Beruflich Dokumente
Kultur Dokumente
Management Development
Why is historical
Integrated Change information useful
Control? in developing the
project plan?
Project Planning
Constraints
Methodology?
Work Authorization
Project Plan
System?
Because it helps
verify assumptions Coordinating
and assess changes across the
identified entire project.
alternatives.
Any structured
Factors that limit
approach to guide
the project
the project team in
management team's
the development of a
options.
project plan.
A formal procedure to A formal, approved
sanction project work
document used to
so that it is done at
the proper time and in manage and control
the proper sequence. project execution.
Matrix
Line Manager
Organization?
Organization
Network Logic?
Planning
Parametric
Pareto Diagram
Estimating
Work Breakdown
Work Package
Structure
The concept of Analyzing the
including acquisition, problem to identify
operating, and disposal viable solutions and
costs when evaluating then making a choice
various alternatives. from among them.
Any organization structure in The manager of any
which the project manager group that actually
shares responsibility with the
makes a product or
functional managers for
assigning priorities and for performs a service.
directing the work of individuals Also called a functional
assigned to the project. manager.
Budgeted Cost of
Work Scheduled Baseline
(BCWS)
"The original plan (for a project, The sum of the approved cost
a work package, or an activity), estimates (including any
plus or minus approved overhead allocation) for
changes. Usually used with a activities (or portions of
modifier (e.g., cost baseline, activities) scheduled to be
schedule baseline, performance performed during a given period
measurement baseline)." (usually project-to-date).
"An element of work performed The calculation of late finish dates and
during the course of a project. late start dates for the uncompleted
An activity normally has an portions of all network activities.
Determined by working backwards
expected duration, an expected through the network logic from the
cost, and expected resource project’s end date. The end date may
requirements. Activities are be calculated in a forward pass or set
often subdivided into tasks." by the customer or sponsor.
Activity Definition Activity Description
Administractive
Application Area
Closure
Estimating the
Total costs incurred
number of work
in accomplishing
periods which will be
work during a given
needed to complete
time period. individual activities.
Total Quality
Workaround
Management (TQM)
Time-Scaled
Team Development
Network Diagram
Target Completion
Successor Activity
Date (TC)
A deliverable-oriented
A deliverable at the
grouping of project
lowest level of the work
elements which
breakdown structure. A
organizes and defines
work package may be
the total scope of the
divided into activities.
project.
Scope Change
Scope Definition
Control
The point in time work was The point in time work was
scheduled to finish on an scheduled to start on an
activity. The scheduled finish activity. The scheduled start
date is normally within the date is normally within the
range of dates delimited by range of dates delimited by
the early finish date and the the early start date and the
late finish date. late start date.
Schedule
Schedule Variance
Performance Index
(SV)
(SPI)
Schedule
Schedule Control
Development
Risk Response
S-Curve
Development
Analyzing activity
Controlling sequences, activity
changes to the durations, and resource
project schedule. requirements to create
the project schedule.
Responding to
Change to project changes in risk
scope. over the course of
the project.
Responsibility
Assignment Matrix Resource Planning
(RAM)
Resource-Limited
Resource Leveling
Schedule
Request for
Reserve
Quotation (RFQ)
Determining which Evaluating the
risk events are probability of risk
likely to affect the event occurrence
project. and effect.
A portion of a contract
payment that is held A discrete
until contract occurrence that may
completion in order to affect the project for
ensure full performance better or worse.
of the contract terms.
Quality Control
Quality Planning
(QC)
A belief in the
Staff acquisition inherent superiority
and procurement. of one's own
culture.
What are the two
ways project Project Team
resources are Members
obtained?
Project Risk
Project Schedule
Management
Project
Project Quality
Procurement
Management
Management
Project Plan
Project Planning
Execution
Project Plan
Project Plan
Development
A subset of project management that
includes the processes required to
ensure that the project includes all of
the work required, and only the work
required, to complete the project
Staff acquisition
successfully. It consists of initiation,
scope planning, scope definition,
and procurement.
scope verification, and scope change
control.
Project Project
Management Management
Software Professional (PMP)
Project
Management Body Project
of Knowledge Management (PM)
(PMBOK)
Project Integration
Project Life Cycle
Management
Any schematic display of the A collection of logically
logical relationships of project related project activities,
activities. Always drawn from
left to right to reflect project
usually culminating in
chronology. Often incorrectly the completion of a
referred to as a “PERT chart.” major deliverable.
A collection of generally
A subset of project management that
includes the processesrequired to
sequential project phases
ensure that the various elements of whose name and number are
the project are properly coordinated. determined by the control
It consists of project plan needs of the organization or
development, project plan execution,
and overall change control. organizations involved in the
project.
Project Human
Project Cost
Resource
Management
Management
Project
Communications Project Charter
Management
Program Evaluation
Project and Review
Technique (PERT)
Procurement
Program
Planning
Predecessor Precedence
Activity Relationship
A subset of project management A subset of project management
that includes the processes that includes the processes
required to ensure that the required to make the most
project is completed within the effective use of the people
approved budget. It consists of involved with the project. It
resource planning, cost consists of organizational
estimating, cost budgeting, and planning, staff acquisition, and
cost control. team development.
Performing Performance
Organization Reporting
Percent Complete
Path Convergence
(PC)
A histogram, ordered by
frequency of A set of sequentially
occurrence, that shows connected activities
how many results were in a project network
generated by each diagram.
identified cause.
Modern Project
Monitoring
Management (MPM)
A depiction of the Identifying,
project organization documenting, and
arranged so as to assigning project roles,
relate work packages responsibilities,and
to organizational units. reporting relationships.
Management
Master Schedule
Reserve
Loop Start-to-finish
Start-to-start Finish-to-finish
A summary-level Taking steps to lessen
schedule which risk by lowering the
probability of a risk
identifies the major event’s occurrence or
milestones. See also reducing its effect
master schedule. should it occur.
Logical
Line Manager
Relationship
How is schedule
What are direct
variance (SV)
costs?
figured?
To identify when a Deemphasizing the
particular resource opponents' differences
is (or will be) and emphasizing their
working on a commonalities over
particular task. the issues in question.
The concept of
Costs that rise including acquisition,
directly with the operating, and disposal
size of the project. costs when evaluating
various alternatives.
Costs incurred
SV = BCWP - BCWS
directly by a
or EV - PV
specific project.
Level of Effort
Lead
(LOE)
Information
Initiation
Distribution
Hanger Hammer
A modification of a logical Support-type activity (e.g.,
relationship which allows an vendor or customer liaison) that
acceleration of the successor does not readily lend itself to
task. For example, in a measurement of discrete
finish-to-start dependency with a accomplishment. It is generally
10-day lead, the successor characterized by a uniform rate
activity can start 10 days before of activity over a specific period
the predecessor has finished. of time.
In the critical path method, the In the critical path method, the
latest possible point in time latest possible point in time
that an activity may be that an activity may begin
completed without delaying a without delaying a specified
specified milestone (usually milestone (usually the project
the project finish date). finish date).
Making needed
Committing the
information available
organization to
to project
begin a project
stakeholders in a
phase.
timely manner.
Functional
Functional Manager
Organization
Fixed Price
Float Incentive Fee (FPIF)
Contract
Estimate To Estimate At
Complete (ETC) Completion (EAC)
Estimate Effort
Critical Path
Critical Path
Method (CPM)
Shortening the project In the critical path method, the earliest
possible point in time on which the
schedule without reducing uncompleted portions of an activity (or
the project scope. Duration the project) can finish based on the
compression is not always network logic and any schedule
constraints. Early finish dates can
possible and often requires change as the project progresses and
an increase in project cost. changes are made to the project plan.
Contingency
Unit price contracts
Reserve
Control charts are a graphic Changes made to
display of the results, over
time and against established bring expected
control limits, of a process. future performance
They are used to determine if
the process is “in control” or of the project into
in need of adjustment. line with the plan.
Completion and The process of comparing
actual performance with
settlement of the planned performance, analyzing
contract, including variances, evaluating possible
alternatives, and taking
resolution of all appropriate corrective action as
outstanding items. needed.
Are contingency
reservers only used Contingency
when dealing with Planning
costs?
Concurrent Communications
Engineering Planning
Change Control
Calendar Unit
Board (CCB)
Contingency reserves Yes, contingency
are intended to reserves are normally
reduce the impact of included in the
missing cost or project’s cost and
schedule objectives. schedule baselines.
The development of a
management plan that
No, contingency
identifies alternative reserves may
strategies to be used to involve cost,
ensure project success if
specified risk events occur. schedule, or both.
Budget At
Baseline
Completion (BAC)
Arrow Diagramming
Backward Pass
Method (ADM)
What is
What is meant by
Social-Econominc
the word
Environmental
internationalization?
Sustainability?
Should you
incorporate What does the
stakeholders' initiating process
requirements into a do?
project?
Yes, always
incorporate the
It authorizes the
stakeholder's
project of phase.
requirements into
the project.
In a weak matrix
does the project
Project Coordinator
manager have much
authority?
Will management
by objectives work
Dephi Technique
if management
doesn't support it.
This refers to
In this type of
locating the offices
matrix the power
for the project team
rests with the
in the same
project manager. room/location.
An individual who reports to a
higher-level manager in the No, the
organization, has the authority to
assign work to individuals in power/authority
various functional organizations,
and shares authoity and
rests with the
resources with the functional functional manager.
manager.
What is an
What is McGregor's organizational
theory Y? breakdown
structure (OBS)?
It complicates team
development because It identifies when a
team members are particular resource
accountable to both a is or will be working
functional manager and on a particular task.
a project manager.
Name three major
What is a
forms of project
projectized
organizational
organization?
structure.
Describe the
What is a project
difference between
"war room" and
a weak matrix and a
what is its benefit?
strong matrix.
What is major
What is most
cause of conflict
difficult conflict to
with functional
deal with?
managers?
Personality
Schedules
conflicts
An analysis that
integrates cost and
Stakeholder schedule measures. It is
analysis used to help the project
management team assess
project performance.
5 Phases of Project
Initiation Phase Activities
Management
Activity Duration
Activity-On-Arrow
Estimating
Initiation - Planning -
Initiation Execution - Control -
Closure
Identifying specific
The scope of work of the activities that must be
activity. - Used in project performed in order to
diagrams. produce a project's
deliverables.
Arrow Diagramming
Arrow
Method
Graphical representation
of a project where Graphic presentation of
activities are represented an activity.
by arrows.
Calculating a project
Same as Data Date
length based on end-date
Bar Chart Baseline
Group of stakeholders
responsible for Smaller unit (Hours -
approving or rejecting Days - Weeks - Shifts -
changes in the project Minutes)
baseline.
Change in Scope Chart of Accounts
Communications
Concurrent Engineering
Planning
Contract - Cost
Contract - Unit Price
reimbursable
Managing the
Completion of the
relationship with the
contract.
seller.
Project Cost at
Cost Performance Index
Compellation
Prediction of costs,
EAC = Actuals-to-date +
resources needed and
ETC
duration.
Amount of time an
activity can be delayed
EST
without affecting the
project schedule.
Calculating a project
Subnet time-line based on a
start-date.
Amount of time an
Specialized department
activity can be delayed
manager (i.e. Marketing
without affecting an early
Mgr.)
start of a project.
Functional Organization Gantt Chart
Hammock Hanger
Integrated Cost/Schedule
Invitation for Bid
Reporting
Department (i.e.
Bar chart Marketing Dept) grouped
staff.
Acquisition - Operating -
A manager who is also
Disposal costs.
working directly on the
Considered when
project.
evaluating alternatives.
Organizational
Node
Breakdown Structure
Broad / Not focused on
cost and time / Focused Steps to lessen risk by
on: scope, cost, time lowering probability.
quality, risk, etc.
The process of
identifying early and late
An activity that has low
finish dates for the
total float.
uncompleted portions of
project activities.
A collection of
Connected activities in
dependencies that make
the project network
up the project network
diagram.
diagram.
Precedence
Performing Organization
Diagramming Method
Identifying, documenting
and assigning project
Coordinating changes
roles, responsibilities
across the entire project.
and reporting
relationships.
Histogram ordered by
frequency of occurrence
Estimates based on
that shows multiple
statistics and history.
results relating to one
cause.
Collecting and
disseminating
Percent of work already
information about project
performed.
performance to help
ensure project progress.
Project Communications
Project Charter
Management
A group of related
Determining what to
projects. Usually
procure and when.
on-going.
Event-oriented. Used to
A temporary endeavor
estimate project
undertaken to create a
duration. Used for
unique product or
projects with uncertainly
service.
in duration.
Project Management
Project Management
Body of Knowledge
Project Management
Project Manager
Team
Computer application
Certified PM from PMI designed to plan and
control a project.
PERT or GANTT
A subset collection of
Schematic display of
project activities.
project activities.
Project Plan Project Plan - Elements
Development and
Carrying out the project
maintenance of the
plan details.
project plan.
Project Time
Projectized Organization
Management
Resource-Limited
Resource Planning
Schedule
Responsibility
Retainage
Assignment Matrix
Relates project
Down payment on a
organization structure to
contracted product or
work breakdown
service.
structure.
An occurrence that
Identifying which risks
affects the projects
will affect the project.
outcome.
Responding to changes
Identifying probability of
in risk over the course of
the risk.
the project.
Risk Response
S-Curve
Development
Schedule Performance
Schedule Variance
Index
Analyzing activity
sequences, durations
Controlling changes to
and resource
the project schedule
requirements to create a
project schedule.
Document stating
requirements and Obtaining quotes, bids
potential sources to meet and offers.
those requirements.
Time-Scaled Network
Team Development
Diagram
A narrative description of
products or services to
Subproject
be supplied under
contract.
The date the work for the The date the work for the
activity is planned to be activity is planned to be
started by. completed by.
How is performance
How is contract closeout
reporting used as a tool
similar to administrative
for contract
closeout?
administration?
1) if granted permission by
the customer, client, or
When reasonable and
employer, and 2) If
clear facts exist to verify
maintaining the
confidentiality is otherwise the violation.
unethical or unlawful.
What is the best way to
demonstrate a
What is the purpose of
professional and
the procurement
cooperative manner with
management plan?
team members or other
stakeholders?
Name three
Name five barriers to
communications
effective project
channels in an
communications.
organization?
Why is communications
planning so tightly linked
What is active listening?
to project organizational
planning?
A tolerance establishes
1) Project archives, 2) the range of acceptable
Project closure, 3) results. A control limit is
Lessons learned. computed based on the
results themselves.
if a project is experiencing
quality problems, should What are the seven (7)
the project manager main quality control
devote more resources to tools, often called the
inspection of to "basic seven" tools?
prevention?
1) Flowcharts, 2)
Diagrams, 3) Pareto Prevention, because
Diagram, 4) preventing a problem is
Cause-and-Effect Diagram, far less costly, than
5) Graphs, 6) Control fixing a problem.
Charts, 7) Checklists
It complicates project
1) Organizational team development.
planning, 2) Staff Because team members
acquisition, 3) Team are accountable to both a
development functional manager and
the project manager.
Integrated Change
Initiation - Inputs
Control - Tools
Product analysis,
benefit/cost analysis. Project selection
alternative methods, expert
identification and judgement
expert judgement
Product description,
WBS templates and project charter,
decomposition constraints, and
assumptions
Scope Definition - Scope Verification -
Inputs Tools
WBS, performance
Decomposition and reports, change
templates requests, and scope
management plan
Precedence Diagram
Other planning outputs,
Method (PDM), Arrow
historical information,
Diagram Method (ADM),
organizational policies,
conditional diagram
constraints,
techniques and network
assumptions
templates
Schedule Development
Cost Control - Input
- Inputs
Activity Duration
Cost Control - Tools
Estimating - Inputs
Quality Assurance -
Quality Control - Tools
Inputs
Benefit/cost analysis,
Quality planning tools benchmarking, flow
and techniques, and charting, design of
quality audits experiments, cost of
quality
Communications Information
Planning - Inputs Distribution - Tools
Information Performance
Distribution - Inputs Reporting - Tools
Negotiations, Project interfaces,
pre-assignment, and staffing requirements,
procurement and constraints
Performance reviews,
variance analysis, trend Work results,
analysis, earned value communications
analysis, and management plan, and
information distribution project plan
tools
Administrative Closure Administrative Closure
- Inputs - Tools
Documentation review,
information gathering
techniques, checklists,
Planning Meetings
assumptions analysis,
and diagramming
techniques
Solicitation Planning -
Solicitation - Tools
Inputs
Source Selection -
Solicitation - Inputs
Inputs
Risk management plan, Project risk response audits,
identified risks, list of periodic project risk reviews,
prioritized risks, list of risks
earned value analysis,
for additional analysis,
historical information, expert technical performance
judgment, and other planning measurements, and additional
outputs risk response planning
Procurement
management plan, Bidders conferences,
statement of work, and and advertising
other planning outputs
Contract Contract
Administration - Inputs Administration - Tools
Contract
Procurement Audits
Documentation
Contract change
Contract, work results,
control systems,
change requests, and
performance reporting,
seller invoices
and payment systems
Interviewing,
sensitivity analysis, Project plan, and
decision tree analysis, supporting details
and simulation
Schedule Development Quantitative Risk
- Outputs Analysis - Outputs
Scope changes,
Project archives,
corrective action,
project closure,
lessons learned, and
lessons learned
adjusted baselines
Scope Verification - Performance
Outputs Reporting - Outputs
Team Development -
Initiation - Outputs
Output
Scope statement,
Communications supporting details,
management plan scope management
plan
Contract
Contract Close-out -
Administration -
Outputs
Output
Workaround plans, corrective
action, project change
requests, updates to risk Resource
response plan, risk database, requirements
and updates to risk
identification checklists
Quantitative Risk
Analysis - Outputs
Quality management
plan, operational
Contract definitions, checklists,
and inputs to other
processes
Procurement
documents, evaluation
Cost baseline
criteria, and statement
of work updates
Work Breakdown
Workaround
Structure
Work Breakdown
Work Item
Structure
Quality improvement
Float
program.
Deliverable oriented
approach. / Project An alternative risk
elements are rolled up mitigation plan. Leaves
into larger project Risk in place.
deliverables.