Equipment

Month Description Excavation (Cu.M) Filling (Cu. M) Disposal (Cu.M)


Excavators/B
Tippers
reakers

Mar-15 0 0
Apr-15 22,686.93 0 0
May-15 11,867.22 0 0
Jun-15 12,240.00 0 0
Jul-15 24,346.21 0 0
Aug-15 10,433.25 0 0
Sep-15 22,966.88 0 0
Oct-15 44,122.98 0 0
Nov-15 50,497.79 0 0
Dec-15 44,884.39 0 0
Jan-16 38,607.55 0 0
Feb-16 55,000.00 0 0
Mar-16 5 3
Apr-16 850.00 12 8
May-16 24,000.00 All excavated 12 8
Jun-16 29,300.00 material send to 12 8
Jul-16 48,300.00 crusher area 12 8
Aug-16 71,000.00 13 9
Sep-16 731,866.81 55,000.00 12 8
Oct-16 58,000.00 12 8
Nov-16 39,500.00 12 8
Dec-16 28,200.00 13 10
Jan-17 39,700.00 13 10
Feb-17 42,150.00 13 10
Mar-17 46,300.00 13 10
Apr-17 60,023.00 50,273.00 30 18
May-17 54,490.00 40,978.00 28 16
Jun-17 14,460.00 31,294.00 11 10
Jul-17 18,001.00 48,118.00 19 12
Aug-17 21,697.00 37,288.00 15 12
Sep-17 6,964.00 52,370.00 17 16
Total earthworks
1,245,155.00 742,621.00
executed (Cu.M)
Total Quantity as
714,000.00 651,000.00
per BOQ
Total Quantity as
per IFC drawings
(Cu.M) 1,442,525.97 982,102.92