Sie sind auf Seite 1von 17

DETAILED BQ

RECORDING AN ESTIMATE OF MATER


ITEM
A
1
2
3
4
5
6
7
8
9
B
10
11
12
13
14
C
15
16
17
18
19
20
21
22
23

24
25
26
27
28

29
30
31
32
33
34

35
36
37
38
39

40
41
42
43
44
45
46
47
48

49
50
51
52
53

54
55
56
57
58
59
60
61
62

63
64
65
66
67
68
69
70
71
72

73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
87
88
89
90
91
92
93
94
95
96
97

98
99
100
101
102
103

104
105
106
107
108
109
110
111
112
DETAILED BQ
RECORDING AN ESTIMATE OF MATERIAL
Description Unit
STORE 10X15Ft
Iron sheets 2.5m No.
Iron sheets 3m No.
Poles (each 18ft) No.
Timber 3"x2" Ft
Timber2"x1" Ft
Windows 3"x3" No.
Door No.
Labour Item
Miscelenoius Items %
TOOLS
Wheel barrow No.
Matox No.
Shovel(spade) No.
Drum 200 Litres No.
Miscellenious items %
CONCRETE WATER TANK ( Depends on capacity required )
Cement Bags
Sand Tons
Ballast Tons
Stones 9" Ft
Labour Item
Miscellenoius Items %
FOUNDATION WORKS
EXCAVATION (The others depends on specific projects )
Top soil Cm
Pad foundation Cm
Trenches Cm
FOUDATION
Reinforcements (Y16) No.
Reinforcements (Y12) No.
Reinforcements (R8) No.
Labour Item
Miscellanious %
FORMWORK
6"x1" Ft
8"x1" Ft
2"x1" Ft
Props(18Ft) No.
Labour Item
Miscellenious Items %
FOUNDATION CONCRETE
Cement Bags
Sand Tons
Ballast Tons
Labour,Mixer,Vibrator Item
Miscellenious items %
FOUNDATION WALL
9" Stones Ft
Cement Bags
Sand Tons
Labour Item
Hardcore Lorries
Polythene paper G500 m
Insecticide Litres
Labour Item
Miscellenious items %
GROUND FLOOR SLAB (100mm thick)
Cement Bags
Sand Tons
Ballast Tons
Labour Item
Miscellenious items %
COLUMNS
Reinforcement Y16 Bars
Reinforcement Y12 Bars
Reinforcement R8 Bars
Labour Item
Cement Bags
Sand Tons
Ballast Tons
Labour, Vibrator Item
Miscellanious Items %
WALL
9" Stones Ft
6" Stones Ft
Dressing stones smooth Ft
Dressing stones rough Ft
Hoop iron Kg.
Labour Item
Cement Tons
Sand Tons
Labour Item
Miscellanious Items %
FIRST FLOOR SLAB
Timber 8"x1" Ft
Timber 6"X1" Ft
Timber 2"x1" Ft
Timber 3"x2" Ft
Props(18Ft) Ft
Labour Timber Item
Reinforcement Y16 Bars
Reinforcement Y12 Bars
Reinforcement R8 Bars
Labour Reinforcement Item
Cement Bags
Sand Tons
Ballast Tons
Labour first floor slab Item
Plumbing materials and labour item
Electrical Materials and Labour Item
STAIR
Timber 8"x1" Ft
Timber 3"x2" Ft
Labour formwoks
Cement Bags
Sand Tons
Ballast Tons
Reinforcement Y12 Bars
Reinforcement R8 Bars
Labour reinforcement Item
Labour , vibrator and mixer Item
Miscelenious items %
FIRST FLOOR WALL
9" Stones Ft
Stone dressing Ft
Cement Bags
Sand Tons
Labour walling Item
Miscelenious items %
COLUMNS
FORMWORK (re-use)
Reinforcement R8 Bars
Reinforcement Y16 Bars
Cement Bags
Sand Tons
Ballast Tons
Labour Reinforcement Item
Labour concrete Item
Miscellenious Items %
RINGBEAM
Formwork (most on site) Ft
Labour formwoks Item
Reinforcement Y16 Bars
Reinforcement Y12 Bars
Reinforcement R8 Bars
Cement Bags
Sand Tons
Ballast Tons
Miscellenoius Items %
GABLE WALL
9"Stones Ft
Cement Bags
Sand Tons
Ballast Tons
Labour,Mixer,Vibrator Item
Miscellanious Items %
ROOF (tiled)
Timber 6"x2" Ft
4"x2" Ft
2"x2" Ft
2"x1" Ft
Planed Fascial board 8"x1" Ft
Polythene paper G1000 M
Roof tiles No.
Ridge cover No.
Wood preservative(waste oil) Litres
Red Oxide Item
Labour Item
Miscelanious items %
SEPTIC TANK,CESSPOOL AND DRAINAGE
Excavate (Soft rock) cft
Walling 9" stones Ft
Cement Bags
Sand Tons
Ballast Tons
Reinforcement Y12 Bars
Y10 Bars
Formwork (6"x1") Ft
Formwork 3"x2" Ft
Labour drainage Item
Labour septic tank and cesspool Item
Miscellanious items %
FINISHES AND FITTINGS
Dismantling formwork Item
Steel door No.
Union lock No.
Door frames No.
Steel windows (3'x4') No.
Plumbing works Item
Plastering cement Bags
Sand Tons
Plaster labour Item
Flush doors No.
Glass (1sq ft) No.
Putty Kg.
Wardrobes No.
Paint emulsion Litres
Paint gloss Litres
Labour Painters Item
Tiles (6"x6") No.
White cement Kg.
Labour tiles Item
Miscellanoius items %
PRIME COST SUMS
Electricity supply Sum
Water connection Sum
SUMMARY
Page 1
Page 2
Page 3
Page 4
Page 5
TOTALS
IN WORDS………………………………………………………………………..

NB
1. The estimate should be prepared using structural and Architectural drawings

2. A quotation should be obtained from plumbing and electrical specialists

4. The costs of the following have not been included


-Fencing and gate
-Roads and car park
-preliminaries
-Overheads and
-Profit where applicable
TAILED BQ
E OF MATERIALS AND LABOUR
Quantity Rate Amount

n capacity required )
specific projects )
Provisional item
Provisional item

………………………..

ral and Architectural drawings

and electrical specialists


ABOUR
Remarks

Das könnte Ihnen auch gefallen