KHAN KHWAR HYDROPOWER PROJECT

Contract No. KC-01& KE-04


Monthly Progress Report No. 74

September 2010

1. Powerhouse Site:

1.1. Fire Fighting and Diesel Generator Rooms:


The concrete placement of fire fighting room slab and diesel generator tank &
generator room foundation has been completed by placing 33m3 concrete during the
month. The progress status is given in “Table B”.

2. Weir Site:

2.1 Weir Structure:


2nd stage concrete of bottom outlet # 3 & 4 has been completed upto El. 815.00 masl
by placing 205m3 concrete during the reported month. The progress status is given in
“Table B”.
All working activities have been suspended after heavy flood in Khan Khwar River.

3. Hydraulic steel works;

Weir Structure:

• Dry testing of Bottom outlet radial gate (WD3 &WD4) completed. Report awaited.

• Grinding of welding seam of circumferential joint of pressure tunnel is in progress.

Page 1 of 9
Quality Control Measures during September 2010:
Sr. No
No. of
Description of Tests Name of Structure Remarks
Tests
S.No
Powerhouse, and Headrace
Tunnel 07 Pass
Compressive Strength of Concrete (7 days / 28 days)
1.
(7 days & 28 days) Weir Structure and Headrace
Tunnel 09 Pass
(7 days / 28 days)
2. Physical Test of Cement Shipment ASKARI OPC Cement 01 Pass

Physical Test of reinforcement Fazal Steel 01 Pass


3
shipment NOMEE Steel -- --

Fineness Aggregate
4. Indus River Side -- Pass
(Fineness Module)

Coarse Aggregate
5. Indus River Side 02 Pass
(Sieve Analysis)

Loss on ignition Fineness Water


6. Karachi Flyash 01 Pass
Requirement

4. Field Survey:
No work.

5. Contractor’s Equipment Status:


List of Contractor’s equipment is attached as Annexure “A”.

6. Condition of Access Road:


The access road remained open for traffic without any blockage.

7. Monitoring Instrument:
The list of monitoring instruments installed at various locations of the project is attached as
Annexure “B”.

08. Weather Record: Nil.

09. New Activity: Nil.


NIL

10. Accident: Nil

11. Visits:
PM-HHC visited Khan Khwar Hydropower Project both powerhouse and weir site on
September 18 and September 25, 2010.

12. Contractual issues: Nil.

13. Bottlenecks: Nil.

Page 2 of 9
Table “B”
Concrete Works
Total Total of upto During Total Qty
S. No Work Description Unit
Qty pre. Month Month to date
3. Switchyard Roads M3 200 50 -- 50
Fire fighting and diesel generator
4. M3 70 20 -- 20
rooms
4. Auxiliary Penstock Backfill Concrete M3 350 300 -- 300
22. Weir Structure M3 130000 95461 25 95486
23. Stilling basin Structure M3 27000 22450 -- 22450
Backfill concrete of power intake left
26. M3 3950 3396 -- 3396
& right sides

Page 3 of 9
Contract KE-04 Lot (E&M)
1- Powerhouse:-
1.1 11 KV Bus Bar:
The connectivity of 11 KV bus bar to the generator terminal of unit No. 01 has been completed
on 19-09-10.

1.2 Thrust Bearing Oil Purification:


Cleaning of thrust bearing oil line by circulating the oil to remove the suspended particles from
thrust bearing oil El. 573.40 of unit No1&2 has been completed.

1.3 Oil Handling Room:


Installation of valves on piping system has been completed whereas cabling work in the oil
handling distribution panel is in progress.

1.4 Water Treatment Room:


Remaining work of piping in the water treatment room has been completed.

1.5 HVAC Room:


Piping work in the HVAC equipment room has been completed whereas painting work on
piping lines and duct installation work is in progress

1.6 Fire Fighting System in Powerhouse:


The extension of fire fighting pipe to hydrant box installed at all locations in power house has
been completed

1.7 Erection of Rails for Draft Tube cone:


Erection / installation of rails for the draft tubes cone of Unit No. 1&2 has been completed and
ready for 2nd stage concreting by civil contractor

2- Auxiliary Unit:-
2.1 Turbine Generator Assembly:
The remaining piping work on turbine and generator along with cable termination work is in
progress.

2.2 Oil Purification:


Cleaning of thrust bearing oil line by circulating the oil through oil purifier to remove
suspended particles from thrust bearing oil has been completed on September 03, 2010.

3- Switchyard:-
3.1 Fire-Fighting Piping System:
Piping system, deluge valve and installation of distribution panel in the main fire fighting
control room has been completed.

4- Testing and Inspection:-


The following tests / inspection have been done jointly from September 15, 2010 to
September 23, 2010.

1. Excitation system for unit # 1.


2. Excitation system for unit # 2.
3. Governor and oil device for unit # 1.
4. Governor and oil device for unit # 2.
5. Dewatering system for powerhouse.
6. Cooling water supply system.
Page 4 of 9
7. Brake system for unit # 1.
8. Brake system for unit # 2.
9. System for high pressure lifting rotor (Jack System) of unit # 1.
10. System for high pressure lifting rotor (Jack System) of unit # 2.
11. System for high pressure (Thrust bearing lift Pump) of unit # 1.
12. System for high pressure (Thrust bearing lift Pump of unit # 2.
13. Inlet valve of unit # 1.
14. Fire fighting system for powerhouse.

The Contractor has advised to submit the formal results along with original data for review and
approval accordingly.

Page 5 of 9
Form GC-CPM3
Construction Projects

INDUS TRIBUTARIES HIGH-HEAD HYDROPOWER COMPLEX PROJECT

KHAN KHWAR HYDROPOWER PROJECT


C&HS WOKS KC 01

PHYSICAL PROGRESS UPTO September 2010


Project Start Date: 16-06-2003 Schedule Project Completion Feb 28, 2010 (Revised)
Summary Tasks
Sr. Target Completion Dates Progress % Remarks
Main Tasks/Milestones
No Original Revised Target Actual
Powerhouse Sub-structure ready
1 15-12-04 11-12-05 100 100
for Turbine, DT Erection. U1&U2
2 Powerhouse Assembly Bay ready
15-06-05 11-06-06 100 100
for Equipment Erection
3 Powerhouse Structure ready for
15-07-05 11-07-06 100 100
Crane Erection
4 Powerhouse Sub-structure ready
15-09-05 11-09-06 100 100
for Turbine Embedment, U1
5 Powerhouse Sub-structure ready
15-10-05 11-10-07 100 100
for Turbine Embedment, U2
6 Powerhouse Sub-structure ready
15-01-06 11-01-07 100 100
for Generator Parts Embed, U1
7 Powerhouse Sub-structure ready
15-02-06 11-02-07 100 100
for Generator Parts Embed, U2
8 Powerhouse Sub-structure ready
15-04-06 11-04-07 100 100
for Turbine Erection, U1
9 Powerhouse Sub-structure ready
15-05-06 11-05-07 100 100
for Turbine Erection, U2
10 Powerhouse Sub-structure ready
15-04-06 11-04-07 100 100
for Generator Erection, U1
11 Powerhouse Sub-structure ready
15-05-06 11-05-07 100 100
for Generator Erection, U2
12 Powerhouse Structure ready for
15-04-06 11-04-07 100 90
e/m and HVAC-installation
13 Aux-Powerhouse ready for
15-04-05 11-04-07 100 100
Erection of Aux. Generating Unit
14 Civil works of Switchyard ready for
15-05-05 11-05-06 100 100
Equipment Installation
15 Control Building at Intake ready for
15-03-06 11-03-07 100 0
electr. Installation
16 Filling of Reservoir 15-03-07 11-07-08 100 --
17 Waterway System ready for Unit
15-04-07 11-08-08 100 100
Commissioning
18 Completion of Civil Works & Hydro.
15-06-07 28-02-10 99 92
Steel Structure Contract

Target completion date “original” has been taken with reference to the construction order
issued on 08 January 2005. Revised target completion date is yet to be reconciled for
Contract KC-01 and KE-04.

Page 6 of 9
Form GC-CPM4
Construction Projects

INDUS TRIBUTARIES HIGH-HEAD HYDROPOWER COMPLEX PROJECT

KHAN KHWAR HYDROPOWER PROJECT


C&HS WOKS KC 01

PHYSICAL PROGRESS UPTO September 2010


Project Start Date: 16-06-2003 Schedule Project Completion Feb 28, 2010 (Revised)
Summary Tasks
Target Completion
Sr. Progress % Remarks
Detailed Activities Dates
No
Original Revised Target Actual
Pre-Construction Stage
1 Award of Contract / Design Order 16-06-03 100 100

2 Detailed Design by Contractor 16-11-03 100 100

3 Design Review & Approval by WAPDA 28-02-04 100 100

Construction Stage

1 Construction Order 29-02-2004 12-01-2005 100 100

2 Mobilization 31-08-2004 12-07-2005 100 100

3 Construction of Access Roads 31-12-2003 31-07-2005 100 86

4 Construction of Diversion Works 31-05-2005 30-04-2006 100 100

5 Excavation of Headrace System 30-09-2005 31-08-2006 100 100

6 Powerhouse & Switchyard Construction 30-09-2006 31-08-2007 100 100

7 Construction of Weir Structure 30-11-2006 31-10-2007 100 97.14


Concrete Lining & Steel Lining of
8 31-01-2007 31-12-2007 100 100
Headrace
9 Construction of Power Intake Works 31-12-2006 31-12-2007 100 100
Headrace System ready for Unit
10 Jan. 2007 Dec.2007 100 100
Commissioning
11 Erection of Hydraulic Steel Structure 31-01-2007 31-01-2008 100 87

12 Powerhouse Finishing Works 31-03-2007 31-08-2008 100 90

13 De-mobilization of Contract 30-06-2007 30-09-2008 100 --

14 Completion of Contract 16-06-2007 28-02-2010 99 94

Page 7 of 9
Form GC-CPM5
Construction Projects

INDUS TRIBUTARIES HIGH-HEAD HYDROPOWER COMPLEX PROJECT

KHAN KHWAR HYDROPOWER PROJECT


E&M WOKS KE-04

PHYSICAL PROGRESS UPTO September, 2010

Project Start Date: 16-06-2003 Project Completion Revised Date February 28, 2010
Summary Tasks
Target Completion Dates Progress % Remarks
Sr.
Main Tasks/Milestones
No
Original Revised Target Actual
Embedded Turbine. DT. Parts
1 15-02-2005 11-02-06 100 100
ready for Embedment. U1
Embedded Turbine, DT. Parts
2 15-03-2005 11-03-06 100 100
ready for Embedment U2
3 Crane Erection Complete 15-08-2005 11-08-06 100 100
Embedded Turbine, SC. Parts
4 15-12-2005 11-12-06 100 100
ready for Embedment, U1
Embedded Turbine, SC. Parts
5 15-01-2006 11-02-07 100 100
ready for Embedment, U2
Embedded Generator parts
6 15-02-2006 11-02-07 100 100
ready for Embedment, U1
Embedded Generator parts
7 15-03-2006 11-03-07 100 100
ready for Embedment, U2
8 Turbine Erection Complete, U1 15-11-2006 11-11-07 100 99.8

9 Turbine Erection Complete, U2 15-01-2007 11-01-08 100 100


Generator Erection Complete,
10 15-01-2007 11-01-08 100 99.3
U1
Generator Erection Complete,
11 15-03-2007 11-03-08 100 97.7
U2
12 Transformers Installed 15-11-2006 11-11-08 100 99.5
Electrical Installation in PH
13 15-01-2007 11-01-08 100 99.5
Complete
System connected to 11 KV
14 15-01-2007 11-01-08 100 05
System
Erection of Aux. Generating
15 Unit Complete, incl. Ancillary 15-03-2007 11-03-08 100 75.26
Equipment
Overall
Switchyard Equipment
16 15-11-2006 11-011-08 100 99.95 installation in
Installation complete
switchyard
Power supply available at
17 15-08-2006 11-08-07 100 --
Weir/intake site.
Taking over Generating Unit
18 15-06-2007 11-06-08 100 --
No. 1
Taking over Generating Unit
19 15-08-2007 11-08-08 100 --
No. 2
Taking over Auxiliary
20 15-06-2007 11-06-08 100 --
Generating Unit
21 Tanking over HV-Switchyard 15-04-2007 11-04-08 100 --
Completion of E&M Works
22 15-08-2007 28-02-10 99 94
Contract

Page 8 of 9
Form GC-CPM6
Construction Projects

INDUS TRIBUTARIES HIGH-HEAD HYDROPOWER COMPLEX PROJECT

KHAN KHWAR HYDROPOWER PROJECT


C&HS WOKS KC 01

SUMMARY OF QUANTITIES FOR MAJOR ITEMS UPTO September 2010.

Project Start Date: 16 June, 2003 Project Completion Date: October 2008

Quantities
Sr. Major Item of During the
No Works Total Up to the pre. month Total
Unit Remarks
Estimated Month Executed
Executed

1 Excavation M3 294,318 467876 -- 467876 --

2 Concrete Work M3 134,857 175004 58 175062 --

1- Penstock steel
liner including
auxiliary Tones 533.395 530.55 0.00 530.55 --
penstock.

2- Steel armor of
weir structure
Tones 749.5 650.895 0.00 650.895 --
including
stilling basin.

3 3- Powerhouse
tailrace and Tones 81.997 81.997 0.00 81.997
outlet gate.

4- Weir Structure
Tones 830.137 624.389 26.8 T 651.19 --
Gates.

G. Total Tones 2195.029 1875.981 26.8 T 1914.632 87 %

Page 9 of 9