CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
An assembly line is built after the engineering economic analysis has shown that the antic-
ipated product demand will generate profits. A new motor, heat exchanger, or filtration
unit is installed after analysis has shown that future cost savings will economically justify
cur-rent costs. A new road, school, or other public facility is built after analysis has shown
that the future demand and benefits justify the present cost to build. However, future
perfor-mance of the assembly line, motor, and so on is uncertain, and demand for the
product or public facility is more uncertain.
Engineering economic analysis is used to evaluate projects with long-term
consequences when the time value of money matters. Thus, it must concern itself with
future consequences; but describing the future accurately is not easy. In this chapter we
consider the problem of evaluating the future. The easiest way to begin is to make a careful
esti-mate. Then we examine the possibility of predicting a range of possible outcomes.
Finally, we consider what happens when the probabilities of the various outcomes are
known or may be estimated. We will show that the tools of probability are quite useful for
economic decision making.
EXAMPLE 10–1
Two alternatives are being considered. The best estimates for the various consequences are as
follows:
A B
Cost $1000 $2000
Net annual benefit 150 250
End-of-useful-life salvage value 100 400
Useful life, in years 10 10
If interest is 31/2%, which alternative has the better net present worth (NPW)?
Estimates and Their Use in Economic Analysis
337
SOLUTION
Alternative A
=− + 1 + 1 =− − ∗
NPW 1000 150( P/A, 3 /2%, 10) 100( P/F, 3 /2%, 10) or 1000 PV(i, n, A, F)
Alternative B
1 1
NPW = −2000 + 250( P/ A, 3 /2%, 10) + 400( P/ F, 3 /2%, 10) or = −2000 − P V (i, n, A, F)
SOLUTION
Revised B
1 1
NPW = −2000 + 250( P/ A, 3 /2%, 10) + 300( P/ F, 3 /2%, 10) or = −2000 − P V (i, n, A, F)
= −2000 + 250(8.317) + 300(0.7089) = −2000 − P V (3.5%, 250, 300)
= −2000 + 2079 + 213 = −2000 − (−2291.8)
= +$292 = $291.8
→ A is now the preferred alternative.
Example 10-1 shows that the change in the salvage value of Alternative B actually results
in a change of preferred alternative. Thus, a more thorough analysis of Example 10-1
would consider (1) which values are uncertain, (2) whether the uncertainty is ±5% or −50
to +80%, and (3) which uncertain values lead to different decisions. A more thorough anal-
ysis, which is done with the tools of this chapter, determines which decision is better over
the range of possibilities. Explicitly considering uncertainty lets us make better decisions.
The tool of breakeven analysis is illustrated in Example 10-2.
CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
EXAMPLE 10–2
Use the data of Example 10-1 to compute the sensitivity of the decision to the Alt. B salvage
value by computing the breakeven value. For Alt. A, NPW = +319. For breakeven between the
alternatives,
NPWA = NPWB
1 1
+319 = −2000 + 250( P/ A, 3 /2%, 10) + Salvage valueB ( P/ F, 3 /2%, 10)
= −2000 + 250(8.317) + Salvage valueB (0.7089) or = −2319 + 250 + Salvage value
PV PMT FV
= F V (i, n, A, P)
= F V (3.5%, 10, 250, −2319)
= $338.3
At the breakeven point
319 + 2000 − 2079 240
Salvage valueB =
0.7089 = 0.7089 = $339
When Alt. B salvage value >$339, B is preferred; when <$339, A is preferred.
Breakeven analysis, as shown in Example 10-2, is one means of examining the impact
of the variability of some estimate on the outcome. It helps by answering the question,
How much variability can a parameter have before the decision will be affected? While
the preferred decision depends on whether the salvage value is above or below the
breakeven value, the economic difference between the alternatives is small when the
salvage value is “close” to breakeven. Breakeven analysis does not solve the basic problem
of how to take the inherent variability of parameters into account in an economic analysis.
This will be considered next.
A RANGE OF ESTIMATES
It is usually more realistic to describe parameters with a range of possible values, rather
than a single value. A range could include an optimistic estimate, the most likely estimate,
and a pessimistic estimate. Then, the economic analysis can determine whether the
decision is sensitive to the range of projected values.
EXAMPLE 10–3
A firm is considering an investment. The most likely data values were found during the feasibility
study. Analyzing past data of similar projects shows that optimistic values for the first cost and the
annual benefit are 5% better than most likely values. Pessimistic values are 15% worse.
The firm’s most experienced project analyst has estimated the values for the useful life and
salvage value.
A Range of Estimates 339
Compute the rate of return for each estimate. If a 10% before-tax minimum attractive rate of
return is required, is the investment justified under all three estimates? If it is justified only under
some estimates, how can these results be used?
SOLUTION
Optimistic Estimate
From the calculations we conclude that the rate of return for this investment is most likely to
be 15.1%, but might range from 3.9% to 19.8%. The investment meets the 10% MARR criterion
for two of the estimates. These estimates can be considered to be scenarios of what may happen
with this project. Since one scenario indicates that the project is not attractive, we need to have
a method of weighting the scenarios or considering how likely each is.
Example 10-3 made separate calculations for the sets of optimistic, most likely, and
pessimistic values. The range of scenarios is useful. However, if there are more than a few
uncertain variables, it is unlikely that all will prove to be optimistic (best case) or most
likely or pessimistic (worst case). It is more likely that many parameters are the most likely
values, while some are optimistic and some are pessimistic.
This can be addressed by using Equation 10-1 to calculate average or mean values for each
parameter. Equation 10-1 puts four times the weight on the most likely value than on
CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
the other two. This equation has a long history of use in project management to estimate
activity completion times. It is an approximation with the beta distribution.
Mean value Optimistic value + 4(Most likely value) + Pessimistic value (10-1)
= 6
EXAMPLE 10–4
Solve Example 10-3 by using Equation 10-1. Compute the resulting mean rate of return.
SOLUTION
Compute the mean for each parameter:
Mean cost = [950 + 4(1000) + 1150]/6 = $1016.7
Mean net annual benefit = [210 + 4(200) + 170]/6 = $196.7
Mean useful life = [12 + 4(10) + 8]/6 = 10.0
Mean salvage life = 100/6 = $16.7
Example 10-3 gave a most likely rate of return (15.1%) that differed from the mean
rate of return (14.3%) computed in Example 10-4. These values are different because the
former is based exclusively on the most likely values and the latter takes into account the
variability of the parameters.
In examining the data, we see that the pessimistic values are further away from the
most likely values than are the optimistic values. This is a common occurrence. For
example, a savings of 10–20% may be the maximum possible, but a cost overrun can be
50%, 100%, or even more. This causes the resulting weighted mean values to be less
favorable than the most likely values. As a result, the mean rate of return, in this example,
is less than the rate of return based on the most likely values.
PROBABILITY
We all have used probabilities. For example, what is the probability of getting a “head” when
flipping a coin? Using a model that assumes that the coin is fair, both the head and tail outcomes
1
occur with a probability of 50%, or /2. This probability is the likelihood of
Probability 341
an event in a single trial. It also describes the long-run relative frequency of getting heads
in many trials (out of 50 coin flips, we expect to average 25 heads).
Probabilities can also be based on data, expert judgment, or a combination of both.
Past data on weather and climate, on project completion times and costs, and on highway
traffic are combined with expert judgment to forecast future events. These examples can
be important in engineering economy.
Another example based on long-run relative frequency is the PW of a flood-protection
dam that depends on the probabilities of different-sized floods over many years. This
would be based on data from past floods and would include many years of observation.
An example of a single event that may be estimated by expert judgment is the probabil-ity
of a successful outcome for a research and development project, which will determine its
PW.
All the data in an engineering economy problem may have some level of uncertainty.
However, small uncertainties may be ignored, so that more analysis can be done with the
large uncertainties. For example, the price of an off-the-shelf piece of equipment may vary
by only ±5%. The price could be treated as a known or deterministic value. On the other
hand, demand over the next 20 years will have more uncertainty. Demand should be ana-
lyzed as a random or stochastic variable. We should establish probabilities for different
values of demand.
There are also logical or mathematical rules for probabilities. If an outcome can never
happen, then the probability is 0. If an outcome will certainly happen, then the probability is 1,
or 100%. This means that probabilities cannot be negative or greater than 1; in other words,
they must be within the interval [0, 1], as indicated shortly in Equation 10-2.
Probabilities are defined so that the sum of probabilities for all possible outcomes is
1 or 100% (Equation 10-3). Summing the probability of 0.5 for a head and 0.5 for a tail
leads to a total of 1 for the possible outcomes from the coin flip. An exploration well drilled
in a potential oil field will have three outcomes (dry hole, noncommercial quantities, or
commercial quantities) whose probabilities will sum to one.
Equations 10-2 and 10-3 can be used to check that probabilities are valid. If the
probabilities for all but one outcome are known, the equations can be used to find the
unknown probability for that outcome (see Example 10-5).
0 ≤ Probability ≤ 1 (10-2)
j=K
P(outcome j ) = 1, where there are K outcomes (10-3)
1 to
EXAMPLE 10–5
What are the probability distributions for the annual benefit and life for the following project?
The annual benefit’s most likely value is $8000 with a probability of 60%. There is a 30%
probability that it will be $5000, and the highest value that is likely $10,000. A life of 6 years is
twice as likely as a life of 9 years.
SOLUTION
For the annual benefit, probabilities are given for only two of the possible outcomes. The third
value is found from the fact that the probabilities for the three outcomes must sum to 1 (Equation
10-3).
0.5
Probability
0.4
0.3
0.2
0.1
0
$0 $5,000 $8,000 $10,000
Annual Benefit
The probability distribution for the life is P(6) = 66.7% and P(9) = 33.3%.
Joint Probability Distributions 343
EXAMPLE 10–6
The project described in Example 10-5 has a first cost of $25,000. The firm uses an interest rate
of 10%. Assume that the probability distributions for annual benefit and life are unrelated or
statistically independent. Calculate the probability distribution for the PW.
SOLUTION
Since there are three outcomes for the annual benefit and two outcomes for the life, there are six
combinations. The first four columns of the following table show the six combinations of life
and annual benefit. The probabilities in columns 2 and 4 are multiplied to calculate the joint
probabilities in column 5. For example, the probability of a low annual benefit and a short life is
0.3 × 2/3, which equals 0.2 or 20%.
CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
The PW values include the $25,000 first cost and the results of each pair of annual benefit
and life. For example, the PW for the combination of high benefit and long life is
PW$10,000,9 = −25,000 + 10,000( P/ A, 10%, 9) = −25,000 + 10,000(5.759) = $32,590
Annual Joint
Benefit Probability Life (years) Probability Probability PW
100.0%
Figure 10-2 shows the probabilities for the PW in the form of a histogram for relative
frequency distribution, or probability distribution function.
30
Probability (%)
20
10
0
$3,224 0 $3,795 $9,842 $18,553 $21,072 $32,590
Present Worth
This probability distribution function shows that there is a 20% chance of having a negative
PW. It also shows that there is a small (3.3%) chance of the PW being $32,590. The three values
used to describe possible annual benefits for the project and the two values for life have been
combined to describe the uncertainty in the project’s PW.
Some problems, such as Examples 10-3 and 10-4, have so many variables or different
outcomes that constructing the joint probability distribution is arithmetically burdensome. If
the values in Equation 10-1 are treated as a discrete probability distribution function, the
probabilities are 1/6, 2/3, 1/6. With an optimistic, most likely, and pessimistic outcome for each
4
of 4 variables, there are 3 = 81 combinations. In Examples 10-3 and 10-4, the salvage value
has only two distinct values, so there are still 3×3×3×2 = 54 combinations.
When the problem is important enough, the effort to construct the joint probability dis-
tribution is worthwhile. It gives the analyst and the decision maker a better understanding of
what may happen. It is also needed to calculate measures of a project’s risk. While spread-
sheets can automate the arithmetic, simulation (described at the end of the chapter) can be a
better choice when there are a large number of variables and combinations.
EXPECTED VALUE
For any probability distribution we can compute the expected value (EV) or weighted
arith-metic average (mean). To calculate the EV, each outcome is weighted by its
probability, and the results are summed. This is NOT the simple average or unweighted
mean. When the class average on a test is computed, this is an unweighted mean. Each
student’s test has the same weight. This simple “average” is the one that is shown by the
button x¯ on many calculators.
The expected value is a weighted average, like a student’s grade point average (GPA).
To calculate a GPA, the grade in each class is weighted by the number of credits. For the
expected value of a probability distribution, the weights are the probabilities.
This is described in Equation 10-5. We saw in Example 10-4, that these expected
values can be used to compute a rate of return. They can also be used to calculate a present
worth as in Example 10-7.
EXAMPLE 10–7
The first cost of the project in Example 10-5 is $25,000. Use the expected values for annual
benefits and life to estimate the present worth. Use an interest rate of 10%.
SOLUTION
[Note: This is the present worth of the expected values, PW(EV), not the expected value of the
present worth, EV(PW). It is an easy value to calculate that approximates the EV(PW), which
will be computed from the joint probability distribution found in Example 10-6.]
CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
Example 10-7 is a simple way to approximate the project’s expected PW. But the true
expected value of the PW is somewhat different. To find it, we must use the joint
probability distribution for benefit and life, and the resulting probability distribution
function for PW that was derived in Example 10-6. Example 10-8 shows the expected
value of the PW or the EV(PW).
EXAMPLE 10–8
Use the probability distribution function of the PW that was derived in Example 10–6 to
calculate the EV(PW). Does this indicate an attractive project?
SOLUTION
The table from Example 10-6 can be reused with one additional column for the weighted values
of the PW (= PW × probability). Then, the expected value of the PW is calculated by summing
the column of present worth values that have been weighted by their probabilities.
Annual Life Joint PW×Joint
Benefit Probability (years) Probability Probability PW Probability
In Examples 10-7 and 10-8, the question was whether the project had a positive PW. With
two or more alternatives, the criterion would have been to maximize the PW. With equivalent
uniform annual costs (EUACs) the goal is to minimize the EUAC. Example 10-9 uses the
criterion of minimizing the EV of the EUAC to choose the best height for a dam.
EXAMPLE 10–9
A dam is being considered to reduce river flooding. But if a dam is built, what height should it be?
Increasing the dam’s height will (1) reduce a flood’s probability, (2) reduce the damage when
Economic Decision Trees
347
floods occur, and (3) cost more. Which dam height minimizes the expected total annual cost?
The state uses an interest rate of 5% for flood protection projects, and all the dams should last
50 years.
Dam
Height (ft) First Cost
No dam $ 0
20 700,000
800,000
900,000
SOLUTION
The easiest way to solve this problem is to choose the dam height with the lowest equivalent
uniform annual cost (EUAC). Calculating the EUAC of the first cost requires multiplying the
first cost by ( A/ P, 5%, 50). For example, for the dam 20 ft high, this is 700,000( A/ P, 5%, 50)
= $38,344.
Calculating the annual expected flood damage cost for each alternative is simplified because
the term for the P(no flood) is zero, because the damages for no flood are $0. Thus we need to
calculate only the term for flooding. This is done by multiplying the P(flood) times the dam-
ages if a flood happens. For example, the expected annual flood damage cost with no levee is
0.25 × $800,000, or $200,000.
Then the EUAC of the first cost and the expected annual flood damage are added together to
find the total EUAC for each height. The 30 ft dam is somewhat cheaper than the 40 ft dam.
The following symbols are used to model decisions with decision trees:
D
1
…
DX
p C1
1
p
…
2 C2 : Represents a probabilistic (chance) event. Each pos-
Chance node
py
CY
sible outcome (C1, C2, . . . , CY ) has a probability ( p1, p2, . . . , py)
associated with it.
Outcome node : Shows result for a particular path through the decision tree.
Pruned branch : The double hash mark indicates that a branch has been pruned
because another branch has been chosen. This can happen only at decision nodes,
not at chance nodes. The term “pruned” is chosen to correspond to the gardener’s
practice of trimming or pruning off branches to make a tree or bush healthier.
Figure 10-3 illustrates how decision nodes , chance nodes , and outcome
nodes can be used to describe a problem’s structure. Details such as the probabili-
ties and costs can be added on the branches that link the nodes. With the branches from
decision and chance nodes, the model becomes a decision tree.
Figure 10-3 illustrates that decision trees describe the problem by starting at the deci-
sion that must be made and then adding chance and decision nodes in the proper logical
sequence. Thus describing the problem starts at the first step and goes forward in time with
sequences of decision and chance nodes.
To make the decision, calculations begin with the final nodes in the tree. Since they
are the final nodes, enough information is available to evaluate them. At decision nodes
the criterion is either to maximize PW or to minimize EUAC. At chance nodes an expected
value for PW or EUAC is calculated.
Once all nodes that branch from a node have been evaluated, the originating node can
be evaluated. If the originating node is a decision node, choose the branch with the best
PW or EUAC and place that value in the node. If the originating node is a chance node,
calcu-late the expected value and place that value in the node. This process “rolls back”
values from the terminal nodes in the tree to the initial decision. Example 10-10 illustrates
this process.
Economic Decision Trees 349
EXAMPLE 10–10
What decision should be made on the new product summarized in Figure 10-3? What is the expected
value of the product’s PW? The firm uses an interest rate of 10% to evaluate projects. If the product
is terminated after one year, the capital equipment has a salvage value of $550,000 for use with other
new products. If the equipment is used for 8 years, the salvage value is $0.
7: Net Revenue
$0
Terminate
4: Net Revenue
Year 1 $100K
Continue
Volume0 .3 8: Revenue
Low P
$100K/year
Medium
2: Volume for Volume 5: Net Revenue
…
New Product P0.6 Year 1 $200K Year 2 n
High1
0
$1M
.
9: Net Revenue
P V
olume
Yes
cos t
$600K/year
Firs t
Continue
No 10: Net Revenue
$400K/year
3: $0
t 0 t 1 t 2, …,
FIGURE 10–3 Economic decision tree for new product.
SOLUTION
Evaluating decision trees is done by starting with the end outcome nodes and the decisions that
lead to them. In this case the decisions are whether to terminate after 1 year if sales volume is
low and whether to expand after 1 year if sales volume is high.
The decision to terminate the product depends on which is more valuable, the equipment’s
salvage value of $550,000 or the revenue of $100,000 per year for 7 more years. The worth
(PW1) of the salvage value is $550,000. The worth (PW 1) of the revenue stream at the end of
Year 1 shown in node 8 is
CHAPTER 10: UNCERTAINTY IN FUTURE EVENTS
Thus, terminating the product and using the equipment for other products is better. We enter the two
“present worth” values at the end of Year 1 in nodes 7 and 8. We make the arc to node 7 bold to
indicate that it is our preferred choice at node 4. We use a double hash mark to show that we’re
pruning the arc to node 8 to indicate that it has been rejected as an inferior choice at node 4.
The decision to expand at node 6 could be based on whether the $800,000 first cost for expan-
sion can be justified based on increasing annual revenues for 7 years by $200,000 per year.
However, this is difficult to show on the tree. It is easier to calculate the “present worth” values
at the end of Year 1 for each of the two choices. The worth (PW 1) of node 9 (expand) is
7: Net Revenue
Terminate
$0
PW1 $550,000
Net Revenue
Year 1 $100K
PW1 $486,800
Continue
Volume0.3
Low P
8: Revenue
$100K/year
Medium
2: Volume for Volume 5: Net Revenue
…
New Product P0.3 Year 1 $200K Year 2 n
High1
0
$1M
.
9: Net Revenue
P
Yes
Volume $600K/year
cos t
Build New
6: Net Revenue First cost $800K
Product
Year 1 $400K
Continue PW 1 $1,947,200
No 10: Net Revenue
$400K/year
3: $0
t 0 t 1 t 2, …,
FIGURE 10–4 Partially solved decision tree for new product.
Economic Decision Trees 351
This is $173,600 less than the expansion node, so the expansion should happen if volume is high.
Figure 10-4 summarizes what we know at this stage of the process.
7: Net Revenue
$0
Medium PW $1,067,000
2: Volume for Volume 5: Net Revenue
EV $1,046,640 …
New Product P0.6 Year 1 $200K Year 2 n
High1
0
$1M
.
9: Net Revenue
P V
olume $600K/year
Yes
Expand
cos t
PW$46,640 PW1$2,120,800
PW $2,291,660
Firs t
3: $0
t 0 t 1 t 2, …,
FIGURE 10–5 Solved decision tree for new product.
EXAMPLE 10–11
Consider the economic evaluation of collision and comprehensive (fire, theft, etc.) insurance for
a car. This insurance is typically required by lenders, but once the car has been paid for, this
insurance is not required. (Liability insurance is a legal requirement.)
$0
Accident
No
.9
0
$800 03
Totaled
Insurance
Buy
$500
$0
Self-
Insure
Accident
No
.9
0
0.07 Small Accident
$300
0 .
03
Totaled
$13,000
FIGURE 10–6 Decision tree for buying auto collision insurance.
Figure 10-6 begins with a decision node with two alternatives for the next year. Insurance
will cost $800 per year with a $500 deductible if a loss occurs. The other option is to self-insure,
which means to go without buying collision and comprehensive insurance. Then if a loss occurs,
the owner must replace the vehicle with money from savings or a loan, or do without a vehicle
until the owner can afford to replace it.
R
i
s
k
3
5
3
Three accident severities are used to represent the range of possibilities: a 90% chance
of no accident, a 7% chance of a small accident (at a cost of $300, which is less than the
deductible), and a 3% chance of totaling the $13,000 vehicle. Since our driving habits are
likely to be the same with and without insurance, the accident probabilities are the same
for both chance nodes.
Even though this is a text on engineering economy, we have simplified the
problem and ignored the difference in timing of the cash flows. Insurance payments
are made at the beginning of the covered period, and accident costs occur during the
covered period. Since car insurance is usually paid semiannually, the results of the
economic analysis are not changed significantly by the simplification. We focus on
the new concepts of expected value, economic decision trees, and risk.
What are the expected values for each alternative, and what decision is recommended?
SOLUTION
The expected values are computed by using Equation 10-5. If insured, the maximum
cost equals the deductible of $500. If self-insured, the cost is the cost of the accident.