project schedule,
risks, probabilistic analysis of
the project, probability of supporting detail,
achieving the cost and time schedule management
objectives, and trends in plan, an resource
quantitative risk analysis
results requirement updates

Overall risk ranking for the


project, list of prioritized risk, Activity duration
list of risks for additional estimates, basis of
analysis and management, estimates, and activity
trends in qualitative risk list updates
analysis results

Risks, triggers, and Project network


inputs to other diagrams, and activity
processes list updates

Activity list, supporting


details, and work
Risk Management Plan
breakdown structure
updates

Scope changes,
Project archives,
corrective action,
project closure,
lessons learned, and
lessons learned
adjusted baselines
Scope Verification - Performance
Outputs Reporting - Outputs

Scope Definition - Information


Outputs Distribution - Outputs

Scope Planning - Communication


Output Planning - Output

Team Development -
Initiation - Outputs
Output

Integrated Change Staff Acquisition -


Control - Output Outputs
Performance reports,
Formal Acceptance
and change requests

Project records, Work breakdown


project reports, and structure, and scope
project presentations statement updates

Scope statement,
Communications supporting details,
management plan scope management
plan

Performance Project charter, project


improvements, and manager identified and
inputs to performance assigned, constraints,
appraisals and assumptions

Project staff assigned, Project plan updates,


and project team corrective action, and
directory lessons learned
Resource Planning - Risk Monitoring and
Output Control - Outputs

Schedule Control - Risk Response


Outputs Planning - Outputs

Schedule Development Risk Response


- Outputs Planning - Outputs

Risk Response Risk Response


Planning - Inputs Planning - Tools

Contract
Contract Close-out -
Administration -
Outputs
Output
Workaround plans, corrective
action, project change
requests, updates to risk Resource
response plan, risk database, requirements
and updates to risk
identification checklists

Risk response plan, residual


risks, secondary risks,
contractual agreements, Schedule updates,
contingency reserve amount corrective action, and
needed, inputs to other lessons learned
processes, and inputs to a
revised project plan

Risk response plan, residual Project schedule,


risks, secondary risks,
contractual agreements, supporting detail,
contingency reserve amounts schedule management
needed, Inputs to other plan, and resource
processes, and inputs to a
revised project plan requirements updates

Risk management plan, list of


Avoidance, prioritized risks, risk ranking of the
project, prioritized list of quantified
transference, risks, probabilistic analysis of the
project, list of potential responses, risk
mitigation, and thresholds, risk owners, common risk
acceptance causes, trends in quality and
quantitative analysis results

Correspondence, Contract file, and


contract changes, and formal acceptance and
payment requests closure
Quality Planning - Source Selection -
Output Output

Cost Control - Outputs Solicitation - Output

Cost Budgeting - Solicitation Planning -


Outputs Outputs

Cost Estimating - Procurement Planning


Outputs - Outputs

Quantitative Risk
Analysis - Outputs
Quality management
plan, operational
Contract definitions, checklists,
and inputs to other
processes

Revised cost estimates,


budget updates,
corrective action,
Proposals
estimate at completion,
project closeout, and
lessons learned

Procurement
documents, evaluation
Cost baseline
criteria, and statement
of work updates

Procurement Cost estimates,


management plan, and supporting detail, and
statements of work cost management plan

Prioritized list of quantified


risks, Probabilistic analysis
of the project, Probability of
achieving the cost & time
objectives, trends in
quantitative risk
Total Quality
Total Float
Management

Work Breakdown
Workaround
Structure

Work Breakdown
Work Item
Structure
Quality improvement
Float
program.

Deliverable oriented
approach. / Project An alternative risk
elements are rolled up mitigation plan. Leaves
into larger project Risk in place.
deliverables.

Lowest level deliverable.


/ May be divided into Activity
activities.

Das könnte Ihnen auch gefallen