Client Petroleum Development Oman LLC Vendor/Supplier Galfar Engineering & Contracting S.A.O.G.
Sub -Vendor/Supplier NA
Project Title Fayyadh Sayyala Gross Pipeline
Local Agent (Oman) NA
Material Inspected
PDO PO Item Quantity Nos. Mtr. Item description Serial No/Tag No/Heat
No No/Batch No
As per PO Actual Inspected
1.0 Summary:
Visit was made to M/s Galfar Engineering & Contracting S.A.O.G, at Nizwa, to carry-out Stagewise inspection for the Fabrication &
Assembly of MSV Skid as per the approved Inspection and Test Plan.
Refer Clause 13.1 of this report and attached vendor Reports for further details.
Record of Hours
Inspection Engineer: N.Mohan Raj Reviewed Oman Coordinator : H S Bal Reviewed by: Arun Kumar
Report Headings:
1.0 SUMMARY 2. 0 PERSONS PRESENT 3.0 DOCUMENTATION USED/APPROVAL STATUS 4.0 DOCUMENTATION REVIEW 4.1 FAT 5.0 VENDOR PERSONAL QUALIFICAITON 6.0 MEASURING INSTRUMENTS CALIBRATION
DETAILS 7.0 WELDING INSPECTION 8.0 VISUAL INSPECITON 9.0 HEAT TREATMENT 10.0 NON DESTRUCIVE TESTING(NDT) 11.0 HYDROSTATIC/PNEUMATIC TESTING 12.0 METALLURGICAL/ CORROSION TESTING -
13.0 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.1 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.2 REPAIR REQUIREMENTS 14.0 BALSTING /PAINTING/COATING/LINING 15.0
BALANCE ACTIVITIES 16.0 AREAS OF CONCERN /REMARKS 17.0 HSE/ENVIRONMENTAL CONDITION 18.0 NEXT VISIT/EXIT CALL 19.0 MANDATORY ATTACHMMENTS 20.0 PHOTOGRAPHS .
Document title Document no. Revision/ year of edition Approval code/Approved by / Remarks
ITP MED-QCP-846-002 2 / Jan-2016 Code A / Approved by ONE 461
NA
Report Headings:
1.0 SUMMARY 2. 0 PERSONS PRESENT 3.0 DOCUMENTATION USED/APPROVAL STATUS 4.0 DOCUMENTATION REVIEW 4.1 FAT 5.0 VENDOR PERSONAL QUALIFICAITON 6.0 MEASURING INSTRUMENTS CALIBRATION
DETAILS 7.0 WELDING INSPECTION 8.0 VISUAL INSPECITON 9.0 HEAT TREATMENT 10.0 NON DESTRUCIVE TESTING(NDT) 11.0 HYDROSTATIC/PNEUMATIC TESTING 12.0 METALLURGICAL/ CORROSION TESTING -
13.0 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.1 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.2 REPAIR REQUIREMENTS 14.0 BALSTING /PAINTING/COATING/LINING 15.0
BALANCE ACTIVITIES 16.0 AREAS OF CONCERN /REMARKS 17.0 HSE/ENVIRONMENTAL CONDITION 18.0 NEXT VISIT/EXIT CALL 19.0 MANDATORY ATTACHMMENTS 20.0 PHOTOGRAPHS .
Not Applicable
10.0 Non Destructive testing (NDT):
Witnessed &
LPT Reviewed & Accepted Not Offered /Pending Not Applicable As per ASTM As per ISO
Accepted
Witnessed &
MPI Reviewed & Accepted Not Offered /Pending Not Applicable As per ASTM As per ISO
Accepted
UT Witnessed &
Reviewed & Accepted Not Offered /Pending Not Applicable As per ASTM As per ISO
Accepted
Witnessed &
RT Films reviewed Not Offered /Pending Not Applicable As per ASTM As per ISO
Accepted
Witnessed &
ECT Reviewed & Accepted Not Offered /Pending Not Applicable As per ASTM As per ISO
Accepted
Overlay Witnessed &
Reviewed and Accepted Not Offered /Pending Not Applicable Not Satisfactory /Rejected
Thickness Accepted
Hardness Witnessed &
Reviewed and Accepted Not Offered /Pending Not Applicable Not Satisfactory /Rejected
Check Accepted
NA
12.1 API Q1, 9th Ed Certification of Facility: Active Withdrawn Transitioned Not Certified
Report Headings:
1.0 SUMMARY 2. 0 PERSONS PRESENT 3.0 DOCUMENTATION USED/APPROVAL STATUS 4.0 DOCUMENTATION REVIEW 4.1 FAT 5.0 VENDOR PERSONAL QUALIFICAITON 6.0 MEASURING INSTRUMENTS CALIBRATION
DETAILS 7.0 WELDING INSPECTION 8.0 VISUAL INSPECITON 9.0 HEAT TREATMENT 10.0 NON DESTRUCIVE TESTING(NDT) 11.0 HYDROSTATIC/PNEUMATIC TESTING 12.0 METALLURGICAL/ CORROSION TESTING -
13.0 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.1 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.2 REPAIR REQUIREMENTS 14.0 BALSTING /PAINTING/COATING/LINING 15.0
BALANCE ACTIVITIES 16.0 AREAS OF CONCERN /REMARKS 17.0 HSE/ENVIRONMENTAL CONDITION 18.0 NEXT VISIT/EXIT CALL 19.0 MANDATORY ATTACHMMENTS 20.0 PHOTOGRAPHS .
14.0 Blasting/Painting/Coating/Lining:
Painting Visual Inspection, Final DFT, Cure Test, Holiday Test & Adhesion Test for the MSV Skid carried out and found
accepted.
15.0 Balance activities:
ITP Sl. Inspection /Activity TPI scope Proposed inspection date
No.
---- ---- ---- ----
16.0 Areas of concern/Remarks:
Nil
Completed
19.0 Mandatory
NCR FAT-R/TAT-R Heat treatment report HIC report Punch list
attachments:
20.0 PHOTOGRAPHS:
Report Headings:
1.0 SUMMARY 2. 0 PERSONS PRESENT 3.0 DOCUMENTATION USED/APPROVAL STATUS 4.0 DOCUMENTATION REVIEW 4.1 FAT 5.0 VENDOR PERSONAL QUALIFICAITON 6.0 MEASURING INSTRUMENTS CALIBRATION
DETAILS 7.0 WELDING INSPECTION 8.0 VISUAL INSPECITON 9.0 HEAT TREATMENT 10.0 NON DESTRUCIVE TESTING(NDT) 11.0 HYDROSTATIC/PNEUMATIC TESTING 12.0 METALLURGICAL/ CORROSION TESTING -
13.0 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.1 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.2 REPAIR REQUIREMENTS 14.0 BALSTING /PAINTING/COATING/LINING 15.0
BALANCE ACTIVITIES 16.0 AREAS OF CONCERN /REMARKS 17.0 HSE/ENVIRONMENTAL CONDITION 18.0 NEXT VISIT/EXIT CALL 19.0 MANDATORY ATTACHMMENTS 20.0 PHOTOGRAPHS .
Report Headings:
1.0 SUMMARY 2. 0 PERSONS PRESENT 3.0 DOCUMENTATION USED/APPROVAL STATUS 4.0 DOCUMENTATION REVIEW 4.1 FAT 5.0 VENDOR PERSONAL QUALIFICAITON 6.0 MEASURING INSTRUMENTS CALIBRATION
DETAILS 7.0 WELDING INSPECTION 8.0 VISUAL INSPECITON 9.0 HEAT TREATMENT 10.0 NON DESTRUCIVE TESTING(NDT) 11.0 HYDROSTATIC/PNEUMATIC TESTING 12.0 METALLURGICAL/ CORROSION TESTING -
13.0 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.1 INSPECTION/ACTIVITY CARRIED OUT/ RESULT & CONCLUSION 13.2 REPAIR REQUIREMENTS 14.0 BALSTING /PAINTING/COATING/LINING 15.0
BALANCE ACTIVITIES 16.0 AREAS OF CONCERN /REMARKS 17.0 HSE/ENVIRONMENTAL CONDITION 18.0 NEXT VISIT/EXIT CALL 19.0 MANDATORY ATTACHMMENTS 20.0 PHOTOGRAPHS .