Beruflich Dokumente
Kultur Dokumente
#3 @ 9 in. C/C
#3 @ 9 in. C/C
#3 @ 9 in. C/C
#3 @ 9 in. C/C
#4 @ 9 in. C/C
DEPTH = 5 in
#4 @ 9 in. C/C
Weight
Dia. Length No. No.3 No.4 No.5 No.6
Shorter Bottom 3 2.82 15 24
3 2.82 15 24
Longer Bottom 3 6.11 7 24
3 6.11 7 24
Shorter Top 3 1.14 29 18
4 0.91 29 26
Longer Top 3 2.24 13 16
4 1.72 13 22
Shorter Hangers 3 1.57 2 2
Longer Hangers 3 3.61 0 0
Total weight in kgs: 138 51 0 0 G.Total= 189
Volume of Concrete = 85.68 Cft Dry vol. = 145.1 Unit Unit Rate Amount
Steel (40), Cost per kg = 40 Rs. Cement= 16.6 Bags @ 400.00 6635
Steel (60), Cost per kg = 72 Rs. Sand = 41.5 Cft @ 15.00 622
Concrete per Cft = 250.00 Rs. Aggregate 82.9 Cft @ 100.00 8294
Total Cost of Slab = 35099 Rs. Steel = 190.0 Kgs @ 72.00 13680
Total Material Cost = 29231