Francisco Sánchez Molada--- 09/09/201308:35:49--- ¿Podríais echarme un mano con esto? Gracias !

Best regards Francisco Sánchez Molada AG INGENIERIA

Ca

AG INGENIERIA
Francisco Sánchez Molada
09/09/2013 08:35
Ángel Martínez Quesada/Abener/Abengoa@Abengoa, Emilio Balado Leal/AG/Abengoa@Abengoa,
Para
Ángel Martínez Quesada/Abener/Abengoa@Abengoa, Emilio Balado Leal/AG/Abengoa@Abengoa,

cc

bcc

Asunto Rm: 0331-TEC-UDS-ING-1284 HVAC system documents comments

Best regards

Francisco Sánchez Molada

AG INGENIERIA
Campus Palmas Altas
C/ Energía Solar nª 1, Palmas Alta
Phone: +34954996771 (34596) Fax: +34955413374
francisco.sanchez@ag.abengoa.com
 Eco-Tip: Printing e-mails is usually a waste.
----- Remitido por Francisco Sánchez Molada/AG/Abengoa con fecha 09/09/2013 08:34 -----

ABEINSA EPC
Rafael Muriel Muñoz
08/09/2013 11:01

Para: Francisco Sánchez Molada/AG/Abengoa@Abengoa


Proyecto UTE Dead Sea Abeinsa EPC/AbeinsaEPC/Abengoa@ABENGOA, Cristina Chaza
Chimeno/AbeinsaEPC/Abengoa@Abengoa, Ignacio Catalan Sanchez/AbeinsaEPC/Abengoa@Abengoa,
Hugo Fanjul Pereza/AbeinsaEPC/Abengoa@ABENGOA, Antonio Vidal
cc:
Rodríguez/AbeinsaEPC/Abengoa@Abengoa, Enrique Araujo Fernandez/AG/Abengoa@Abengoa, Iván
Fuertes Pérez/AG/Abengoa@Abengoa, Edén Anselmo García Herrero/AG/Abengoa@Abengoa, Nieves
Jurado Ibáñez/AG/Abengoa@Abengoa
Asunto: 0331-TEC-UDS-ING-1284 HVAC system documents comments
Dear Francisco,

UDS has several comments related to the document "0331-CAL-ING-014-010-0001


R0b HVAC Calculation report":

2.1 HVAC system: In the 3rd and 5th paragraphs, please update the number of pumps
to the final number chosen. At this moment, it is mentioned four pumps for the
condensation pumps and others four for the primary circuit.

8.2 Operating conditions: Some values are not according to those shown in section 8.3
and in HDDs. I.e. HVAC Condensation pump suction should be 0,7 barg, HVAC
Secondary pump discharge (electrical building) should be 4,7 barg or HVAC Secondary
pump discharge (office & WTP buildings) value that should be 4,84 barg.
The documents below are approved by UDS:

0331-HDD-ING-014-062-0001 R0b HVAC Primary & Secondary Circuits Pumps Data


sheets.
0331-HDD-ING-014-062-0002 R0b HVAC Condensation Circuit Pumps_Data Sheets.

Atentamente / Yours sincerely,

Rafael Muriel Muñoz

ABEINSA EPC
DSW Combined Heat & Power Plant
Industrial Park Omer
Omarim 9, Omer Industrial Park, Israel
Cell: +972 543980189
rafael.murielmunoz@abeinsaepc.abengoa.com