Design


There's no margin for error with a sports project. With high expectations and
tight time schedules, you'd better do it right the first time.
Courtesy: CMX Group

by Don Dillon and Mike Lloyd

N
otwo college stadiwn projects Department guidelines, to
are alike. When you're start- its traditions and history, to
ing to design a new facility, you the existing stadium's design
can't simply dust off plans that worked and utility structure, and to
for another stadiwn. Each site is unique, the overall goal of the
and you must engineer design solutions administrators. Basically, it's
that are specific to each case. a good idea to talk to every-
There's no margin for error with a one.
sports project. By nature, it's a very
demanding process with high expecta- General guidelines
tions, tough standards, and tight time Contractors need to get
schedules. Your finished project is down and dirty on stadiwn
instantly placed on public display, so turf projects long before the
you'd better do it right the first time. first shovel ever hits the
ground. The following are a
Detailed approach few general guidelines: Natural Springs under the stands at Berkeley's
Doing it right the first time means Memorial Stadium created a particular challenge.
taking a painstakingly detailed manage- • First, find out exactly what Courtesy: CMX Group
ment approach to each project. the client wants.
Remember that people skills are just as • Determine the project's var-
important as securing the proper materi- ious constituencies, and establish a system From root zones to Irrigation
als and contractors for the job. of effective written and verbal communica- While most of our stadiwn projects
The initial programming stage is tions to eliminate any potential surprises. have been college facilities, our first major
essential to a project's success. It's critical • Develop a realistic project budget with field installation was contracted by the
that you determine what everyone is realistic cost estimates. Use local contrac- Arizona Cardinals. The City of Tempe had
expecting, and it's just as important to tors and subconsultants to properly quan- helped fund a new, $12-million, state of
know who "everyone" includes. tify those estimates. the art NFL training facility as an incen-
A major college sports project often • Treat each project as a unique entity. tive for the Cardinals to move from St.
has many indirect constituencies whose Involve local architects, planners,' and Louis. We came in to oversee the project,
agendas may differ greatly. You need to landscape managers. Select only those which included installation of three full-
work with the school's athletic director, materials that match the project's location length, grass practice fields.
because this person usually determines and climate. Establish local testing proto- The Cardinals insisted on attention to
the budget. You should also get input cols. detail. For instance, the organization
from the coaches, since their players will requested that the three practice fields be
be the ultimate judges of the quality of A company's versatility can be a major built on the same north-south axis as
the new field. asset to stadiwn projects. It's best if a firm Arizona State University's Sun Devil
Projects must also conform to the can do it all: design, engineer, and project Stadiwn, where the team plays its home
school's Planning and Construction manage. games.

20 sports TURF • http://www.sportsturfonline.com


A specially designed drainage system and lime treatments helped
keep the Berkeley project on schedule. Courtesy: CMX Group

Overcoming obstacles under the stadium. These procedures


became even more necessary when heav-
We faced a particular chal- ier than normal winter rains kept the
lenge when California- local water table high and the stadium
Berkeley brought us in to help soil very moist. If we hadn't addressed the
convert its football field at uniqueness of the project early on, it
Memorial Stadium back to would not have been completed on sched-
grass from artificial turf. We ule.
knew going in that
Strawberry Creek ran Sports projects are intense, highly-vis-
through a drainage structure ible endeavors with tight budgets and
under the stadium. even tighter time schedules. There's con-
In the information-gather- stant media scrutiny and no margin for
ing stage, we looked at the error.
stadium's "as-built" records, It's never easy, but by starting with a
It was a great experience. The review which dated back to the 1920s. We firm foundation and developing contin-
and communication process was intense brought in local expertise, and took soil gency plans, it can be most exciting and
and constant. Our plans needed to be borings for pre-evaluation and analysis. satisfying. 0
extremely precise. The Cardinals During our geotechnical soils testing,
remained involved in all phases of the we discovered that there were natural
field installation, from setting the root- springs under the stands. These would
zone specifications to incorporating a likely empty into the lowered playing field Don Dillon is chief executive officer
unique subsurface irrigation system. area during construction, so we needed to and Mike Lloyd is president of CMX
The results speak for themselves. The address the situation immediately. Group, Inc. 1515 E. Missouri Ave.,
fields have held up exceptionally well, We designed a drainage system to Suite 115, Phoenix, AZ 85014. Phone:
and the training facility still ranks as one intercept the water, and then used a spe- (602) 279-8436, Fax: (602) 265-1191,
of the best in the NFL. cial lime treatment to stabilize the soil Web: http / / :www.cmxinc.com.

AERA-vator® Laser Grading


with GRADEMASTER

• Laser Controlled
Accuracy
• Final Grade Tolerance
of only 1/4"
• Automated Operation
• Durable 112" Steel Construction
"This past summer, our goal was to aerate all • 3-Point Hitch Maneuverability
of our athletic fields on a regular basis all
summer (once every 3 weeks was the end
result). The Aera-Vator" proved to be a very
versatile and valuable addition to our turf GRADEMASTER allows you to complete final grading
program. We use it in hard compacted soils of tees in one-third of the time of conventional
where core aeration would not penetrate. We
methods. And with over 18 years in the laser in-
were able to loosen up areas prior to games
without having a negative effect on play. dustry, Laser Leveling has the experience and
Overall we are very pleased with the varity of knowledge to keep you at the top of your market.
turf tasks we can use the Aera- Vator on. It is
Paul M. Edwardson
reliable and has become a very important
Laser Leveling, Inc.

A\
Park Maintenance Mgr.
City oj Bloomington, MN piece of our Turf Maintenance Program." P.O. Box 338
Lutz, FL33548
R~~DUC The Multi-Purpose Tool Versatile
Tel: (800) 622-5777 (813) 949-4777
TS Enough for Golf or Sports Turf! Fax: (813) 949-0509
~ 800·363·8780 OUTSIDE GA. 912/382·4768
SALES REP & DEALER INQUIRIES WELCOMED. "We're Taking the Grading Industry to a New Level"

Call 1 (800) 817-1889 use Fast Fax#1091198 and/or Circle 109 on Inquiry Card Call 1 (800) 817-1889 use Fast Fax#1101198 and/or Circle 110 on Inquiry Card

November 1998 21

Das könnte Ihnen auch gefallen