Sie sind auf Seite 1von 5

Name of work : Rate analysis for valve chamber (1.5 m X 1.

5 m X 1 m)
ABSTRACT
Sr Qty. Item Unit Rate Rate incl. Amount
No. (Rs.) 10% Tribal (Rs.)
& 1% & 1%
Labour (Rs.)

Valve Chamber 10%


1 ITEM NO-1
Excavation for Chamber
Excavation for valve chamber incl. all safety provisions using
site rails and stacking excavated stuff up to a lead of 90 mts.
cleaning the site etc. complete for lifts and strata as specified.
4.85 For 0 m to 1.5 m Cu.m. 132 145.2 704.22
(GWSSB SOR 14-15 WS,Sec-B, I.8)
2 ITEM NO-2
PCC
Providing and casting in situ mass cement concrete in grade M-
10 (approx. corresp. to prop. 1:3:6) using granite quartzite trap
metal of size 12 mm to 25 mm incl. consolidation curing etc.
complete.
0.8 Without form work Cu.m. 3698 4067.8 3254.24
(GWSSB SOR 14-15 WS,Sec-C, I.2)
3 ITEM NO-3
RCC Work
Providing and casting in situ C.C. in grade M-15 (proportions
as per mix design or as per Table 9 of IS456
2000 in masses by weigh batching ) using granite, quartzite
trap metal of size 6 mm to 20 mm for RCC work, including
scaffolding centering, form work, needle vibrated
consolidation, curing comp. up to 6 meter depth or height
(excluding cost of reinforcement and neat finishing) with
centering and shuttering etc. comp. for structure for other than
water retaining.
RCC work for Precast Cover in Pieces
0.23 Without form work Cu.m. 4498 4947.8 1137.99
(GWSSB SOR 14-15 WS,Sec-C, I.3)
4 ITEM NO-4
Steel reinforcement for RCC work
9.20 Supplying cutting, bending, binding and placing in position kg 60.08 66.09 608.03
steel as per plan and design and as per ISS 2502 including cost
of steel and binding wire for reservoirs/structures only
including lift up to 6 meter height or depth below G.L. for all
diameters - Do- Thermo mechanically treated (TMT)bars Fe-
415 grade for all diameters.
(GWSSB SOR 14-15 WS,Sec-C, I.9.2)
5 ITEM NO-5
Brick Work
Brick work using common burnt building bricks having crushing
strength not less that 35 Kg/Cm2 foundation and plinth in
cement mortar 1:6 (1 cement: 6 fine sand)
1.59 (B) Conventional Cu.m. 2820 2848.2 4528.64
(R & B SOR, 15-16, ch 6, Pg 79 Item.No. 9)
6 ITEM NO-6
Cement Plaster
Providing 20 mm. thick cement plaster in single coat on single
or half brick walls for interior plastering upto floor two level
and finished even smooth in even smooth in 1:3 (1 cement : 3
fine sand ) & finishing with a floating coat of neat cement
slurry.
6 Inside Cement Plaste for Chamber wall Sq.mt. 167.3 168.97 1013.82
(R & B SOR, 15-16, ch 17, Pg 154, S.No.7+10)
7 ITEM NO-7
Refilling of excavated earth
0.98 Refilling extra excavated earth incl. ramming, watering, cu.m 22.00 24.20 23.72
consolidating disposal of surplus stuff as directed within a
radius of 3 km.
(GWSSB SOR 14-15 WS,Sec-C, I.9.2)
8 ITEM NO-8
C.I. Steps
6.00 Providing and fixing cast iron steps of size 500mmx 150 mm X No 177.00 178.77 1072.62
22.5 mm and painting with two coats of anticorrosive paint
etc. complete.
(R & B SOR, 15-16, ch 24, Pg 195, S.No.50)
TOTAL 12343.28
Say (Rs.) 12350
Extra depth for Valve Chamber
1 ITEM NO-1
Excavation for extra depth of Chamber
Excavation for valve chamber incl. all safety provisions using
site rails and stacking excavated stuff up to a lead of 90 mts.
cleaning the site etc. complete for lifts and strata as specified.
5.11 For 0 m to 3 m Cu.m. 308 338.8 1731.27
(GWSSB SOR 14-15 WS, Sec-B, I.8) (Note: Average rate of 0 m to
3 m depth is considered.
2 ITEM NO-2
Brick Work
Brick work using common burnt building bricks having crushing
strength not less that 35 Kg/Cm2 foundation and plinth in
cement mortar 1:6 (1 cement: 6 fine sand)
1.59 (B) Conventional Cu.m. 2820 2848.2 4528.64
(R & B SOR, 15-16, ch 6, Pg 79 Item.No. 9)
3 ITEM NO-3
Cement Plaster
Providing 20 mm. thick cement plaster in single coat on single
or half brick walls for interior plastering upto floor two level
and finished even smooth in even smooth in 1:3 (1 cement : 3
fine sand ) & finishing with a floating coat of neat cement
slurry.
6 Inside Cement Plaster for Chamber wall Sq.mt. 167.3 168.97 1013.82
(R & B SOR, 15-16, ch 17, Pg 154, S.No.7+10)
4 ITEM NO-4
Refilling of excavated earth
1.27 Refilling extra excavated earth incl. ramming, watering, cu.m 22.00 24.20 30.70
consolidating disposal of surplus stuff as directed within a
radius of 3 km.
(GWSSB SOR 14-15 WS, Sec-C, I.9.2)
5 ITEM NO-5
C.I. Steps
6.00 Providing and fixing cast iron steps of size 500mmx 150 mm X No 177.00 178.77 1072.62
22.5 mm and painting with two coats of anticorrosive paint
etc. complete.
(R & B SOR, 15-16, ch 24, Pg 195, S.No.50)
TOTAL 8377.05
Say (Rs.) 8380
Name of work : Rate analysis for valve chamber (1.5 m X 1.5 m X 1 m)
MEASUREMENT SHEET
L (m) W (m)
Inside Dimension - 1.50 1.50 Counterfort part from wall for Base - 0.00
Height of Chamber above GL - 0.20 Counterfort part from Base for PCC - 0.15
Depth of Chamber below GL up to pipe IL - 0.50 Excavation Offset - 0.00
Depth of Chamber from pipe IL to Bottom - 0.30 Thickness of RCC Base - 0.00
Total depth of chamber (0.2 + 0.5 + 0.3) m - 1.00 Thickness of PCC - 0.15
Chamber Wall thickness - 0.23 RCC Cover Thickness - 0.10
C.I. Steps c/c distance - 0.175
SR NO ITEM UNIT Nos L(M) WIDTH(M) DEPTH(M) QTY
Valve Chamber
1 ITEM NO-1
Excavation for Chamber
For 0 m to 1.5 m Cu.m. 1 2.26 2.26 0.95 4.85
2 ITEM NO-2
PCC Cu.m. 1 2.26 2.26 0.15 0.77
Supporting Block Cu.m. 1 0.3 0.3 0.3 0.03
0.8
3 ITEM NO-3
RCC Work
RCC work for Precast Cover in Pieces Cu.m. 1 1.50 1.50 0.10 0.23
Total RCC qty 0.23
4 ITEM NO-4
Steel reinforcement for RCC work
By volume of concrete kg 40 kg/cum X 0.23 Cum 9.2
5 ITEM NO-5
Brick Work
Brick Masonary Cu.m. 1 6.92 0.23 1 1.59
Total Qty 1.59
6 ITEM NO-6
Cement Plaster
Inside Cement Plaster
For Chamber Wall Sq.mt. 2 1.5 1 3
Sq.mt. 2 1.5 1 3
Total for Inside Plaster = 6
7 ITEM NO-7
Refilling of excavated earth
Total excavation cu.m 4.85
Deduction - qty of PCC cu.m -0.8
Qty excavated for Chamber below cu.m -1.00 1.96 1.96 0.80 -3.07
G.L.
Total qty for refilling 0.98
8 ITEM NO-8
C.I. Steps No 6 6
Extra depth for Valve Chamber
1 ITEM NO-1
Excavation for extra depth of Chamber
For 0 m to 3 m Cu.m. 1 2.26 2.26 1 5.11
2 ITEM NO-2
Brick Work
Brick Masonry Cu.m. 1 6.92 0.23 1 1.59
Total Qty 1.59
3 ITEM NO-3
Cement Plaster
Inside Cement Plaster
For Chamber Wall Sq.mt. 2 1.5 1 3
Sq.mt. 2 1.5 1 3
Total for Inside Plaster = 6

4 ITEM NO-4
Refilling of excavated earth
Total excavation cu.m 5.11
Qty excavated for Chamber below cu.m -1.00 1.96 1.96 1.00 -3.84
G.L.
Total qty for refilling 1.27
5 ITEM NO-5
C.I. Steps No 6 6