ELEVATION
200
100 750
450
1.2 6 1.2
8.4
(DIMENSIONS IN CM)
1.00 TOP SLAB 1.00 840.00 20.00 16800.00 10.00 168.00 16.80 5.60
2.00 LT TRIANGLE POR 1.00 120.00 10.00 600.00 26.67 16.00 4.27 0.03
3.00 RT TRIANGLE POR 1.00 120.00 10.00 600.00 26.67 16.00 4.27 0.03
4.00 BOTTOM SLAB 1.00 600.00 55.00 33000.00 47.50 1567.50 744.56 83.19
a Kerb
2 nos *0.45*0.3*2.4 = 0.65 T
Span = 14.30 m
w = 12.24 T/m
16.45 16.45
Reaction = 103.96
DESIGN OF 15.0 M SOLID SLAB
SECTION AT O.1 L
11.40 11.40 6.80 6.80 6.80
1.20 4.30
3.00 3.00
0.14
1.29 1.17 0.74 0.44
1.43 12.87
Shear force
0.10
0.82 0.52 0.31
0.90
S.F. = 25.80
SECTION AT O.2 L
11.40 11.40 6.80
1.20 4.30
3.00 6.80
2.86 11.44
Shear force
0.21
0.72 0.42
0.80
S.F. = 21.51
SECTION AT O.3 L
11.40 11.40 6.80 6.80
1.20 4.30
3.00
4.29 10.01
Shear force
0.11
0.62 0.32
0.70
S.F. = 17.87
Factored corresponding S.F.= =17.87*8.4/8.4*1.22 21.83 T
DESIGN OF 15.0 M SOLID SLAB
SECTION AT O.4 L
11.40 11.40 6.80
2.70 1.20 4.30 6.80
3.20 3.00
5.72 8.58
Shear force
0.01
0.52 0.22
0.60
S.F. = 14.23
SECTION AT O.5 L
2.70 11.40 11.40 6.80
2.70 1.20 4.30
1.20 3.20
1.98
1.38 3.58 2.98 0.83
7.15 7.15
Shear force
0.19 0.28
0.42 0.12
0.50
S.F. = 12.49
Factored corresponding S.F.= =12.49*8.4/8.4*1.22 15.26 T
HIGH LEVELBRIDGE ACROSS RIVER SEZBAHAR
CLASS AA Span = 14.30 Impact = 1.10
O.36 3.24
1.43 12.87
R= 55.95
0.72 2.88
2.86 11.44
R= 50.71
1.08 2.52
4.29 10.01
R= 45.48
1.44 2.16
5.72 8.58
R= 40.24
7.15 7.15
R= 35.00
TOTAL B.M
n = 1.00 = 1.00
[ 1+ fc/m*fbc] [1+ 2039
10*101.9]
= 0.333
j = [ 1 -n/3] = [1-0.333/3]
= 0.889
Q = 0.5*Fc*n* j =0.5*101.9*0.333*0.889
15.0890059
M = Q *b*d2
d = (M*105)
(15.08*b)
HIGH LEVELBRIDGE ACROSS RIVER SEJBAHAR
MODULAR RATIO = 10
Where
Y is central distance of bar from the bottom
n is number of bars
= 5.4
DEPTH OF N.A.
1* 840 * N2 * 0.5
= 10 * 184.8 *( 69.6 - N
Solving above
(b2-4ac)1/2 34.7217511
15.16088
MOMENT OF RESISTANCE
Mr = Ast*fst*(d-N/3) 243.22
> 239.76
f cb = fst*Ast/(0.5*b*N) 58.34
HIGH LEVELBRIDGE ACROSS RIVER SEJBAHAR
MODULAR RATIO = 10
Where
Y is central distance of bar from the bottom
n is number of bars
= 5.4
DEPTH OF N.A.
1* 840 * N2 * 0.5
= 10 * 332.64 *( 69.6 - N
Solving above
(b2-4ac)1/2 46.2839238
19.18196
MOMENT OF RESISTANCE
Mr = Ast*fst*(d-N/3) 428.70
> 412.56
MODULAR RATIO = 10
Where
Y is central distance of bar from the bottom
n is number of bars
= 5.4
DEPTH OF N.A.
1* 840 * N2 * 0.5
= 10 * 418.88 *( 69.6 - N
Solving above
(b2-4ac)1/2 51.740783
20.88372
MOMENT OF RESISTANCE
Mr = Ast*fst*(d-N/3) 535.00
> 530.11
f cb = fst*Ast/(0.5*b*N) 96.49
HIGH LEVELBRIDGE ACROSS RIVER SEJBAHAR
MODULAR RATIO = 10
Where
Y is central distance of bar from the bottom
n is number of bars
= 5.4
DEPTH OF N.A.
1* 840 * N2 * 0.5
= 10 * 492.8 *( 69.6 -
Solving above
(b2-4ac)1/2 55.9364719
22.10157
MOMENT OF RESISTANCE
Mr = Ast*fst*(d-N/3) 625.33
> 598.63
f cb = fst*Ast/(0.5*b*N) 103.62
HIGH LEVELBRIDGE ACROSS RIVER SEJBAHAR
MODULAR RATIO = 10
Where
Y is central distance of bar from the bottom
n is number of bars
= 5.4
DEPTH OF N.A.
1* 840 * N2 * 0.5
= 10 * 529.76 *( 69.6 -
Solving above
(b2-4ac)1/2 57.9003957
22.64353
MOMENT OF RESISTANCE
Mr = Ast*fst*(d-N/3) 670.28
> 621.16
f cb = fst*Ast/(0.5*b*N) 105.26
HIGH LEVELBRIDGE ACROSS RIVER SEJBAHAR
Ast = M*105
2039*0.889*d
Ast = 0.817292 *M
0.1L 133.54 22.26 106.22 17.70 9.76 7.98 12 dia @100 c/c
0.2L 237.60 39.60 174.96 29.16 16.67 13.62 16 dia @120 c/c
0.3L 311.93 51.99 218.17 36.36 21.31 17.41 16 dia @95 c/c
0.4L 356.53 59.42 242.09 40.35 23.99 19.61 20 dia @130 c/c
0.5L 371.40 61.90 249.76 41.63 24.87 20.32 20 dia @130 c/c
It is proposed to use M-30 grade of concrete for the chair.The permissible stress in
direct compression for M-30 concrete as per table 8 under Clause .303
5.3
R.L 101.11
0.5 R.L 100.61
0.6
0.6
R.L. 99.41
99.01
1.8
CROSS- SECTION IN TRAFFIC DIRECTION
5.3 CROSS SECTION IN CURRENT DIRECTION
0.7
0.55
0.35 1.8
0.35
0.55
0.6 2.65 2.65 0.6
6.5
PLAN
Max Vertical load per chair 67.42313 T
refer bearig calculation
= 51.77462 sqcm
= 93.194314