Beruflich Dokumente
Kultur Dokumente
Referring to the above inspection, outstanding works which require your action as follows;-
NO OUTSTANDING WORKS
WWCT/SBT (CIVIL WORKS)
1 Reinstate existing sump
2 Reinstate existing sewer pipes
3 Painting of WWCT/SBT
4 Water Tightness Testing
5 Backfilling works for WWCT/SBT
GEOTUBE (CIVIL WORKS)
6 Construction of ramp for Geotube
7 Installation of Geotube
POLYMER BUILDING (CIVIL WORKS)
8 Installation of roof truss, covering & accessories
9 Installation of roller shutter, door and window
10 Plastering (external & internal)
11 Installation of frame & ceiling (external & internal)
12 Painting (external & internal)
13 Electrical wiring works
14 Construction of drain, apron & ramp for Polymer Building
PIPEWORKS
15 Excavation & backfilling works
16 Pipe laying & jointing
17 Miscellaneous works, cleaning & testing works
MECHANICAL WORKS
18 Delivery of Crane / Lifting Equipment, High Pressure Rubber Hose (WWCT/SBT)
19 Construction of Horizontal Screw Pump Pit (WWCT/SBT)
20 Installation of Submersible Mixer (WWCT/SBT)
21 Installation of Crane / Lifting Equipment, High Pressure Rubber Hose (WWCT/SBT)
22 Installation of Horizontal Screw Pump, Submersible Pump, Pipes, Fittings & Valves (WWCT/SBT)
23 Installation of Submersible Sludge Pump Pipes, Fittings & Valves (Existing Sedimentation Tank)
24 Delivery of Metering Pumps, Crane/Lifting Equipment, Static Mixer & Sludge Blender (Polymer Plant)
25 Fabrication of Mixing & Service Tank (Polymer Plant)
26 Fabrication of Hopper, Feeder & Pump Skid (Polymer Plant)
27 Fabrication of Local Control Panel (Polymer Plant)
28 Installation of Mixing & Service Tank (Polymer Plant)
29 Installation of Hopper, Feeder & Pump Skid (Polymer Plant)
30 Dosing Pipeworks (Polymer Plant)
31 Installation of Local Control Panel (Polymer Plant)
32 Installation of Crane/Lifting Equipment, Static Mixer & Sludge Blender (Polymer Plant)
33 Delivery of 100mm dia. Butterfly Valves & Booster Pump (Miscellaneous)
34 Installation of Booster Pump Set, Air Compressor Set & Penstock/Valves (Miscellaneous)
ELECTRICAL WORKS
35 Delivery of Switchboard/MCC Panel
36 Installation of Switchboard/MCC Panel
NO OUTSTANDING WORKS
37 Delivery of Submain Cable for MMC-SDP-Palong
38 Installation of Submain Cable for MMC-SDP-Palong
39 Delivery of Distribution & Earthing System
40 Installation of Distribution & Earthing System
41 Delivery of Compound Lighting System
42 Installation of Compound Lighting System
43 Miscellaneous works
INSTRUMENTATION WORKS
44 Fabrication & delivery of Instrument Panel
45 Installation of Instrument Panel
INFRASTRUCTURE WORKS
46 Site clearance, levelling & compaction
47 Lay of crusher-run & premix
SITE HANDOVER WORKS
48 Preparation of Testing & Report
49 Pre-commissioning
50 Setting to Work
51 Commissioning & Training
Any delay in completing the above outstanding works will delay the process of handing over. Please notify us
after all comments have been attended and completed for re-inspection.
……………………………………………. …………………………………………….
En. Mohd Ishak Kasim En. Zulkurnain Tunggak