Page 1 of 95
Main Objectives:
The main objective of this document is to show basic setups required for cross docking
(Release 12) and has examples of some flows that will give any user an head start in using the
functionality.
The information contained in this document is subject to change without notice. If you find any
problems in the documentation, please report them by e-mailing
john.chankaramangalam@oracle.com.
Special Thanks to Harry Herman (Support Manager), Madhu Punugati (Product Management) ,
Anand Nallaalaghu (QA Manager), Gopal Rao (Development), Lydia Chen (Program
Management) , Support team & Development team.
Page 2 of 95
Table of Contents
Overview Of Crossdocking...................................................................................................................... 4
Planned Crossdocking:........................................................................................................................ 5
Planned Cross Docking With PO as Supply and SO as Demand: ......................................................... 6
Planned Cross Docking With ASN as Supply and SO as Demand: ..................................................... 27
Planned Crossdocking: ........................................................................................................................ 28
Opportunistic Crossdocking: ............................................................................................................ 52
Opportunistic Crossdocking with Sales Order as Demand & PO as Supply: ...................................... 53
Opportunistic Crossdocking with WIP Component Demand: .............................................................. 72
Cross dock exceptions: ...................................................................................................................... 89
Planned & Opportunistic Cross Docking: .............................................................................................. 91
Crossdocking and Change Management :........................................................................................ 92
Debugging Issues:............................................................................................................................... 95
Page 3 of 95
Crossdock Planning & Execution
Overview Of Crossdocking
With this feature, crossdocking can be planned in the warehouse. The system can identify
crossdocking opportunities in the warehouse by comparing expected receipts and outbound
shipments. When a crossdocking opportunity is identified, the scheduled inbound
receipt(supply) is pegged to the outbound shipment(demand) using crossdock criteria. A
specific inbound receipt is identified based on whether the warehouse wants to maximize
crossdocking or minimize wait time or minimize fragmentation. In case of Planned crossdocking
the pre-allocation is done during Pick Release. In opportunistic crossdocking dynamic allocation
is done during material putaway.
Page 4 of 95
Planned Crossdocking:
Scenario:
In this example we will show how Planned Crossdocking happens for a PO as supply and Sales Order as
Demand. We will define an item and assign it to organization W1. Then we will create a PO for the item
for qty 20. Create a Sales Order for the item for qty10. Run pick release with allocation method as “Cross
Dock Only”. Then we review the reservations created. Then we execute the cross docking.
Page 5 of 95
Planned Cross Docking With PO as Supply and SO as Demand:
Planned Crossdock is demand driven and prior to arrival of the material, demand is planned to be fulfilled
using incoming supply.
In the above example we are creating a planned crossdock criteria by the name ‘CJP CROSS DOCK
PLANNED’.
Crossdocking Time fences - Identify eligible supply sources (for planned crossdocking) or eligible
demand sources (for opportunistic crossdocking)
Crossdock Window (CW) : Wait Time
Order Processing Time (OPT) : Load/unload/move Time
Buffer Time (BT) : Safety margin
Past Due Supply Cut-off (PDS) : To exclude uncertain supplies
Page 6 of 95
Crossdocking Goal - Choose one or more supply (or demand) sources from the pool of eligible supply
(or demand) sources
Maximize Crossdock (FIFO)
Minimize Wait (LIFO)
Custom
Page 7 of 95
Eligible supplies for planned crossdock
PO, ASN, Internal Requisition, In-transit shipment, Receiving
Page 8 of 95
PCross 2 Define Item
Business Approach:
Define an Item and assign it to child organization where you will be doing the transaction.
In our example we have defined item ‘testplnxdocitem’.
Page 9 of 95
PCross 3 Setup Crossdock criteria assignment
Business Approach:
Two new Rule Types are introduced in R12. Planned Crossdock & Opportunistic Crossdock.
In out planned cross dock test we will select Planned Crossdock type.
We create a new assignment with a sequence number. Lower the sequence higher the precedence.
In our case we have assigned sequence 5 . Then we have selected the cross dock criteria we had
defined (CJP CROSS DOCK PLANNED). We select organization (W1) and select the crossdock planned
item (testplnxdocitem). Select ‘Always’ in the Date Type column. Check ‘Enabled’.
Note: Always remember to run ‘Generate All Rules’ Concurrent program after you have defined any new
rule or made changes to existing rule.
Page 10 of 95
Navigation: → Other Æ Requests Æ Requests Æ Run
Page 11 of 95
PCross 4 Create Crossdock Operation Plan
On operation select Cross dock. In cross dock method select appropriate cross dock method. In our
example we select ‘(Default) LPN based consolidation in staging lane within delivery’.
The other options are:
Locator based consolidation in consolidation locator, within delivery in staging lane
LPN based consolidation in consolidation locator, within delivery in staging lane
Direct consolidation in staging lane within delivery
LPN based consolidation in staging lane across deliveries
Direct consolidation in staging lane across deliveries
LPN based consolidation in consolidation locator, across deliveries in staging lane
Locator based consolidation in consolidation locator, across deliveries in staging lane
Page 12 of 95
PCross 5 Order Management & Shipping Parameter Setup
Business Approach:
Page 13 of 95
Navigation: → Setup Æ Shipping Æ Global Parameters
For “Delivery Date Calculation Method” field select “ Scheduled Date, Requested Date” value.
Note: This will ensure that the Delivery’s initial pickup data is correctly set as per the scheduled ship date.
Page 14 of 95
PCross 6 Create Purchase Order and Sales Order
Responsibility: Purchasing
Business Approach:
Create a Standard PO(In our case created PO 6117). Set Ship-to and Bill-to to your organization (W1).
Create a line for crossdock planned item (testplnxdocitem) for qty (20) and enter promise date with time
details (10-Nov-2006 16:00:00).
Once can change the receipt routing to “Standard Receipt”.
Page 15 of 95
Responsibility: Order Management
Business Approach:
In our test case we created order 65333 for item ‘testplnxdocitem’ for qty 10.
Page 16 of 95
PCross 7 Run Pick Release
Two new allocation methods are available ‘Cross Dock Only’ and ‘Prioritize Cross Dock’. We select
‘Cross Dock Only’ for allocation method.
Page 17 of 95
Page 18 of 95
PCross 8 View Reservations
We enter organization (W1) and item (testplnxdocitem). A new filed is added to reservation inquiry
‘Include Crossdock’. We check that field. Now we select ‘Find’ button.
Page 19 of 95
You can see the Demand & Supply and the planned reservation for crossdock. The crossdock field
shows ‘Yes’.
Page 20 of 95
PCross 9 View Sales Order From Shipping Transactions
When you query up the sales order you will see that the line status is Planned For Crossdocking.
Page 21 of 95
PCross 9 Perform PO Receipt
Page 22 of 95
PCross 10 Verify Planned Cross Dock task
Page 23 of 95
Under Inbound Plan select Plan Type “Cross-docking”.
Under Inbound tab select the purchase order (6117). Select ‘Find’ button.
Page 24 of 95
You will now be able to see the crossdock plan task.
Page 25 of 95
PCross 11 Execute Cross Docking
You will see that system directly suggests the staging subinventory/Locator , thus doing cross docking.
Page 26 of 95
Planned Cross Docking With ASN as Supply and SO as Demand:
In this scenario we are going to have Supply as “ASN”, Demand as “Sales Order
Scheduled”, Allocation Method= Priortize Inventory, ensuring remaining lines are
allocated from cross dock supply
Scenario:
In this example we will show how Planned Crossdocking happens for an ASN as supply and Sales Order
as Demand. We will define an item and assign it to organization W1. Then we will create a PO for the
item for qty 10. Create an ASN for the PO. Create a Sales Order for the item for qty10.
Do Miscellaneous Alias receipt for qty 7. Run pick release with allocation method as “Prioritize Inventory”.
Then we review the reservations created. You will see that there are 2 reservations created. One for
quantity 7, for the quantity available in inventory. The second for quantity 3 against the ASN. Then we
execute the cross docking.
Page 27 of 95
Planned Crossdocking:
Page 28 of 95
We have selected ASN as the supply.
Page 29 of 95
PACross 2 Define Item
Business Approach:
Define an Item and assign it to child organization where you will be doing the transaction.
In our example we have defined item ‘testitem’.
Page 30 of 95
PACross 3 Setup Crossdock criteria assignment
Business Approach:
Page 31 of 95
PACross 4 Create Crossdock Operation Plan
Business Approach:
Page 32 of 95
PACross 5 Order Management & Shipping Parameter Setup
Page 33 of 95
Navigation: → Setup Æ Shipping Æ Global Parameters
For “Delivery Date Calculation Method” field select “ Scheduled Date, Requested Date” value.
Note: This will ensure that the Delivery’s initial pickup data is correctly set as per the scheduled ship date.
Page 34 of 95
PACross 6 Create Supplier & Supplier Sites
Complete the supplier site creation for W1 for ship to and bill to location.
Page 35 of 95
PACross 7 Create Supplier User & Register User
Responsibility: Purchasing Super User
Navigation: → Supply base → Supplier User Management → Supplier User Creation → Register
Supplier User
Page 36 of 95
Responsibility: Sysadmin
When the user is registered through Isupplier Portal a user is created and you can check it from sysadmin
/security/user and you can change the password.
Note: One needs to log in using this user id to create ASN’s.
Page 37 of 95
PACross 8 Create Purchase Order
Responsibility: Purchasing
Create a Standard PO(In our case created PO5416). Set Ship-to and Bill-to to your organization (W1).
Create a line for crossdock planned item (testitem) for qty (10) .One can change the receipt routing to
“Standard Receipt”.
Page 38 of 95
PACross 9 Create ASN
Responsibility: Isupplier Portal Full Access
Page 39 of 95
We select “Create Advance Shipment Notice” and create ASN. In our case we defined ‘cjptest1’.
Page 40 of 95
PACross 10 Create Sales Order
In our test case we created order 63714 for item ‘testitem’ for qty 10.
Page 41 of 95
PACross 11 Perform Alias Receipt
Page 42 of 95
PACross 12 Run Pick Release
Page 43 of 95
Pick slip report output.
Page 44 of 95
PACross 13 View Reservation
We enter organization (W1) and item (testitem). A new field is added to reservation inquiry ‘Include
Crossdock’. We check that field. Now we select ‘Find’ button.
Page 45 of 95
You will see 2 reservation records. One for quantity 7, against the quantity present in inventory. Second
against the ASN for quantity 3. You will see that the crossdock flag is set to ‘Yes’ for this record.
Page 46 of 95
PACross 14 View Sales Order From Shipping Transactions
When you query up the sales order you will see that the line status is “Planned For Crossdocking”.
Page 47 of 95
PACross 15 Perform Receipt for ASN
Page 48 of 95
PACross 16 Verify Task In Control Board
Page 49 of 95
PACross 17 Execute Cross Docking
Now when we try to do the putaway the system suggest the staging subinventory and locator
and suggest that the material can be crossdocked. We execute the cross docking.
Page 50 of 95
PACross 18 View Sales Order From Shipping Transactions
You will see that the line status is changed to “Staged/Pick Confirmed”.
Page 51 of 95
Opportunistic Crossdocking:
Opportunistic Crossdock
Supply driven - Supply of inbound material is dynamically crossdocked on arrival to fulfill a demand.
The newly received material can be crossdocked directly to backordered component requirements.
Supply from purchase order receipts and LPN-based completions will be considered. Both push and pull
component requirements will be considered for demand. A push requirement would be crossdocked
directly to the job, while a pull requirement would be crossdocked to the supply subinventory and locator.
Page 52 of 95
Opportunistic Crossdocking with Sales Order as Demand & PO as Supply:
Scenario:
In this example we will show how Opportunistic Crossdocking happens for a PO as Supply and Sales
Order as Demand. We will define an item and assign it to organization W1. Then we will create a PO for
the item for qty 10. Then we create a Sales Order for the item for qty10. Now we do PO receipt for
quantity of 10. When you try to do put away system will prompt you that crossdocking opportunity exists.
Execute cross docking.
Page 53 of 95
OCross 1 Define a Opportunistic Crossdock Criteria
Business Approach:
Page 54 of 95
Eligible demands for opportunistic crossdock
Sales Order, Internal Order, WIP components (Discrete, Repetitive, and lot based jobs)
Page 55 of 95
OCross 2 Define Item
Business Approach:
Page 56 of 95
OCross 3 Setup Crossdock criteria assignment
Business Approach:
Two new Rule Types are introduced in R12. Planned Crossdock & Opportunistic Crossdock.
In our Opportunistic Cross dock test we will select Opportunistic Crossdock type.
We create a new assignment with a sequence number. Lower the sequence higher the precedence.
Page 57 of 95
In our case we have assigned sequence 30 . Then we have selected the crossdock criteria we had
defined (CJP CROSS DOCK OPPORTUNISTIC). We select organization (W1) and select the crossdock
planned item (testoprxdocitem). Select ‘Always’ in the Date Type column. Check ‘Enabled’.
Note: Always remember to run ‘Generate All Rules’ Concurrent program after you have defined any new
rule or made changes to existing rule.
Page 58 of 95
OCross 4 Setup Organization Parameters
Business Approach:
Page 59 of 95
OCross 5 Create Crossdock Operation Plan
Business Approach:
On operation select Cross dock. In cross dock method select appropriate cross dock method. In our
example we select ‘(Default) LPN based consolidation in staging lane within delivery’.
The other options are:
Locator based consolidation in consolidation locator, within delivery in staging lane
LPN based consolidation in consolidation locator, within delivery in staging lane
Direct consolidation in staging lane within delivery
LPN based consolidation in staging lane across deliveries
Direct consolidation in staging lane across deliveries
LPN based consolidation in consolidation locator, across deliveries in staging lane
Locator based consolidation in consolidation locator, across deliveries in staging lane
Page 60 of 95
OCross 6 Shipping Parameter Setup
Business Approach:
Page 61 of 95
OCross 7 Create Purchase Order
Responsibility: Purchasing
Business Approach:
Page 62 of 95
OCross 8 Create Sales Order
Responsibility: Order Management
Business Approach:
Page 63 of 95
Page 64 of 95
OCross 9 Execute PO Receipt
We receive against the purchase order (7046). We receive the item into the receiving subinvenory locator
and into LPN LPN863A.
Page 65 of 95
OCross 10 View Reservation
Page 66 of 95
Page 67 of 95
OCross 11 Execute Cross Docking
We enter the LPN number(In our case LPN863A). As we confirm the subinventory we get the message
“Crossdock material exists. Crossdock will be performed. Press any key to continue.”
Then we enter the locator information and select “Drop Full LPN”.
Page 68 of 95
OCross 12 View Sales Order From Shipping Transactions
Select Lines and LPN’s from the query window and then put in the order number. In our case the order
number was 70747. You will see that line status is “Staged/Pick Confirmed”.
Page 69 of 95
OCross 13 View Reservation
Responsibility: Warehouse Manager
Page 70 of 95
Page 71 of 95
Opportunistic Crossdocking with WIP Component Demand:
Scenario:
In this example we will show how Opportunistic Crossdocking happens for a PO as Supply and
backordered WIP component as Demand. We will define an item and assign it to organization W1. Then
we will create a BOM & Routing for the assembly including the component. We run Component Pick
Release. Then we create a Purchase Order for the item. Now we do PO receipt. When you try to put
away, system will prompt you to do the cross docking by suggesting the job. Execute cross docking.
Page 72 of 95
OWCross 1 Define a Opportunistic Crossdock Criteria
Business Approach:
Page 73 of 95
OWCross 2 Define Item
Page 74 of 95
OWCross 3 Setup Crossdock criteria assignment
Business Approach:
Page 75 of 95
OWCross 4 Setup Organization Parameters
Business Approach:
Page 76 of 95
OWCross 5 Create Crossdock Operation Plan
Business Approach:
Page 77 of 95
OWCross 6 Create BOM
Page 78 of 95
Page 79 of 95
OWCross 7 Create Routing
Page 80 of 95
OWCross 8 Create Job
Page 81 of 95
Page 82 of 95
OWCross 9 Run Component Pick release
Page 83 of 95
OWCross 10 Create Purchase Order
Responsibility: Purchasing
Page 84 of 95
OWCross 11 Execute PO Receipt
We receive against the purchase order (7047). We receive the item into the receiving subinvenory locator
and into LPN LPN864A.
Page 85 of 95
OWCross 12 Move Assembly
Page 86 of 95
OWCross 13 Execute Cross Docking
Page 87 of 95
OWCross 14 Verify Job
When you query up the job you will see in the issued column that the material was issued to the job.
Page 88 of 95
Cross dock exceptions:
(Please refer to R12 WMS User Guide Pg 6-12)
Oracle Warehouse Management uses a concurrent program to check for exceptions and
assign an exception code to each exception. It uses the parameter Look-Ahead Time to
check whether incoming supply is available for crossdocking. The concurrent program
checks for all supply scheduled to arrive in the warehouse within the exception
look-ahead time window. It considers the past-due supply and assumes the
supply-scheduled receipt date and time is the current system date and time. It uses the
supply source and the crossdocking reservation and determines the corresponding
demand source. The concurrent program divides the future time window for the supply
into four zones. The concurrent program uses these zones to categorize the different
exception types.
If crossdocked demand lies in zone one, then the remaining time for crossdocking is less
than the order processing time. The system cannot perform a crossdock and records an
error. If the supply source is late, then the system records a late exception. If the supply
is not late, then the system records a schedule exception.
If crossdocked demand lies within zone two, the remaining crossdock time is more than
Page 89 of 95
the order processing time, but less than the order processing time + buffer time. Though
the system can still perform crossdocking, you may need to manually expedite the
supply. In this case, the system records a warning exception code. If the supply source
is past due, then the system records a late exception. If the supply is not late, then it
records a schedule exception.
If crossdocked demand lies within zone three, the remaining crossdock time is more
than the order processing time + buffer time, but less than the order processing time +
buffer time + crossdock window. This implies that crossdocking is possible without
manual expedite, and the system does not record an exception.
If crossdocked demand lies within zone four, the remaining crossdock time is more
than the order processing time + buffer time + crossdock window. Though crossdocking
is possible, an unnecessary wait time is required for the inbound material before you
can ship the order; therefore, the system records a scheduled exception with the code warning.
Page 90 of 95
Planned & Opportunistic Cross Docking:
The “Planned” depiction of crossdock window(CW), Buffer Time (BT), and Order Processing
Time (OPT) will be used in Planned Crossdocking process for backward scheduling. Similarly
“Opportunistic” depiction will be used for Opportunistic Crossdocking process for forward
scheduling.
Page 91 of 95
Crossdocking and Change Management :
(Please Refer to R12 User Guide Pg 6-8)
You can make changes to supply and demand sources after the system links the supply
and demand. The following tables display the changes the system makes if you modify
supply and demand sources.
Page 92 of 95
Page 93 of 95
Page 94 of 95
Debugging Issues:
The following are the requirements from support for logging a tar.
• Screen shots of the issue along with a good scenario.
• Pick release log files :
Set profile options
OM: Debug set to level 5
OM: Debug log directory = <first directory path returned by sql query
select value from v$parameter where name = 'utl_file_dir';>
INV: Debug Trace = YES
INV: Debug File = [directory value from above query]/logfilename.log (make sure that you have
write permission for this file and directory)]
INV: Debug Level = 9
While running pick release please select Tools from Tool bar and “Check” debug.
Upload the pick release log file and the inventory debug log file.
• In case there are issues with completing the cross dock transaction on mobile that please also
upload the mobile log files.
1. set mwa.cfg to trace level. To do this go to the mwa server config file,
/mwa/secure/mwa.cfg, and modify log level to trace
2. restart the mobile server and hit ctrl-X, see what directory is for the logging
3. perform the transaction again and get the following log files from that log directory
[port].INV.log
[port]WMS.log
[port].system.log
Inventory Debug log from the directory set in profile 'INV: Debug File’
Page 95 of 95