Revision Record
23 August
V2.0 Change Cabling diagram EARIHHE
2017
2
MOP for implementation of MBC
_________________________________________________________________________________________________
Table of Contents
1 EXECUTIVE SUMMARY............................................................................................................4
2 BACKGROUND AND OBJECTIVES.............................................................................................5
3 SCOPE OF WORK.....................................................................................................................6
4 DETAIL TIME TABLE OF OVERALL ACTIVITY.............................................................................7
5 DETAIL OPERATION AND EXECUTION......................................................................................8
6 SERVICE AND AREA IMPACT....................................................................................................9
7 TESTING AND VERIFICATION.................................................................................................10
8 ROLLBACK OPERATION..........................................................................................................12
9 PERSON IN CHARGE..............................................................................................................13
10 SUPPORTING DOCUMENTS...................................................................................................14
3
MOP for implementation of MBC
_________________________________________________________________________________________________
1 EXECUTIVE SUMMARY
- The purpose of this document to facilitate identifying and communicating the key steps
and actions required as part of the said MBC Activation and to ensure that ALL parties
are aware of the documentation that is required. All parties must sign the MOP for the
upgrade to commence if satisfied that all roles, responsibilities & actions are clearly
understood and in place. On completion of the full upgrade procedure, all parties must,
again sign the MOP listing any outstanding items identified with a specified completion
date. It is not the intention of this document to replace any of the implementation
procedures nor is it part of the standard deliverables.
- The involved NE descript in the NIW Request by Ericsson Project (ITC Coordinator or
Implementation Manager)
- The impact activity will cause outage during implementation on correlated node
- Correlated node will be down for 1 Hour during configuration.
- Before activity prerequisites of this activity should be fulfilled such as
NIW Approval from Customer
RBS Health Check
Access to enter site should be secure
RBS Should have No Major Alarm, any major Alarm should be got approval from
Customer via ITC Coordinator or Ericsson Implementation Manager
4
MOP for implementation of MBC
_________________________________________________________________________________________________
- Perform MBC Activation with existing configuration preparation for activation LTE
Upgrade Bandwidth 20 MHz
5
MOP for implementation of MBC
_________________________________________________________________________________________________
3 SCOPE OF WORK
PREPARATION
2 Activation MBC
Site Access (Permit Letter for Site access & Site Key)
5
- Shelter Room
6
MOP for implementation of MBC
_________________________________________________________________________________________________
10.00 –
Pre-Health Check No service impact
10.30
10.30 –
MBC Execution, including recabling Down 1 Hour during configuration
14.00
14.00 –
Perform testing services No service impact
15.00
7
MOP for implementation of MBC
_________________________________________________________________________________________________
3. Reconfigure of DUG 2
8
MOP for implementation of MBC
_________________________________________________________________________________________________
9
MOP for implementation of MBC
_________________________________________________________________________________________________
Summary of Disturbances
The table below shows a summary of the expected disturbances during the RBS implementation:
10
MOP for implementation of MBC
_________________________________________________________________________________________________
11
MOP for implementation of MBC
_________________________________________________________________________________________________
8 ROLLBACK OPERATION
Detailed of activity
- Fallback will be done in case either the site is not coming up at all or calls are not getting
matured for the RBS site.
- Decision of the fallback with the CU SPOC for the RBS site with approval from Customer
through ITC Coordinator and Implementation manager
Step of fallback
1. Change Back IDB
2. Reload CV Before executing
12
MOP for implementation of MBC
_________________________________________________________________________________________________
9 PERSON IN CHARGE
Phone
Name Company Number Roles and Responsibilities
Mochamad Ismail PT Indosat Tbk 0816803279 Project Manager
Edison Panjaitan PT Indosat Tbk 0816800642 Staf
Achmad Asikin PT Ericsson Indonesia 08161450989 Ericsson Customer Project Manager
Maming Yunianto PT Ericsson Indonesia 08111880108 Service Delivery Manager (CNS)
Sugeng rahmanto PT Ericsson Indonesia 081514338513 Ericsson ITC Coordinator
Ari Hendra H PT Ericsson Indonesia 08119304755 Ericsson TAC Team Lead
Henry Erik Estrada PT Ericsson Indonesia 081905013686 Ericsson RNC / BSC Team Lead
CNS Emergency PT Ericsson Indonesia 085584033872 Hot Line Number Emergency Support
13
MOP for implementation of MBC
_________________________________________________________________________________________________
10 SUPPORTING DOCUMENTS
2.
14