Sie sind auf Seite 1von 1

PROCESS PRODUCT MANUFACTURING AACE INTERNATIONAL

LABOR COSTS

Labor costs, particularly in a labor-intensive process, may be (equation 10.5)


the dominant cost factor in an operating or manufacturing number of
cost estimate. To properly estimate these costs, a staffing Operating workhours =t processing steps
table must be established in as detailed a manner as possible. tons of product (capacity, tons/day)0.76
This table should indicate the following: where
t = 23 for batch operations with a maximum of labor,
1. the particular skill or craft required in each operation, t = 17 for operations with average labor requirements, and
2. labor rates for the various types of operations, t = 10 for well-instrumented continuous process opera-
3. supervision required for each process step, and tions.
4. overhead personnel required.
As pointed out previously, the relationship between labor
It is not always possible to determine the extent of supervi- requirements and production rate is not usually a direct one.
sion and overhead personnel required. In such cases, alter- The Wessell equation recognizes that labor productivity gen-
nate methods of estimating these costs may be used as dis- erally improves as plant throughput increases. It can also be
cussed later in this book. However, if sufficient data are avail- used to extrapolate known workhour requirements from one
able, these factors should be included in the staffing table for plant to another of different capacity.
maximum estimate accuracy.
Another shortcut method of estimating labor requirements,
Table 10.2 is a typical staffing table for a complete estimate. when requirements at one capacity are known, is to project
This table illustrates the detail required in a complete staffing labor requirements for other capacities to the 0.2 to 0.25
table. Note that the table includes general and administrative power of the capacity ratio.
personnel, production workers, maintenance workers, and
direct supervision. A significant factor to be considered in estimating labor costs is
overtime. As mentioned earlier, around-the-clock, 24-hr/day, 7-
Once the staffing table is developed (at a minimum including day/week operations have an inherent overtime penalty of 8
all direct production labor), labor costs can readily be esti- hr/week. With this exception, and occasional overtime to cover
mated from company records of wages and salaries by posi- for absent workers, overtime is usually not a major considera-
tion, union wage scales, salary surveys of various crafts and tion in manufacturing and production operations.
professions, or other published sources. Because labor rates
are prone to rapid inflation, often at rates sharply different However, in estimates involving construction projects, or
from general inflation rates, care must be taken to obtain cur- those which anticipate regular scheduled overtime, these
rent figures and to properly project future wage rates. costs can be substantial and must be carefully evaluated.

Generally, data on wage rates includes shift differentials and Scheduled overtime over an extended period can result in
overtime premiums. If not, these factors must be added to the substantial decreases in worker productivity resulting in a
extent applicable. major cost penalty for productivity losses in addition to the
higher direct costs of premium pay at 1.5, 2, or even 3 times
Further, when estimating around-the-clock, 168-hr/wk oper- normal hourly rates.
ations, allowance must be made for the fact that a week
includes 4.2 standard 40-hr weeks. Even with four work Scheduled overtime involves a planned, continuing schedule
crews on “swing shift,” one crew must work 8 hr/week of for extended working hours for individual workers or even
overtime to keep the plant in steady operation. Depending entire crews. It is not occasional overtime caused on an irreg-
upon local custom, laws, and union contracts, this overtime ular basis by absenteeism, equipment malfunctions, etc.
is generally payable at 1.5 to 3 times the normal hourly rate.
Unfortunately, scheduled overtime rarely saves money or
An alternate method of calculating labor requirements, if suf- accelerates production. Two articles which appeared in the
ficient data are not available to establish a staffing table, is to AACE Bulletin in 1973 [2, 5] amply illustrated this point.
consider a correlation of labor in workhours per ton of prod- These articles, prepared by representatives of the
uct per processing step. This relationship, which was devel- Construction Users Anti-Inflation Roundtable (now the
oped by Wessell [6], relates labor requirements to plant Business Roundtable), clearly demonstrated that scheduled
capacity by the following equation: overtime rarely, if ever, is beneficial, and that overtime
should be avoided in favor of additional employees working
normal shifts or partial shifts.

10.8

Das könnte Ihnen auch gefallen