Beruflich Dokumente
Kultur Dokumente
a) above 300 mm to 600 mm No 0.920 0.920 Add 3% for Tools and plants
b) above 600 mm to 900 mm No 3.500 3.500
c) above 900 mm to 1800 mm No 9.750 9.750
d) above 1800 mm to 2400 mm No 16.000 16.000
e) above 2400 mm to 3000 mm No 40.000 40.000
f) above 3000 mm No 78.710 78.710
Recommendation:
Replace the Item of works in S.No 2 of Existing Norms by the above
Justification:
In this Item of work in the existing Norms manpower for stacking the cut material and the filling depressions/pits are not included, the quantity of manpower
is as per the DoR and DoI norms
Page 1 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
2A 1-1.5(c) and Felling and uprooting of bamboo, clearing m3 2.8 2.8
(New) 1-1.6 the area, stacking of bamboo and disposing
of waste to 10 m (Volume of the excavated
area should be measured)
Recommendation:
Add this item of work as 2A in the existing norms
Justification:
This is the new item of works is added in existing DoLIDAR norms and prepared as per DoR and DoI norms
Page 2 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
3 1-2 Dismantling of culverts, bridges, pavements
and other structures. The operations covered 1. Pickaxes
are :
· dismantling 2. Spades
· excavation 3. Crowbars
· back filling 4. Shovels
· stacking 5. Hammers and chisels
· disposing 6. Doko/Baskets
Page 3 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
a-4) Plain cement concrete; PCC
i) 1:4:8 or leaner mix
. 1 m3 1.40 0.05 1.40 0.05 Add 3% of Labour cost for T &P
ii) 1:3:6 or richer mix 1 m3 2.30 0.05 2.30 0.05 Add 3% of Labour cost for T &P
b) Dismantling flexible and Cement concrete
Pavement
b-1) Flexible Pavement
(i) water bound Macadam materials including
soling/sub-base. 1 m3 0.890 0.010 0.890 0.010 Add 3% of Labour cost for T &P
(ii) Bitumenous materials 1 m3 2.420 0.010 2.420 0.010 Add 3% of Labour cost for T &P
b-2) Rigid Pavement as per (a-3) or (a-4)
c)Dismantling steel structures 1 tonne 6.000 1.000 6.000 1.000 Add 5% for pulleys, ropes, ladder,
gas, gas-cuttter & supporting
arrangement etc.
Page 4 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
g) Dismanlting R.C.C pipes
(excluding excavation & refilling)
i) upto 600mm dia. 1m 0.400 0.010 0.400 0.010 Add 3% of Labour cost for T &P
ii) above 600mm dia. 1m 0.800 0.010 0.800 0.010 Add 3% of Labour cost for T &P
h) Dismantling Gabion m3 1.000 0.100 1.000 0.100 Add 3% of Labour cost for T &P
Add 15% of Labour cost for Tools
i) Cutting reinforcement in dismentling RCC or like chisele, hackshaw or gas cutter,
RB work ( to be calculated on the basis of m2 1.200 0.100 gas etc.
cross-sectional area i.e length x thickness)
Recommendation:
Replace the Serial Number 3 with respective Clause of Specifications 1-2 of Work Norms for Construction, Rehabilitation and Maintenance of Rural Roads by above items of
works
Justifucation:
Dismantling work is used more in the maintenance of road and also often used in construction and rehabilitation works. It is also used in upgrading of the roads. The items of
works provided in S.No 3 having respective Specification Clause 1-2 does not indicate the type of brick and stone masonry to be dismantled. Also it is not clear for the
dismantling of flexible and rigid pavement, so dismentling of brick masonry and stone masonry are catagorised in two groups i) brick work in mud mortar and cememt mortar
and ii) stone masonry in dry masonry and cement mortar respectively. In addition to that items for dismantling of cement concrete is divided in two types i) Reinforced
Concrete and ii) Plane Cement Concrete similarly dismentaling of road pavement is provided in rigid and flexoible pavement. Flexible pavement is divided in two catagories
one WBM ie un-matelled surface and other of bituminous surface. Further more work items for dismentaling of RCC pipes as well as gabion structures are incorporated in
this item of works.
Page 5 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
5 2-1.2.2, 2-1.8 1. Picks; 2. Shovels; 3. Kodalo;
and 2-1.9 Excavation in roadway and drain including 4. Doko/Baskets; 5. Wheel barrows;
removal and satisfactory disposal of all 6. Crowbars; 7. Drilling machines; 8.
materials up to a lead of 50 m along the lead Petrol for plants; 9. Blasting materials
route. This includes handling and stacking or required for (e): gelatine = 0.25 kg;
hauling (to sites of embankment construction) detonator = 2 nos.; fuse wire = 2 m;
of suitable cut materials as required and also
the disposal of unsuitable cut materials in
specified manner. This further covers trimming
and finishing of the road way. For
Recommendation:
Person per day for a) ordinary soil is replaced by 0.75 instead of 0.60, b) hard soil (Incliding gravel/Boulder mixed soil) is replaced by 1.0 instedd of 0.70, e) hard rock
requiring blasting is replaced by 3.5 instead of 2 with additional of 0.1 personday for blasting and f) hard rock manual excavation is replaced by 12.0 instead of 17.00.
Justification:
In comparision with the working norms of DoR and DoI it is found that the manpower provided in sub-item (a); (b) and (e) is less where as in sub-item (f) is more so for these
four sub-items the man power is provided as per the DoR norms.
Page 6 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
9 2-4 1. Picks; 2. Shovels; 3. Kodalo;
Excavation for structures including cutting of
slopes, shoring, shuttering, planking, ordinary 4. Doko/Baskets; 5. Wheel barrows;
sealing and disposal of materials up to a lead of 6. Crowbars; 7. Drilling machines; 8.
50 m along the lead route in: Petrol for plants; 9. Blasting materials
required for (d):
a) ordinary soil 1 m3 0.90 1.00
b) hard soil 1 m3 1.50 2.00
c) ordinary rock 1 m3 4.00 4.00
d) medium rock 1 m3 8.00 8.00 Gelatine = 0.50 kg
e) hard rock (requiring blasting) 1 m3 4.50 0.12(blaster) 4.50 0.12(blaster) Detonator = 4 nos.
f) hard rock (chiselling, wedging, tempering,
1 m2 16.00 16.00 Fuse =4m
etc.)
g) special provision for preparation of rock
1 m3 0.50 0.50 Add 3% of Labour cost for T &P
foundation
h) marshy soil 1 m3 3.00 3.00 Portable Drill Machine 1 hr
Recommendation:
Person per day for a) ordinary soil is replaced by 0.9 instead of 1.0, b) hard soil (Incliding gravel/Boulder mixed soil) is replaced by 1.5 instedd of 2, e) hard rock requiring
blasting is replaced by 4.50 instead of 6 with additional of 0.1 personday for blaster and f) hard rock manual excavation is replaced by 16.00 instead of 30.00.
Justification:
In comparision with the working norms of DoR and DoI it is found that the manpower provided in sub-item (a); (b) ; (e) and (f) are more so for these four sub-items the
manpower is provided as per the DoR norms.
Page 7 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
10 2-5 Construction of roadway in 1. Picks; 2. Shovels; 3. Doko/
embankments and miscellaneous Baskets; 4. Wheel barrows; 5.
backfilling areas with approved material Rollers as specified in S. No. 6.
obtained either from
° excavation for road construction or 1 m3 0.50 0.50
° borrow pits or Add 0.04 for manual compaction;
° other sources If machanically compacted by roller
add working hour of roller 0.017 hr.
excluding the excavation (which shall be covered separately under S. No. 5)
and initial transportation (which shall be covered under S. No. 6 or 11)
components. In this case, lead is 50 m.
Recommendation:
Replace the manpower by 0.50 instead of 0.25. Add 0.04 man day for manual compoaction or 0.17 hr working hour of road roller if machanically compacted.
Justification:
In comparision with the working norms of DoR and DoI it is found that the manpower provided in item of work is less hence norms for this item of work is updated as per
DoR norms.
Page 8 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
14 2-5.7.5 Removal of unsuitable materials and 1. Picks; 2. Shovels; 3. Kodalo; 4.
replacement with suitable materials (same as Doko/Baskets; 5. Wheel barrows
S.No 5)
a) Ordinary soil 1 m3 1.75 1.75
g) Marshy soil 1 m3 2.00 2.00 Add 3% of Labour cost for T &P
Recommendation:
Delit the item works from (b) to (f) of S.No 14 with respective Clause of Specification 2-5.7.5
Justification:
Hard soil, ordinary rock, Medium rock, Hard rock bears high bearing capacity. Materials having CBR value more than 5 % is considered as the suitable materials for civil
engineering works. Hence for such types of soil replacement of suitable materials is not applicable. Quantity of man power is the sum of excavation as per S. No 5; and
replacement with suitable materials in lieu of removed unsuitable material as per S.No 6 (c)
15 2-5.7.6 and Scarifying existing granular/bituminous road surface for carrying out the required 1. Harrows; 2. Picks; 3. Shovels;
2-5.4.3 operations necessary to complete the work. This includes handling, salvaging, stacking and 4. Doko/Baskets; 5. Wheel
disposing of scarified material up to a lead of 100 m along the lead route. barrows or Bullock carts or Tractor
trailer
i) Granular Saurface (WBM) 1 m2 0.0445 0.0005 0.0445 0.0005
ii) Bituminous surface 1 m2 0.121 0.0005 0.121 0.0005
Recommendation:
Repalace the mandays in two sub-item of work instead one as provided in existing norms.
Justification:
Taking average thickness to be scarify as 100mm the manpower provided in S. No 3 (b-1) of this report (updated norms) the quantity of manpower required
per cubic metre is coverted to square meter.
Page 9 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
16 2-5.7.7 Dismantling and removal of existing 1 m3
cement concrete pavement (same as S.
No. 3.(a-3 or a-4))
a-3) Reinforce Cement Concrete 1 m3 3.25 0.05 3.25 0.05
a-4) Plain cement concrete;
i) 1:4:8 or leaner mix Add 3% of Labour cost for T &P
1 m3 1.40 0.05 1.40 0.05
ii) 1:3:6 or richer mix 1 m3 2.30 0.05 2.30 0.05
Recommendation:
Replace the manpower as above
Justification:
The manpower provide in existing norms is for backfill work by suitable materials for which separate norms is prepared as S.N. 25-A. Production of filter
material manually is incorporated in S.N. 25 of existing norms. The above quantity of manpower is as per the DoR norms.
Page 10 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
24 2-9.3.4, Providing and laying HDP pipes with
perforations including jointings (no. and
dia of holes to be specified)
2-9.4 a) series II, HDP pipe 250 mm dia m 0.10 0.10 0.10 0.10 HDP pipe = 1.0 m
and 2-9.5.2 Petrol = 0.20 lit.
Generator<2kva = 0.44 hr
screw jack = 0.32 hr
electric heaing plate= 0.32 hr
electric handdriller = 0.13 hr
b) series II HDP pipe 160mm dia m 0.90 0.08 0.09 HDP pipe = 1.0 m
HDP pipe
Petrol Petrol = 0.18 lit.
Generator<2kva = 0.40 hr
screw jack = 0.26 hr
electric heaing plate = 0.28 hr
electric handdriller = 0.13 hr
Justification:
The fittings of pipe are to be carried out manually which requires more skill manpower for joining the pipe with the help of heated plate, so the manpower is
changed as per DoR norms in this report
Page 11 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
25 A 2-9.3.2; Back filling in layers in foundaion pits, Add 3% of Labour cost for Tools
New 2-9.3.4; trenches, etc. including compaction and & Plants
2-9.3.6; watering all complete, lead 10m.
m3
2-9.4 and
2-9.5.2 a) Depth of foundation upto 1.5m 1.14 1.14 suitable material excavated for
b) Depth more than 1.5m upto 3m 1.62 1.62 foundation to be used.
c) Depth more than 3m upto 4.5m 2.10 2.10
d) Depth more than 4.5m upto 6m 2.58 2.58
e) Depth more than 6m.
Increase by 30% for every additional meter depth of foundation over the rate for the
previous depth.
Note : Add 5% of the total rate (except for transporation of material) for necessary testing as per specifications.
Recommendation:
This norms is prepared for the backfilling on the adjacent side of structures, which is replacement of S.No 17 and 25 of existing norms.
Justification:
The item of work provided in S.No 17 is for the manual backfilling of graded filter material and S.No. 25 is for backfilling of graded filter material with
manually production of graded filter material. So for the item of work, backfilling with suitable material of this norms is provided as per DoR norms.
Page 12 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
30-A ,4-7 Providing and spraying bituminious lit 0.046 0.003 Bitumen Boiler = .0025 hr
tack coat MC30/MC70 including MC30/MC70 = 1.05 ltr Sprayer =.0025 hr
cleaning the road surface using wire, Kerosene = 0.1 ltr Air compresser=.003 hr
brushes, broom etc. before applying Diesel = 0.275 ltr
tack coat.
Providing and spraying bituminious lit 0.620 0.003 Bitumen Boiler =0.014 hr
tack coat MC30/MC70 including MC30/MC70 = 1.05 ltr Hand Sprayer = 0.014 hr
cleaning the road surface using wire, kerosene = 0.1 ltr
brushes, broom etc. before applying
tack coat.
(for manual works)
Recommendation: Add this item of work for Prime coat on th WBM surface before application og Tack coat.
Justification:
This item of work is not provided in existing norms. This is the new item of work which is carried out on the WBM
surface before applying the Tack coat.
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
33, ,4-4 Laying of single/double /multiple Bitumen 80/100open = 1.05 ltr
34,35, bituminous coats for surface dressing Kerosene =.10 ltr
36 using river gravels ( grits) , shingles or Diesel = 0.27 ltr
broken stone chips including compactation lit 0.0140 0.0020 0.0140 0.0020 Boiler = 0.0025 hr
Distributor =.0025 hr
Air compresser=.0025 hr
Recommendation: Repalce the item of work peovided in S.No. 33,34,35 and 36 of existing norms by above norm.
Justification:
Page 13 of 49
The norms prepared for these items of works in old norms is not as per the guide line provided in the TRL Road Note -3 revised in 2000. So it is changed in
this report (updatednorms) as per the DoR norms.
Page 14 of 49
The man power provided for this item of work in existing norms is much less than compared with DoR and DoI norms. It is 15 and 12 mandays/metric ton
in DoR and DoI norms respectively. The manpower in thisreport (updated norms) is prepared as oper DoI norms and the manpower for respective individual
bar bending is calculated accordingly.
Justification:
This norms for the above item of work is as per the DoR norms regarding manpower for placining in possion and other activities required for gabion box at
site. The quantity of binding wire is calculated as required for Lacing of adjoining panels; bracing and lacing of adjoining boxes. The requirements for the
mechanically produced gabion crates shall be as per the specification provided in this report.
Page 15 of 49
Respective For Hill Area For Terai/Plain Area
Unskilled Skilled Unskilled Skilled
Clause of Labour Labour Labour Labour
S.No. Description Unit Materials and Tools/Equipment
Specifications
(personday) (personday) (personday) (personday)
45 17-1.4, 17- 5 Packing and filling of gabion crates with 1 m3
and 17- 6 rubble stones same as dry stone masonry
S.No. 38-A a)
i.e. Uncoursed dry rubble masonry 1.00m3 2.60 0.50 2.60 0.50 Transportation & Royalty
Break Down - rubble = 1.1 m3
- collection of rubble at quarry (refer 1.10m3 1.10 1.10
Annex II)
- dry masonry with rubble stone 1.00m3 1.50 0.50 1.50 0.50
Recommendation:
Replace the manpower provided for this item of work in existing norms by above.
Justification:
Filling of stone in the gabion crate is similar to that of dry stone masonry. So, the manpower provided for this iem of work is updated as per S.No 38-A a) of
existing norms.
Page 16 of 49
Work Norms
For Construction, Rehabilitation and Maintenance of Rural Roads
Maintenance of road works (New Item)
Resouces
Spec. Unskilled Skilled
Activity Materials / Royalties Tools/Equipment
Clause Description Unit Labour Labour
Nos.
No.
personday personday Type Unit Qty.
29.01 2902 Restoration of rain cuts in embankment slopes including Add 3% of labour cost for
watering and compaction etc. all complete lead 10m. m3 0.75 0.10 Suitable material m3 1.1
T&P
29.02 2903 Maintenance of earthen shoulders by making irregularities m2 0.20 0.02 Add 3% of labour cost for
even to the required level including watering and T&P
compaction etc. all complete lead 10m.
29.03 2904 Maintenance of gravel shoulders and gravel carriageway m2 0.30 0.03 Suitable gravel Add 3% of labour cost for
by repairing pot holes and making iregularities even to T&P
material m3 0.11
the required level including watering and compaction etc.
all complete lead 10m.
Page 17 of 49
Resouces
Spec. Unskilled Skilled
Activity Materials / Royalties Tools/Equipment
Clause Description Unit Labour Labour
Nos.
No.
personday personday Type Unit Qty.
29.04 2905 ii) Using cold premix material 100m2 10.56 0.26 MC 30 cutback Mixing plant = 1.1 hr
bitumen ltr 110.00
Emulsion ltr 572.00
aggregate 10mm m3 0.40 Wheel loader =0.31 hr
aggregate 6mm m3 1.30 Steel wheel roller = 2.2 hr
Diesel ltr 35.00
29.04 2905 ii) Using cold premix material 100m2 7.50 0.17 MC 30 cutback Mixing plant = 0.60 hr
bitumen ltr 110.00
Emulsion ltr 280.00 Wheel loader = 0.15 hr
aggregate 10mm m3 2.00 Steel wheel roller = 1.20 hr
aggregate 6mm m3 0.70 Add 3% of Labour Cost for
Diesel ltr 20.00 T & P
c) Deep Patching (More than 40mm) 100m2 Labour & materials of shallow patching to be increased according to the thickness of
base and sub base to be excavated and filled using the norms of related items.
d) Carriage way edge repair 100m2 Refer shallow patching or deep patching as applicable
Page 19 of 49
Resouces
Spec. Unskilled Skilled
Activity Materials / Royalties Tools/Equipment
Clause Description Unit Labour Labour
Nos.
No.
personday personday Type Unit Qty.
13.08.02 1301, Normal slurry mix 100m2 3.00 0.20 Aggregate m3 0.56 Mixer = 0.08 hr
1306 Emulsion ltr 139.00 Pneumatic Tyred
Cement kg 9.40 Roller = 0.55 hr
Water LS Add 3% of Labour Cost for
Diesel ltr 8.40 T & P
13.08.03 1301, Coarse slurry mix 100m2 3.00 0.20 Aggregate m3 0.67 Mixer = 0.09 hr
1306 Emulsion ltr 167.00 Pneumatic Tyred
Cement kg 11.30 Roller = 0.55 hr
Water LS Add 3% of Labour Cost for
Diesel ltr 8.40 T & P
13.05 1301, Maintenance with surface Dressing including cleaning, Same as norms of Surface Dressing
1303 brooming and rolling etc. all complete lead 10m. Patch
work
13.05.02 1301, Bitumen binder for surface dressing ltr 0.052 0.003 Bitumen 80/100 ltr 1.05 Boiler = 0.004 hr
1303 Kerosene ltr 0.10 Distributor = 0.004 hr
Diesel ltr 0.108 Air compresser = 0.004 hr
13.05.04 1301, Chipping for surface dressing Patch work t 0.21 0.001 Chips t 1.05 Chips spreader = 0.10 hr
1303 Diesel ltr 3.60 PN.Tyred Roller =0.20 hr
Add 3% of Labour Cost for
T&P
1301, Maintenance with Sand Seal including cleaning,
13.07
1305 brooming and rolling etc. all complete lead 10m.
Same as norms of Sand Seal 10 m2 0.14 0.10 Bitumen ltr 6.60 Boiler = 0.04 hr
Kerosene ltr 0.10 Roller = 0.04 hr
Diesel ltr 0.81 Sprayer = 0.04 hr
Fine aggregates m3 0.12
Page 20 of 49
Resouces
Spec. Unskilled Skilled
Activity Materials / Royalties Tools/Equipment
Clause Description Unit Labour Labour
Nos.
No.
personday personday Type Unit Qty.
29.09 2910 Repair of Brick shoulders / Foot paths
i) One layer Flat brick soling with sand filling in Joints 10m2 0.50 0.50 Brick nos 410
& bottom. Sand m3 0.20
ii) One layer brick soling on edge with sand filling in 10m2 0.80 0.80 Brick nos 750
joints and bottom. Sand m3 0.20
iii) One layer flat brick soling and jointing with 1:6 10m2 2.00 1.00 Brick nos 410
cement sand mortar.
Cement kg 50.00
Sand m3 0.20
Water ltr 30.00
iv) One layer brick soling on edge and jointing with 1:6 10m2 3.00 1.50 Brick nos 750
cement sand mortar.
Cement kg 72.50
Sand m3 0.30
Water ltr 40.00
Page 21 of 49
Norms for Recurrent Maintenance of Paved Road
Recommended Cycle
Surface Condition
Traffic (VPD)
Good → 0.0 -1.7 SDI Fair → 1.8 - 3.0 SDI Poor → 3.1 - 5.0 SDI
Low (<250) 1 2 Ad-hoc maintenance
Moderate ( 250 - 1500) 2 2 waiting
High > 1500 2 3 Rehabuilitation or Reconstruction
Page 22 of 49
Providing, laying and fixing of Geo-textile (filter fabrics)
New Item:
Unskilled Skilled
Respective Materials Tools/Equipment
Labour Labour
S.No. Clause of Description Unit
Specifications (personday) (personday)
New item Providing, laying and fixing of Geo- m2 0.0170 Geotextile = 1.20 m2
textile (filter fabrics), lead 30m
Recommendation:
New item of work to be use for laying of Geo-textile
Justification:
The norms is prepared from DoR Norms.
Unskilled Skilled
Respective Materials Tools/Equipment
Labour Labour
S.No. Clause of Description Unit
Specifications (personday) (personday)
Recommendation:
Use this norms for land slide clearance manually
Justification:
Prepared fron the DoR norms.
Page 23 of 49
Work Norms
For Construction, Rehabilitation and Maintenance of Rural Roads
Otta Seal (New Item)
Unskilled Skilled
Respective Labour Labour
S.No. Clause of Description Unit Materials
Specifications (personday) (personday)
Recommendation:
Use this norms for otta seal work as a new norms as apecified in the specification clause 4.9-2 b
Tools/Equipment
Boiler = 0.0014 hr
Air Compresser = 0.0014 hr
Boiler = 0.0014 hr
Air Compresser = 0.0014 hr
Boiler = 0.0014 hr
Air Compresser = 0.0014 hr
Tipper = 0.09 hr
Loader = 0.09 hr
Pneumatic Roller = 0.36 hr
Truck = 0.09 hr
Loader = 0.0014 hr
Transportation = 1 Kg
Work Norms
For Construction, Rehabilitation and Maintenance of Rural Roads
Recommendation & Justification
S.No as
Avtivity per Specification Description Recommendations
Norms Clause No.
Site 3 1-2 Dismantling of culverts, bridges,
Clearance pavements and other structures.
The operation covered are:
◦ dismantling
◦ excavation
◦ back filling
◦ stacking
◦ disposing
◦ handling and
◦ haulage up to a lead of 100m along the lead route.
Th activity includes safety and precaustions and incidentals.
Roadway New 2-1.3.3; Earth work excavation by heavy New Item of work;
and Drain Item 2-1.3.4; equipment using Recommended for Excavation
Excavation 2-1.3.6; of Roadway and foundation for
wheel loader of capacity 1.0m3
2-1.3.7; structures.
& wheel loader of capacity 1.5m3
2-1.3.8 wheel loader of capacity 2.0m3
Roadway New 2-1.3.3; New Item of work;
and Drain Item 2-1.3.4; Recommended for Excavation
Excavation 2-1.3.6; of Roadway and foundation for
S.No as 2-1.3.7; structures.
Avtivity per Specification
& Description Recommendations
Norms Clause No.
2-1.3.8
Hydraulic Excavator of capacity 0.35
m3
Hydraulic Excavator of capacity 0.63
m3
Hydraulic Excavator of capacity 0.80
m3
Hydraulic Excavator of capacity 1.32
m3
Otta Seal New 4-9 Otta seal surfacing, Bitumen Binder, & New Item of work;
Item Otta seal chips Recommended for Bituminous
Surfacing
Maintenanc New Repair of embankment slopes, Repair Recommended for Maintenance
e of road Item of Gravel and Bituminous surface of Road
works
Work Norms
r Construction, Rehabilitation and Maintenance of Rural Roads
Recommendation & Justification
Justifications
Brick work is carried out in mud mortar and cement mortar, similarly the
stone masonry in dry/mud mortared randam rubble and with cement
mortar. Likewise cement concrete work is either RCC or PCC. Hence,
dismantling of existing structure of above nature is also to be carried out
accordingly. The manpower shown in the changed items are as per the
Water bound macadom (WBM) and WBM with bituminous surfacing are
considered as flexible pavement and are treated as that of gravel/ boulder
mixed soil (hard soil). Whereas Cement concrete is a rigid pavenet and
treat as soft to hard rock according to its strength. Hence dismantling of
flexible and cement concrete pavement has to be dealt seperately. The
manpower shown in the changed items are as per the DoR Norms.
In DoLIDARs' existing Norms, this item of works does not exists. This
item of work is recommended as per the DoR norms.
In DoLIDARs' existing Norms, this item of works does not exists. This
item of work is recommended as per the DoR norms.
Hard soil to Hard rock does not contain unsuitable material hence
replacement is not required.
1/4 of dia. 1/2 of dia. 3/4 of dia. 1/4 of dia. 1/2 of dia. 3/4 of dia.
3 Clean culverts, inlets and outfalls, dia. 40cm row/wd 7 5 3 0.029 0.040 0.067
4 Clean culverts, inlets and outfalls, dia. 60cm row/wd 5 3 1 0.040 0.067 0.200
5 Clean culverts, inlets and outfalls, dia. 100cm row/wd 2 1 0.5 0.100 0.200 0.400
L=5m
L=5m
L=5m
With=5m
Remarks
Proposed work norms for Cobble pavement works
Respective
SN Clause of Description Unit Unskilled Skilled Materials/Royalties
Specifications
1 Production of cobblestones
A. Production of chisel dressed cubical
1 Cum
cobblestones
Royalties, local tax and tolls
Quarrying of rubble stones 1.8 Cum 3.5 Transport of materials from the quarry
by laborers or other means.
Breaking into required sizes 1.8 Cum 1.8 Rubble stones = 1.75 cum
Breaking into required sizes 1.5 Cum 1.5 Rubble stones = 1.5 cum
Notes:
1. Prevailing DoLIDAR work norms shall be used for other items of work associated with cobble pavement construction like preparation of subgrade, construction of ker
confinement, construction of subbase and laying of granular sand cushion.
Equipments/Tools
Hill Road 3 KM
Black top roads
For Monsoon period Supervisor Nos 0.17 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 2.50 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
For Dry season
Supervisor Nos 0.17 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.00 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
Tarai Roads 5 KM
Black top roads
For Monsoon period Supervisor Nos 0.25 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.50 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
For Dry season
Supervisor Nos 0.25 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.00 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
Norms for Routine Maintenance (DoR) of Roads
Resource
S. No Work Details Unit Labour Social Tools & Plants
Rank Unit Qty Type unit Qty Type
Routine Maintenance
Hill Road 2 KM
Gravel/Earthen Road
For Monsoon period Supervisor Nos 0.11 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.50 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
For Dry season
Supervisor Nos 0.11 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.00 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
Tarai Roads 5 KM
Gravel/Earthen Road
For Monsoon period Supervisor Nos 0.17 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.50 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
For Dry season
Supervisor Nos 0.17 ARMP Training Percent 1.70 Tools & plants
Length worker Nos 1.00 Insurance Percent 1.00 Feul
First aid Box Percent 0.30 Tools & plants
repair
Length of Bridge between 0 and 100 m 100 m Length worker No 0.50 Tools and Plants
Bridge length beyond 100 m for additional each
20 m 20 m Length worker No 0.05 Supervision
Repair of p/tools
Tools & Plants Remarks
unit Quantity
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
Tools & Plants Remarks
unit Qty
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
Percent 9.00
Percent 8.00
Percent 3.00
percent 5.00
percent 15.00
percent 3.00