Intake RC retaining wall concrete work


Description L(m) W1(m) W2(m) H(m) R1(m) R2(m) Area (m2) Nr
Footing pad
Lean concrete
Below pads 1.000 1.000 270.000 1

SUB TOTAL= 270.000

Pad and wall 5.900 68.830 1.000 1


Beam 0.500 0.500 52.850 1
SUB TOTAL=

CONTRACTOR
Name ___________
Signature_______________
Date_______________
crete work
Volume (m3) remark

406.097
13.213
419.310

CONSULTANT
Name _________________
Signature__________________
Date__________________
Consultant - SWS Consultancy
Raw water header tank form work
Description L(m) W1(m) W2(m) H(m) R1(m) R2(m) Area (m2) Nr
Footing pad
2.700 2.000 2.000 10.800
68.830 1.100 1.000 75.713
Wall&Beam 6.170 68.830 2.000 849.362
SUB TOTAL= 935.875

CONTRACTOR
Name ___________
Signature_______________
Date_______________
m work
Volume (m3) remark

CONSULTANT
Name _________________
Signature__________________
Date__________________
Consultant - SWS Consultancy
Raw water header tank form work
Description L(m) W1(m) W2(m) H(m) R1(m) R2(m) Area (m2) Nr

Excavation 68.830 25.370 1.000 1746.217


Deduction Concrete Volume 432.810
Back Fill 1313.408

CONTRACTOR
Name ___________
Signature_______________
Date_______________
m work
Volume (m3) remark

CONSULTANT
Name _________________
Signature__________________
Date__________________
Consultant - SWS Consultancy
In take stone pitching
Description A(m2) N At remark

1.000 10.580 1.000 10.580


2.000 78.900 1.000 78.900
3.000 17.200 1.000 17.200
4.000 136.900 1.000 136.900
5.000 225.000 1.000 225.000
6.000 1.180 1.000 1.180
7.000 142.860 1.000 142.860
8.000 64.550 1.000 64.550
9.000 8.000 2.000 16.000
10.000 88.440 2.000 176.880
Total 870.050

CONTRACTOR CONSULTANT
Name ___________ Name _________________
Signature_______________ Signature__________________
Date_______________ Date__________________
Consultant - SWS Consultancy
In take Cocrete culvert pipe on C-20 concrete class A bedding
Description L N Total L. remark

precast concrete 12.000 15.000 180.000


Total 180.000

CONTRACTOR CONSULTANT
Name ___________ Name _________________
Signature_______________ Signature__________________
Date_______________ Date__________________
Consultant - SWS Consultancy
In take head wall masonry
L H Wavg. N V (m3) remark

1 7.290 2.520 1.010 2.000 37.109


2 10.680 2.720 1.010 2.000 58.680
3 15.330 3.030 1.010 2.000 93.829
4 4.000 2.180 1.010 2.000 17.614
Total 207.232

Consultant - SWS Consultancy


In take head wall and culvert excavation
A L N V (m3) remark
1 32.160 2.620 2.000 168.518
Total 168.518

Consultant - SWS Consultancy


In take head wall and culvert Backfill
A L N V (m3) remark
1 0.930 38.800 2.000 72.168
Total 72.168

Consultant - SWS Consultancy


In take lean concrete under head wall
W L N V (m3) remark
1 1.720 38.800 2.000 133.472
Total 133.472