Dilip Buildcon Ltd (DBL)

2 Laning with Paved Shoulder from Km 30+800 to


Km 70+800 and 2 Laning without Paved Shoulder
from Km 70+800 to Karnataka/Goa Border (km
84+120) of NH-4A in the State of Karnataka on
EPC mode

Location MNB 53+504 66+230


Span Size 3X18 3X10
Type of Construction RC RC
Layout/ Excavation/level 05/10/18 01/11/18
PCC
A1 10/10/18 06/11/18
A2 15/10/18 11/11/18
P1 19/10/18 15/11/18
P2 23/10/18 19/11/18
Raft
A1 15/10/18 12/11/18
A2 20/10/18 18/11/18
P1 24/10/18 20/11/18
P2 28/10/18 25/11/18
Wall
A1 1st Lift 18/10/18 16/11/18
A1-2nd Lift 21/10/18 20/11/18
A1-3rd Lift 24/10/18 24/11/18
A1 Final Lift 27/10/18 28/11/18
A2 1st Lift 23/10/18 21/11/18
A2-2nd Lift 26/10/18 25/11/18
A2-3rd Lift 29/10/18 29/11/18
A2 Final Lift 01/11/18 03/12/18

P1 1st lift 27/10/18 24/11/18


P1 2nd lift 30/10/18 27/11/18
P1 3rd lift & Final Lift 02/11/18 30/11/18
P2 1st Lift 31/10/18 29/11/18
P2 2nd lift 03/11/18 02/12/18
P2 3rd lift & Final Lift 06/11/18 06/12/18

ABT-CAP & PIER-CAP


A1 31/10/18 02/12/18
A2 05/11/18 07/12/18
P1 10/11/18 08/12/18
P2 14/11/18 14/12/18
PEDESTAL
A1-A2 07/11/18 09/12/18
P1-P2 16/11/18 16/12/18
RCC Girder casting Start 10/10/18
RCC Girder casting End 24/11/18
RCC GIRDER LAUNCHING
A1-P1 08/12/18
P1-P2 12/12/18
P2-A2 15/12/18

DIAPHARAM
A1-P1 10/12/18
P1-P2 14/12/18
P2-A2 17/12/18
DECK SLAB
A1-P1 22/12/18 19/12/18
P1-P2 27/12/18 26/12/18
P2-A2 01/01/19 05/01/19
DIRT WALL/ Bracket
A1 25/12/18 22/12/18
A2 04/01/19 08/01/19
MISCELLANEOUS WORK
Crash Barrier 10/01/19 14/01/19
APPROACH SLAB 15/01/19 19/01/19