September 2010
1. Powerhouse Site:
2. Weir Site:
Weir Structure:
• Dry testing of Bottom outlet radial gate (WD3 &WD4) completed. Report awaited.
Page 1 of 9
Quality Control Measures during September 2010:
Sr. No
No. of
Description of Tests Name of Structure Remarks
Tests
S.No
Powerhouse, and Headrace
Tunnel 07 Pass
Compressive Strength of Concrete (7 days / 28 days)
1.
(7 days & 28 days) Weir Structure and Headrace
Tunnel 09 Pass
(7 days / 28 days)
2. Physical Test of Cement Shipment ASKARI OPC Cement 01 Pass
Fineness Aggregate
4. Indus River Side -- Pass
(Fineness Module)
Coarse Aggregate
5. Indus River Side 02 Pass
(Sieve Analysis)
4. Field Survey:
No work.
7. Monitoring Instrument:
The list of monitoring instruments installed at various locations of the project is attached as
Annexure “B”.
11. Visits:
PM-HHC visited Khan Khwar Hydropower Project both powerhouse and weir site on
September 18 and September 25, 2010.
Page 2 of 9
Table “B”
Concrete Works
Total Total of upto During Total Qty
S. No Work Description Unit
Qty pre. Month Month to date
3. Switchyard Roads M3 200 50 -- 50
Fire fighting and diesel generator
4. M3 70 20 -- 20
rooms
4. Auxiliary Penstock Backfill Concrete M3 350 300 -- 300
22. Weir Structure M3 130000 95461 25 95486
23. Stilling basin Structure M3 27000 22450 -- 22450
Backfill concrete of power intake left
26. M3 3950 3396 -- 3396
& right sides
Page 3 of 9
Contract KE-04 Lot (E&M)
1- Powerhouse:-
1.1 11 KV Bus Bar:
The connectivity of 11 KV bus bar to the generator terminal of unit No. 01 has been completed
on 19-09-10.
2- Auxiliary Unit:-
2.1 Turbine Generator Assembly:
The remaining piping work on turbine and generator along with cable termination work is in
progress.
3- Switchyard:-
3.1 Fire-Fighting Piping System:
Piping system, deluge valve and installation of distribution panel in the main fire fighting
control room has been completed.
The Contractor has advised to submit the formal results along with original data for review and
approval accordingly.
Page 5 of 9
Form GC-CPM3
Construction Projects
Target completion date “original” has been taken with reference to the construction order
issued on 08 January 2005. Revised target completion date is yet to be reconciled for
Contract KC-01 and KE-04.
Page 6 of 9
Form GC-CPM4
Construction Projects
Construction Stage
Page 7 of 9
Form GC-CPM5
Construction Projects
Project Start Date: 16-06-2003 Project Completion Revised Date February 28, 2010
Summary Tasks
Target Completion Dates Progress % Remarks
Sr.
Main Tasks/Milestones
No
Original Revised Target Actual
Embedded Turbine. DT. Parts
1 15-02-2005 11-02-06 100 100
ready for Embedment. U1
Embedded Turbine, DT. Parts
2 15-03-2005 11-03-06 100 100
ready for Embedment U2
3 Crane Erection Complete 15-08-2005 11-08-06 100 100
Embedded Turbine, SC. Parts
4 15-12-2005 11-12-06 100 100
ready for Embedment, U1
Embedded Turbine, SC. Parts
5 15-01-2006 11-02-07 100 100
ready for Embedment, U2
Embedded Generator parts
6 15-02-2006 11-02-07 100 100
ready for Embedment, U1
Embedded Generator parts
7 15-03-2006 11-03-07 100 100
ready for Embedment, U2
8 Turbine Erection Complete, U1 15-11-2006 11-11-07 100 99.8
Page 8 of 9
Form GC-CPM6
Construction Projects
Project Start Date: 16 June, 2003 Project Completion Date: October 2008
Quantities
Sr. Major Item of During the
No Works Total Up to the pre. month Total
Unit Remarks
Estimated Month Executed
Executed
1- Penstock steel
liner including
auxiliary Tones 533.395 530.55 0.00 530.55 --
penstock.
2- Steel armor of
weir structure
Tones 749.5 650.895 0.00 650.895 --
including
stilling basin.
3 3- Powerhouse
tailrace and Tones 81.997 81.997 0.00 81.997
outlet gate.
4- Weir Structure
Tones 830.137 624.389 26.8 T 651.19 --
Gates.
Page 9 of 9